GET /api/v0.1/hansard/entries/117085/?format=api
HTTP 200 OK
Allow: GET, PUT, PATCH, DELETE, HEAD, OPTIONS
Content-Type: application/json
Vary: Accept

{
    "id": 117085,
    "url": "https://info.mzalendo.com/api/v0.1/hansard/entries/117085/?format=api",
    "text_counter": 181,
    "type": "speech",
    "speaker_name": "Mr. Keter",
    "speaker_title": "The Assistant Minister for Energy",
    "speaker": {
        "id": 169,
        "legal_name": "Charles Cheruiyot Keter",
        "slug": "charles-keter"
    },
    "content": " Mr. Speaker, Sir, I beg to reply. (a) There has been a delay in completing Chemalal- Kapset and Cheptabach- Chemelet power lines as a result of some challenges encountered by the contractor in procuring imported materials. However, these lines are complete, except for some defects noted during the inspection which are currently being rectified. But I want to say that as per now this has been done. On 29th October, they energised the lines and two transformers were placed. (b) Chemalal-Kapset and Cheptabach power lines will be fully completed and energised by mid of this month. Otherwise, as I am talking now, these lines are complete. The project for last year cuts across all the constituencies, but we have a problem in procuring transformers. You will see most of the transformers being installed beginning mid of this month. We have a target by January next year, all last years projects will be completed. We have already started projects for this Financial Year, 2009/2010. However, there are some Members who have not responded to letters from Rural Electrification Authority (REA) and I wish to remind them to do so, because already these projects are ongoing."
}