    "id": 1287060,
    "url": "https://info.mzalendo.com/api/v0.1/hansard/entries/1287060/?format=api",
    "text_counter": 285,
    "type": "speech",
    "speaker_name": "Hon. Chirchir",
    "speaker_title": "The Cabinet Secretary for Energy and Petroleum",
    "speaker": null,
    "content": "the status of compensation by Kenya Electricity Transmission Company (KETRACO) to landowners affected by construction of UMMA University in Namanga, UMMA University in Konza and Emali-Loitoktok electricity lines. The current compensation status of the two lines is as follows- For the Kenya-Tanzania-Isinya-Namanga transmission line, the project affected persons compensation status is as shown in the table, where with the 502 are project affected persons and 297 have been fully compensated; which represents 59 per cent."
}