GET /api/v0.1/hansard/entries/194593/?format=api
HTTP 200 OK
Allow: GET, PUT, PATCH, DELETE, HEAD, OPTIONS
Content-Type: application/json
Vary: Accept
{
"id": 194593,
"url": "https://info.mzalendo.com/api/v0.1/hansard/entries/194593/?format=api",
"text_counter": 36,
"type": "speech",
"speaker_name": "Mr. Keter",
"speaker_title": "The Assistant Minister for Energy",
"speaker": {
"id": 169,
"legal_name": "Charles Cheruiyot Keter",
"slug": "charles-keter"
},
"content": " Mr. Speaker, Sir, I beg to reply. (a) Yes, I am aware that some pegging work for the Matungu-Koyonzo-Munami-Lubanga electrification project was undertaken between August to September, 2007, but currently no work is in progress. This stoppage was occasioned by the post-election violence that erupted in January and February, 2008, which made the contractor, China National Wire and Cable Import/Export Corporation, suspend operations. 934 PARLIAMENTARY DEBATES May 8, 2008 (b) Work on the project, which is estimated to cost Kshs32.6 million, is expected to resume in June, 2008, and be completed by September, 2008."
}