{"id":477505,"url":"http://info.mzalendo.com/api/v0.1/hansard/entries/477505/?format=json","text_counter":45,"type":"speech","speaker_name":"Hon. Kamanda","speaker_title":"","speaker":{"id":221,"legal_name":"Maina Kamanda","slug":"maina-kamanda"},"content":"Kshs656, 510,497. The earth works and drainage structures are complete. The progress was 49.83 per cent as at June, 2014 against a lapsed period of 29 months. (d) over the last three financial years, the project has not had adequate funding as indicated in 2011/2012. The project was given Kshs85,000,000 in 2012/2013, Kshs53,469,660 in 2013/2014 and Kshs.122,000,000. The project has already now taken a total of Kshs260,469,660. At the beginning of the last financial year, there was no budgetary allocation. An allocation of Kshs122,000,000 in the last financial year 2013/2014 to that road was only received at the supplementary budget that we passed the other day and the remaining work is planned to be completed this financial year over a period of 6-12 months, depending on the weather of that particular place."}