    "content": " Mr. Deputy Speaker, Sir, I beg to reply. (a) I am aware that the Masalani Bridge project which started in 2002 has not been completed to date. The delay has been occasioned by changes in the use of the original steel. The earlier design was to use steel that was formerly used at Sabaki Bridge in Malindi District. However, the steel was found to be so badly corroded that it was found necessary to fabricate new steel parts. The new steel parts had to be fabricated and transported to the site; that is Masalani. The original cost of the bridge was Kshs556,198,900.40. So far, payment has been made to the tune of Kshs339,322,664.92. The work is expected to be completed by 30th May, 2007."
}