    "id": 251543,
    "url": "https://info.mzalendo.com/api/v0.1/hansard/entries/251543/?format=api",
    "text_counter": 91,
    "type": "speech",
    "speaker_name": "Mr. Shaaban",
    "speaker_title": "The Assistant Minister for Local Government",
    "speaker": {
        "id": 262,
        "legal_name": "Isaack Shaban",
        "slug": "isaack-shaaban"
    },
    "content": " Mr. Deputy Speaker, Sir, I beg to answer. (a) It is true that construction work on Nyamira Town Bus Park has stalled. (b) In September, 2005, a dispute arose over the ownership of the land on which the central bus park was being constructed. In October, 2005, the High Court issued restraining orders on the contractor carrying out the works pending the determination of who is supposed to be the rightful owner of this disputed piece of land. The ruling on the matter was supposed to be delivered in March, 2006. This was, however, put off until May, 2006. In the meantime, the contractor is set to resume work on Nyambite site any time. Works on the central bus park will resume once the matter is determined in court."
}