{"id":97001,"url":"http://info.mzalendo.com/api/v0.1/hansard/entries/97001/?format=json","text_counter":165,"type":"speech","speaker_name":"Mr. Obure","speaker_title":"","speaker":{"id":118,"legal_name":"Christopher Mogere Obure","slug":"christopher-obure"},"content":"Mr. Deputy Speaker, Sir, this was not the only time. The initial cost revision was carried out in 1994 raising the contractual amount from a figure of Kshs35,900,000 to a figure of Kshs201,356,464. Then there was a subsequent revision which included a justification for additional works by a further Kshs93 million."}