    "speaker_name": "Eng. Toro",
    "speaker_title": "The Assistant Minister for Roads and Public Works",
    "speaker": {
        "id": 239,
        "legal_name": "Joshua Ngugi Toro",
        "slug": "joshua-toro"
    },
    "content": " Mr. Deputy Speaker, Sir, I beg to reply. (a) I am aware that Ouko Bridge across Kibos/Nyamasaria River and the Gita Bridge across Awach River along the Gita-Obwolo-Mamboleo Road within Kisumu Town East Constituency were about to be washed away due to massive erosion. (b) To prevent the imminent disaster, my Ministry has taken the following measures: (i) During the month of April, 2006, the Ministry carried out protection works on the approaches to the Ouko Bridge across the Kibos/Nyamasaria River at a total cost of Kshs912,000. The works were completed and the bridge is now safe. May 4, 2006 PARLIAMENTARY DEBATES 939 (ii) A total of Kshs6 million will be released to the District Works Officer, Kisumu for emergency works on the Gita Bridge across Awach River along the Gita-Obwolo-Mamboleo Road. The bridge is impassable at the moment. It is envisaged that the work will be completed before end of June this year."
}