    "content": "The contract sum for the proposed installation of five electric powered high mast flood lighting structures in various informal settlements in Kitui County was Kshs18,599,150. The contract period was 28 weeks plus a six-month defect liability period. The project officially commenced on 3rd September, 2020 and was completed on 18th March, 2021. Certificate of practical completion was issued on 15th December, 2021 and a certificate of making good defects was issued on 15th June, 2022."
}