"type": "speech",
"speaker_name": "Mr. Kiunjuri",
"speaker_title": "The Assistant Minister for Water and Irrigation",
"speaker": {
"id": 175,
"legal_name": "Festus Mwangi Kiunjuri",
"slug": "mwangi-kiunjuri"
},
"content": "A further population of 15,000 people in the area is being served by Naari-Mutethia Water Project whose construction is 90 per cent complete. Kiirua Location will be served by the proposed Kiirua-Buuri Water Project whose intake is at Kathita River. Survey and design of the project is being finalised. Ruiri and Rwarera locations will be served by the ongoing Ruiri Water Project which targets 50,000 residents of these areas. Phase I and II of this water project has been completed at a cost of Kshs40 million."
}