    "speaker_name": "Mr. Omingo",
    "speaker_title": "",
    "speaker": {
        "id": 180,
        "legal_name": "James Omingo Magara",
        "slug": "omingo-magara"
    },
    "content": ", asked the Minister for Energy:- (a) when the construction of power lines to cover the following areas in South Mugirango will commence:- - Nyatike-Ramoya-Bokimai Health Centre; - Gotichaki Mongane; - Nyamarembe Mochengo-Nyangweta DOK Secondary School; - Keiyan-Nyamaiya Etago-Nyangweta SDA Secondary School; - Tabaka Kiorori Secondary School; and Ranen-Maroo Moticho Dispensary; (b) what has caused the delay in the commencement of the works under GoK and French Phase II Project; and, (c) whether he could state the exact dates of commencement and completion of the project."
}