    "speaker_name": "Mr. Kiunjuri",
    "speaker_title": "The Assistant Minister for Energy",
    "speaker": {
        "id": 175,
        "legal_name": "Festus Mwangi Kiunjuri",
        "slug": "mwangi-kiunjuri"
    },
    "content": " Mr. Deputy Speaker, Sir, I beg to reply. Electricity supply to Enkaroni Market has already been approved for implementation at a cost of Kshs9.7 million. The project is currently at the tendering stage, and the construction work is scheduled for completion by December, 2007. However, electricity supply to the remaining areas will be considered along with others for funding during the next two financial years."
}