Erastus Kivasu Nzioka

Parties & Coalitions

Link

@MbooniMp on Twitter

All parliamentary appearances

Entries 61 to 70 of 121.

  • 26 Feb 2019 in National Assembly: (1) The NG-CDF Board takes administrative action against fund account managers who reallocated funds contrary to the NG-CDF Act, 2015; view
  • 26 Feb 2019 in National Assembly: (2) The fund account managers ensure compliance with Section 6(2) and Section 31 of the NG-CDF Act, 2015; view
  • 26 Feb 2019 in National Assembly: (3) The NG-CDF Board publishes a list of all incomplete and stalled projects initiated by the former CDF Board prior to the enactment of the NG-CDF Act, 2015; view
  • 26 Feb 2019 in National Assembly: (4) The NG-CDF Board in consultation with the National Treasury and other relevant authorities expedite completion of all incomplete and stalled projects; view
  • 26 Feb 2019 in National Assembly: (5) The fund account managers ensure that relevant Government departments are involved during project implementation in line with the provisions of Section 36(1) of the NG-CDF Act, 2015; view
  • 26 Feb 2019 in National Assembly: (6) The NG-CDF Board in consultation with the County Public Works office and the National Construction Authority (NCA) assesses the structural integrity of projects in question and issue occupational certificate; view
  • 26 Feb 2019 in National Assembly: (7) NG-CDF Committees engage the services of the Clerk of Works in management of projects as provided for in the NG-CDF Board guidelines. view
  • 26 Feb 2019 in National Assembly: There is also the issue of the disbursement of funds for the implementation of the projects as indicated in the Second Report of the Committee. Late disbursement of funds to the NG-CDF Board by the National Treasury adversely affects implementation of the approved projects. We realised that money is released but many times, we do not get the Authority to Incur Expenditure (AIE). We cannot spend without getting it. The Committee observed that funds were disbursed in the second and third quarter of the financial years which made it difficult to complete procurement processes and ultimately led to non-implementation of ... view
  • 26 Feb 2019 in National Assembly: There is failure to submit documents during audit period. It was observed that the fund account managers did not avail the required documents that were subject of examination by the Auditor-General for verification at the time of audit. The documents which were not availed for audit include cash books, bank statements, payment vouchers, project completion certificates and procurement records. view
  • 26 Feb 2019 in National Assembly: The Committee therefore recommends that: The electronic version of the Official Hansard Report is for information purposes only. Acertified version of this Report can be obtained from the Hansard Editor. view