{"id":49105,"url":"http://info.mzalendo.com/api/v0.1/hansard/entries/49105/?format=json","text_counter":19,"type":"other","speaker_name":"","speaker_title":"","speaker":null,"content":"Mr. Speaker, Sir, I beg to reply. (a) I am not aware that the contractor on Road B5 has moved out. Road B5 is the Nakuru-Nyahururu Road. However, I am aware that in April, 2011 there was a breakdown of the contractorâs asphalt plant which slowed down the works, mainly pothole-patching. (b)The asphalt plant has now been repaired and pothole-patching has commenced. It is expected that the works will be completed by 17th August, 2011. It was a six-month contract."}