    "content": "payments that have been made to the contractor, out of a contract sum of Kshs4 billion, only Kshs800 million has been paid and we are half way through this contract. So, the clarification I want to seek is; is the Government going to pay the contractor the amount that is owed so that the contractor can accelerate the work as soon as possible? As I said, the contractor has only done 11 per cent of the work and we are mid way through the contract. What steps is the Government taking to ensure that the contractor who is behind schedule, catches up with the schedule and moves to complete the contract within the contract period?"
}