    "id": 1183394,
    "url": "https://info.mzalendo.com/api/v0.1/hansard/entries/1183394/?format=api",
    "text_counter": 56,
    "type": "speech",
    "speaker_name": "Baringo North, UDA",
    "speaker_title": "Hon. Joseph Makilap",
    "speaker": null,
    "content": "On 29th January 2010, KPLC entered into a contract with LTWP through a power purchase agreement to finance, design, procure, construct, install, test, commission, operate and maintain the power plant and sell the net electrical output exclusively to KPLC in order to supply power from Loiyangalani in Turkana County to Suswa sub-station, Kenya’s main power interchange, for interconnection to the national grid. However, over ten years later, the said power is yet to be supplied despite payment of over Ksh17 billion and provision of other infrastructure having been made."
}