    "content": "It is over two and a half years since REA began the installation of electricity in the area between Konyao and Alale, a distance of 70 kilometres. Up to now, only about 10 kilometres have been connected. The District Headquarters in Alale, schools in Losam, Natemer, Kiwawa, Lowoi, Kasses and health facilities do not have access to electricity. This has caused anxiety among the residents, who were informed that the project would be completed by December, 2012. In his statement, the Chairperson should give reasons for the delay in the installation of electricity in this area. Two, he should indicate when the REA project is expected to be completed."
}