"content": " Mr. Temporary Deputy Speaker, Sir, I beg to reply. (a) Yes, I am aware that West Karachuonyo Water Project which was commissioned in 1973 does not operate at full capacity due to frequent pipe bursts experienced at some sections of the aged pipeline. The clogging of the intake by the water hyacinth weed has also contributed to reducing the capacity of this water supply project. (b) Rehabilitation works on one of the two main pipelines to Got Oyaro has been completed and the pipeline is operational, while rehabilitation of the other line is ongoing. Rehabilitation of the three-kilometre branchline to Homa Hills is also ongoing and is scheduled to be completed in two months time. (c) West Karachuonyo Water Project was constructed over 30 years ago and comprises of old and damaged structures including the pipelines. Rehabilitation and augmentation of this water project is a continuous exercise which has been ongoing since the year 2000."
}