"speaker_name": "Eng. M.M. Mahamud",
"speaker_title": "The Assistant Minister for Energy",
"speaker": {
"id": 373,
"legal_name": "Mohammed Maalim Mahamud",
"slug": "mohammed-mahamud"
},
"content": " Mr. Speaker, Sir, I beg to reply. (a) The power supply from Brigidia through Tongaren to Lukhuna in Kimilili Constituency is being undertaken through the Spanish Phase II Rural Electrification Project. There was a delay in the approval process of the Spanish credit which also caused a delay in the supply of power to Lukhuna. However, work is currently in progress and power supply to Lukhuna is expected to be complete by October, 2010. (b) The Ministry will monitor the work progress to ensure implementation and connection of power supply by October, 2010. (c) The construction of the Naitiri/Mbakalo Project is in progress and it is expected to be complete by July, 2010. The delay has been due to the use of concrete poles which take a lot of time and care to erect, to avoid damage."
}