"speaker_name": "Hon. Davis Chirchir",
"speaker_title": "The Cabinet Secretary for Roads and Transport",
"speaker": null,
"content": "The contractor then requested to subcontract the works as an alternative to avert a lengthy litigation process that would further delay progress. The request was granted in the interest of the greater public good. Subsequently, Hon. Members, the contractor, has over time entered into several subcontracting agreements to facilitate the completion of works. The latest being the 20th February, 2023, when Lido Supplies and General Traders Limited was brought on board. As of now, the sub-contractors have collectively delivered 16 kilometers of tarmac at the Ekalakala-Matuu and the Junction A3 Kathulani Junction C439 Road section translating to 54 per cent completion status with some 92 almost 93 months, which is their lapse time. However, on March, 2024, the subcontractor left site citing non-payment of dues. The Ministry has recently paid a total of Kshs88 million to the The electronic version of the Senate Hansard Report is for information purposesonly. A certified version of this Report can be obtained from the Director, Hansard and AudioServices, Senate."
}