    "type": "speech",
    "speaker_name": "Prof. Anyang-Nyong’o",
    "speaker_title": "The Minister for Medical Services",
    "speaker": {
        "id": 193,
        "legal_name": "Peter Anyang' Nyong'o",
        "slug": "peter-nyongo"
    },
    "content": "(a) I am aware that there are stalled staff houses at Kapsabet District Hospital. They stalled following a dispute with the contractor which we took to court in the early 1990s. The contractor passed on before the dispute could be resolved. The contract was later terminated. Thereafter no funds were allocated to complete the project. After the 2002 General Election, when the NARC Government came to power, it initiated a stalled projects programme under the Ministry of Public Works. We had expected this project to be completed within this framework. However, we have recently learnt that it was not among the projects funded under the stalled projects programme that the NARC Government initiated."
}