"speaker_name": "The Auditor-General",
"speaker_title": "",
"speaker": null,
"content": "(Dr.) Edward Ouko): The title is “Delay in completion of non- motorized facility of Kshs48,744,467,055.” “During the financial period under review the Nyeri County Government undertook construction of Non-motorized Facility (NMT) in Nyeri Town at a cost of Kshs48,744,467.55. The engineer had estimated the cost of facility to be Kshs38,638,342, therefore, resulting in a variance of Kshs10,106,125.55 or 26 per cent above the estimated cost. The excess variation would have necessitated a review of the tender before awarding was done. The construction work was also behind schedule as it was planned to be completed on 27th June, 2014. At the time of the audit in August 2014, this work was still ongoing at about 50 per cent complete. In the circumstances, it could not, therefore, be confirmed if the public got value for money from the construction of this building by the county government.”"
}