    "content": "Sorry, Hon. Temporary Speaker. The Company operates under Section 117 of the Energy Act that provides that a person who wishes to carry out generation, exportation, importation, transmission, distribution, and retail supply of electricity must apply for a license, as the case may be, to the Authority in accordance with the provisions of the Act. KUDURA Power East Africa Limited was granted a Construction Permit by EPRA on 3rd April 2019 for a period of one year for the development of 10 solar PV mini grids, as listed in Table 1."
}