The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.

It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

Projects in Ainamoi

Soin Water Project

location
Soin (in Ainamoi)
year first funded
2009
action
New Water Project
output
-
implementation status
roofed
total cost
Ksh 5,000,000
estimate
Ksh 15,000,000

Kapkwen Primary School

location
Ainamoi (in Ainamoi)
year first funded
2008
action
Purchase Of Land & Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 4,600,000
estimate
Ksh 6,500,000

Maso Primary School

location
Kapsaos (in Ainamoi)
year first funded
2007
action
Electricity Connection
output
-
implementation status
In Progress
total cost
Ksh 3,047,777
estimate
Ksh 1,836,320

Kiburet Primary School

location
Ainamoi (in Ainamoi)
year first funded
2006
action
Electricity Connection
output
-
implementation status
In Progress
total cost
Ksh 2,718,502
estimate
Ksh 1,879,768

Chebigen Secondary School

location
Kapsaos (in Ainamoi)
year first funded
2003
action
Construction Of Adm Block
output
-
implementation status
plastered
total cost
Ksh 2,447,000
estimate
Ksh 1,486,600

Kapsorok Secondary School

location
Kapsorok (in Ainamoi)
year first funded
2008
action
Construction Of New Day Secondary School
output
-
implementation status
comlete
total cost
Ksh 2,100,000
estimate
Ksh 2,500,000

Motero Secondary School

location
Soliat (in Ainamoi)
year first funded
2008
action
Construction Of New Day Secondary School
output
-
implementation status
plastered
total cost
Ksh 2,100,000
estimate
Ksh 2,500,000

Manyoror Secondary School

location
Kapsaos (in Ainamoi)
year first funded
2008
action
Construction Of New Day Secondary School
output
-
implementation status
roofed/others ongoing
total cost
Ksh 2,100,000
estimate
Ksh 2,500,000

Kenegut Dispensary

location
Kenegut (in Ainamoi)
year first funded
2003
action
Maternity Wing
output
-
implementation status
Completed
total cost
Ksh 2,000,000
estimate
Ksh 10,225,930

Ainamoi Secondary School / Kapsigirio

location
Ainamoi (in Ainamoi)
year first funded
2004
action
Construction of 2 Classrooms
output
-
implementation status
plastered
total cost
Ksh 1,800,000
estimate
Ksh 700,000

Kapcheptoror Sec

location
Ainamoi (in Ainamoi)
year first funded
2003
action
Construction Of Classrooms
output
-
implementation status
plastered
total cost
Ksh 1,750,000
estimate
Ksh 616,850

Laliat Dispensary

location
Poiywek (in Ainamoi)
year first funded
2003
action
Two Consultation Rooms
output
-
implementation status
In Progress
total cost
Ksh 1,700,000
estimate
Ksh 1,300,000

Ainamoi Health Centre

location
Ainamoi (in Ainamoi)
year first funded
2004
action
Building 2 Staff Houses & Purchase Of Equipment
output
-
implementation status
Completed
total cost
Ksh 1,698,296
estimate
Ksh 2,000,000

Sombicho Primary School

location
Kaitui (in Ainamoi)
year first funded
2007
action
Electricity Connection
output
-
implementation status
In Progress
total cost
Ksh 1,612,214
estimate
Ksh 1,262,760

Kipsitet Dispensary

location
Soin (in Ainamoi)
year first funded
2003
action
Male Ward And Kitchen
output
-
implementation status
Completed
total cost
Ksh 1,500,000
estimate
Ksh 2,089,232

Kenegut Secondary School

location
Kenegut (in Ainamoi)
year first funded
2004
action
Construction Of Dormitory
output
-
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 4,992,950

Torsogek Water Project

location
Kenegut (in Ainamoi)
year first funded
2008
action
Piping & Construction Of Water Tank
output
-
implementation status
plastered
total cost
Ksh 1,500,000
estimate
Ksh 2,500,000

Otui Water Project

location
Kapsaos (in Ainamoi)
year first funded
2004
action
Construction Of Water Tank
output
-
implementation status
to start
total cost
Ksh 1,400,000
estimate
Ksh 1,029,300

Kipchimchim Secondary School

location
Ainamoi (in Ainamoi)
year first funded
2004
action
Construction Of Boys Dorm
output
-
implementation status
to lintel
total cost
Ksh 1,378,000
estimate
Ksh 314,015

Kapsigirio Primary School

location
Ainamoi (in Ainamoi)
year first funded
2005
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 1,350,000
estimate
Ksh 1,200,000

Kenegut Water Project

location
Kenegut (in Ainamoi)
year first funded
2004
action
Rehabilitation Of The Water Project
output
-
implementation status
roofed
total cost
Ksh 1,300,000
estimate
Ksh 1,500,000

Cheramor Primary School

location
Kapsorok (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 1,250,000
estimate
Ksh 642,000

Ainamoi Polytechnic

location
Ainamoi (in Ainamoi)
year first funded
2009
action
Purchase Of Polytechnic Land
output
-
implementation status
Yet To Receive Funds
total cost
Ksh 1,200,000
estimate
Ksh 10,000,000

Ainamoi Water Projects-Elnino Project

location
Ainamoi (in Ainamoi)
year first funded
2008
action
New Water Project
output
-
implementation status
on going
total cost
Ksh 1,200,000
estimate
Ksh 1,500,000

Kaitui Secondary School

location
Kaitui (in Ainamoi)
year first funded
2003
action
Construction Of A Kitchen
output
-
implementation status
complete
total cost
Ksh 1,200,000
estimate
Ksh 792,350

Kaptalamwa Water Project

location
Soin (in Ainamoi)
year first funded
2004
action
Piping & Construction Of Water Tank
output
-
implementation status
tanks installed
total cost
Ksh 1,100,000
estimate
Ksh 3,193,950

Ngeny Koiborot Secondary School

location
Koitaburot (in Ainamoi)
year first funded
2004
action
Construction Of 3 Classroom
output
-
implementation status
roofed
total cost
Ksh 1,100,000
estimate
Ksh 1,000,000

Ainamoi Divisional Hqs-Reconstruction

location
Ainamoi (in Ainamoi)
year first funded
2008
action
Rehabilitation Of Do'S Office
output
-
implementation status
roofed
total cost
Ksh 1,000,000
estimate
Ksh 1,200,000

Kechiriet Water Project

location
Koitaburot (in Ainamoi)
year first funded
2005
action
Securing Of Source And Piping
output
-
implementation status
complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Kechiriet Dispensary

location
Koitaburot (in Ainamoi)
year first funded
2004
action
Construction Of Dispensary
output
-
implementation status
Completed
total cost
Ksh 1,000,000
estimate
Ksh 1,200,000

Bogwo Primary School

location
Soin (in Ainamoi)
year first funded
2005
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 1,000,000
estimate
Ksh 2,400,000

Kaitui Dispensary

location
Kaitui (in Ainamoi)
year first funded
2004
action
Construction Of Dispensary
output
-
implementation status
In Progress
total cost
Ksh 1,000,000
estimate
Ksh 1,100,000

Kamasega Dispensary

location
Soliat (in Ainamoi)
year first funded
2004
action
Construction Of Ward
output
-
implementation status
In Progress
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Ketipyese Primary School

location
Ainamoi (in Ainamoi)
year first funded
2005
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 950,000
estimate
Ksh 1,200,000

Nyalilbuch Dispensary

location
Soin (in Ainamoi)
year first funded
2003
action
Construction Of Dispensary
output
-
implementation status
In Progress
total cost
Ksh 950,000
estimate
Ksh 1,700,000

Kapsorok Water Project

location
Kapsorok (in Ainamoi)
year first funded
2008
action
Trenching & Plumbing
output
-
implementation status
well dug
total cost
Ksh 900,000
estimate
Ksh 900,000

Kabokyek Adv Sec

location
Kapsegut (in Ainamoi)
year first funded
2004
action
Construction Of Laboratory
output
-
implementation status
trees planted
total cost
Ksh 900,000
estimate
Ksh 1,150,000

Kapsorok Dispensary

location
Kapsorok (in Ainamoi)
year first funded
2004
action
Construction Of Dispensary
output
-
implementation status
In Progress
total cost
Ksh 900,000
estimate
Ksh 1,200,000

Kapsorok Primary School

location
Kapsorok (in Ainamoi)
year first funded
2004
action
Repair Wind Damage
output
-
implementation status
not known
total cost
Ksh 900,000
estimate
Ksh 1,000,000

Ngenybare Primary School

location
Ainamoi (in Ainamoi)
year first funded
2007
action
Construction Of Classrooms
output
-
implementation status
roofed
total cost
Ksh 850,000
estimate
Ksh 600,000

Maso Dispensary

location
Kapsaos (in Ainamoi)
year first funded
2008
action
Construction Of Dispensary
output
-
implementation status
In Progress
total cost
Ksh 800,000
estimate
Ksh 500,000

Chebirir Primary School

location
Soin (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 800,000
estimate
Ksh 600,000

Chesiche Water Project

location
Kapsegut (in Ainamoi)
year first funded
2005
action
Rehabilitation Of Old Water Supply
output
-
implementation status
windoWest level
total cost
Ksh 800,000
estimate
Ksh 3,744,374

Otui Primary School

location
Kapsaos (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
trees planted
total cost
Ksh 800,000
estimate
Ksh 250,000

Kipchimchim Primary School

location
Ainamoi (in Ainamoi)
year first funded
2005
action
Construction Of Pavement / Toilet
output
-
implementation status
Clinic blg complete,Dr hse to start
total cost
Ksh 800,000
estimate
Ksh 700,000

Tuiyobei Primary School

location
Kapsegut (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
complete
total cost
Ksh 750,000
estimate
Ksh 750,000

Bagao Primary School

location
Ainamoi (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 750,000
estimate
Ksh 600,000

Kapkiam Dispensary

location
Tendwet (in Ainamoi)
year first funded
2006
action
Construction Of Ward
output
-
implementation status
In Progress
total cost
Ksh 750,000
estimate
Ksh 700,000

Soliat BoysSecondary School

location
Soliat (in Ainamoi)
year first funded
2004
action
Staff House
output
-
implementation status
fdn level
total cost
Ksh 735,000
estimate
Ksh 800,000

Kabokyek Primary School

location
Kapsegut (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 700,000
estimate
Ksh 300,000

Koyabei Primary School

location
Koitaburot (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
fdn walling
total cost
Ksh 700,000
estimate
Ksh 700,000

Kaptoroi Primary School Startin

location
Ainamoi (in Ainamoi)
year first funded
2008
action
Purchase Of Land & Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 700,000
estimate
Ksh 800,000

Arorwet Cheribo Primary School

location
Kenegut (in Ainamoi)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 700,000
estimate
Ksh 800,000

Chepyegon Primary School

location
Kapsorok (in Ainamoi)
year first funded
2005
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 650,000
estimate
Ksh 676,740

Sertwet Primary School

location
Soin (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
funds to be realocated
total cost
Ksh 650,000
estimate
Ksh 650,000

Kabasenwo Primary School

location
Kaitui (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 650,000
estimate
Ksh 750,000

Mureret Primary School

location
Kapsaos (in Ainamoi)
year first funded
2003
action
Construction Of Classrooms
output
-
implementation status
well dug
total cost
Ksh 650,000
estimate
Ksh 250,000

Chepngobob Primary School

location
Kapsaos (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 650,000
estimate
Ksh 700,000

Kiburet Primary School

location
Ainamoi (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 600,000
estimate
Ksh 600,000

Ainamoi Primary School

location
Ainamoi (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 600,000
estimate
Ksh 340,000

Kiplogoi Primary School

location
Soin (in Ainamoi)
year first funded
2005
action
Construction Of Classrooms
output
-
implementation status
complete
total cost
Ksh 600,000
estimate
Ksh 3,364,520

Kapsoit Secondary School

location
Kapsoit (in Ainamoi)
year first funded
2003
action
Construction Of Adm Block
output
-
implementation status
on going
total cost
Ksh 600,000
estimate
Ksh 200,000

Chemorir Water Project

location
Ainamoi (in Ainamoi)
year first funded
2005
action
Trenching & Plumbing
output
-
implementation status
to lintel
total cost
Ksh 600,000
estimate
Ksh 1,200,000

Ndonyo Mare Primary School

location
Soin (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
roofed
total cost
Ksh 550,000
estimate
Ksh 600,000

Kileges Primary School

location
Soin (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 550,000
estimate
Ksh 600,000

Kapkormom Dispensary

location
Koitaburot (in Ainamoi)
year first funded
2005
action
Construction Of Dispensary
output
-
implementation status
In Progress
total cost
Ksh 550,000
estimate
Ksh 2,000,000

Kapkisai Primary School

location
Soin (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 550,000
estimate
Ksh 250,000

Kapkormom Primary School

location
Koitaburot (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 550,000
estimate
Ksh 650,000

Kapngetuny Primary School

location
Kapsaos (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 500,000

Kebimbir Primary School

location
Soin (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 371,720

Lemeiywet Primary School

location
Kenegut (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
purchased
total cost
Ksh 500,000
estimate
Ksh 350,000

Simbi Primary School

location
Soin (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
complete to painting
total cost
Ksh 500,000
estimate
Ksh 600,000

Kapsaos-Manyoror Bridge

location
Kapsaos (in Ainamoi)
year first funded
2004
action
Opening Of Access Road
output
-
implementation status
to be funded
total cost
Ksh 500,000
estimate
Ksh 500,000

Chepngobob Secondary School

location
Kapsaos (in Ainamoi)
year first funded
2009
action
Construction Of Classrooms
output
-
implementation status
half way done
total cost
Ksh 500,000
estimate
Ksh 500,000

Chepkongony Water Project

location
Ainamoi (in Ainamoi)
year first funded
2004
action
Piping & Construction Of Water Tank
output
-
implementation status
fdn level
total cost
Ksh 500,000
estimate
Ksh 1,110,549

Ndonyo Mare Primary School bridge

location
Soin (in Ainamoi)
year first funded
2009
action
Construction Of Footbridge
output
-
implementation status
roofed
total cost
Ksh 500,000
estimate
Ksh 700,000

Itoibei Primary School

location
Kapsaos (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 600,000

Kamasega Primary School

location
Soliat (in Ainamoi)
year first funded
2005
action
Construction Of Classroom
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 150,000

Kapkigoro Primary School

location
Soin (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 600,000

Kaplelach Primary School

location
Soin (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 1,800,000

Cheplel Primary School

location
Kenegut (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 1,582,770

Koitaborot Dispensary

location
Koitaborot (in Ainamoi)
year first funded
2005
action
Construction Of Dispensary
output
-
implementation status
In Progress
total cost
Ksh 500,000
estimate
Ksh 800,000

Kapsaos Dispensary

location
Kapsaos (in Ainamoi)
year first funded
2006
action
Construction Of Dispensary
output
-
implementation status
In Progress
total cost
Ksh 500,000
estimate
Ksh 1,000,000

Cheptililik Primary School

location
Koitaburot (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 1,672,820

Manyoror Primary School

location
Kapsaos (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
complete
total cost
Ksh 450,000
estimate
Ksh 600,000

Koitabmat Primary School

location
Ainamoi (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
to floor slab
total cost
Ksh 450,000
estimate
Ksh 500,000

Kiboibei Primary School

location
Kenegut (in Ainamoi)
year first funded
2005
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 450,000
estimate
Ksh 600,000

Kaplilo Water Project

location
Ainamoi (in Ainamoi)
year first funded
2005
action
n/a
output
-
implementation status
Stalled - Being Audited
total cost
Ksh 400,000
estimate
Ksh 1,000,000

Kaplellach Water Project

location
Soin (in Ainamoi)
year first funded
2009
action
New Water Project
output
-
implementation status
roofed
total cost
Ksh 400,000
estimate
Ksh 500,000

Moi Kipsitet Secondary School

location
Soin (in Ainamoi)
year first funded
2005
action
Construction Of Staff House
output
-
implementation status
complete
total cost
Ksh 400,000
estimate
Ksh 2,953,600

Sugutek Primary School

location
Kapsaos (in Ainamoi)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
to be funded
total cost
Ksh 400,000
estimate
Ksh 450,000

Kibugat Pre School

location
Koitaburot (in Ainamoi)
year first funded
2007
action
Construction Of One Classrooms
output
-
implementation status
Being Audited
total cost
Ksh 400,000
estimate
Ksh 500,000

Manyoror Dispensary

location
Kapsaos (in Ainamoi)
year first funded
2009
action
Purchase Of Land For Expansion
output
-
implementation status
Yet To Receive Funds
total cost
Ksh 400,000
estimate
Ksh 500,000

Ketitui Dispensary

location
Telanet (in Ainamoi)
year first funded
2005
action
Construction Of Dispensary
output
-
implementation status
Completed
total cost
Ksh 400,000
estimate
Ksh 800,000

Kamasega Polytechnic

location
Soliat (in Ainamoi)
year first funded
2009
action
Purchase Of Polytechnic Land
output
-
implementation status
Yet To Receive Funds
total cost
Ksh 400,000
estimate
Ksh 400,000

Mureret Water Project

location
Kapsaos (in Ainamoi)
year first funded
2008
action
New Water Project
output
-
implementation status
on going
total cost
Ksh 400,000
estimate
Ksh 500,000

Kapsaos Water Project

location
Kapsaos (in Ainamoi)
year first funded
2008
action
New Water Project
output
-
implementation status
well dug
total cost
Ksh 400,000
estimate
Ksh 450,000

Kipsitet Primary School

location
Soin (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
plastered
total cost
Ksh 387,160
estimate
Ksh 391,000

Kipsigori Primary School

location
Kapsaos (in Ainamoi)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
Complete
total cost
Ksh 350,000
estimate
Ksh 400,000

Chemorir Pre-School

location
Ainamoi (in Ainamoi)
year first funded
2007
action
Construction Of Classrooms
output
-
implementation status
In Progress
total cost
Ksh 350,000
estimate
Ksh 300,000

Laitigo Primary School

location
Koitaburot (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
on going
total cost
Ksh 350,000
estimate
Ksh 350,000

Kenegut Primary School

location
Kenegut (in Ainamoi)
year first funded
2004
action
Renovation Of Roofing / Floor
output
-
implementation status
not known
total cost
Ksh 350,000
estimate
Ksh 500,000

Kosisit Primary School

location
Kenegut (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
complete
total cost
Ksh 350,000
estimate
Ksh 676,500

Kiboibei Water Project

location
Kenegut (in Ainamoi)
year first funded
2009
action
New Water Project
output
-
implementation status
roofed
total cost
Ksh 330,998
estimate
Ksh 600,000

Motero Kurabei Dispensary

location
Soliat (in Ainamoi)
year first funded
2004
action
Construction Of Dispensary
output
-
implementation status
In Progress
total cost
Ksh 300,000
estimate
Ksh 300,000

Sirimdo Water Project

location
Ainamoi (in Ainamoi)
year first funded
2009
action
New Water Project
output
-
implementation status
plastered
total cost
Ksh 300,000
estimate
Ksh 300,000

Kiburuny Water Project

location
Kapsaos (in Ainamoi)
year first funded
2008
action
New Water Project
output
-
implementation status
on going
total cost
Ksh 300,000
estimate
Ksh 500,000

Kiburet Water Project

location
Ainamoi (in Ainamoi)
year first funded
2009
action
New Water Project
output
-
implementation status
equipment bought
total cost
Ksh 300,000
estimate
Ksh 500,000

Kaboswa Water Project

location
Kapsoit (in Ainamoi)
year first funded
2008
action
New Water Project
output
-
implementation status
fdn level
total cost
Ksh 300,000
estimate
Ksh 400,000

Tabain -Cherungus Road

location
Kapsaos (in Ainamoi)
year first funded
2009
action
Opening Of Access Road
output
-
implementation status
windoWest level
total cost
Ksh 300,000
estimate
Ksh 300,000

Maso-Mureret Road

location
Kapsaos (in Ainamoi)
year first funded
2008
action
Opening Of Access Road
output
-
implementation status
procurement
total cost
Ksh 300,000
estimate
Ksh 300,000

Kenegut -Kisabei-Kiptegan Road

location
Kenegut (in Ainamoi)
year first funded
2008
action
Opening Of Access Road
output
-
implementation status
on going
total cost
Ksh 300,000
estimate
Ksh 300,000

Bagao Road

location
Ainamoi (in Ainamoi)
year first funded
2008
action
Opening Of Access Road
output
-
implementation status
tanks puschased
total cost
Ksh 300,000
estimate
Ksh 300,000

Ainamoi Chief Office

location
Ainamoi (in Ainamoi)
year first funded
2007
action
Construction Of Chief'S Office
output
-
implementation status
to start
total cost
Ksh 300,000
estimate
Ksh 600,000

Samaria Primary School

location
Kapsaos (in Ainamoi)
year first funded
2009
action
Construction Of Classrooms
output
-
implementation status
to lintel
total cost
Ksh 300,000
estimate
Ksh 400,000

Nyalilibuch Primary School

location
Soin (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
to start
total cost
Ksh 300,000
estimate
Ksh 300,000

Kongeren Primary School

location
Soliat (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
equipqment bought and West sp renovated
total cost
Ksh 300,000
estimate
Ksh 300,000

Koirir Primary School

location
Soliat (in Ainamoi)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
structures erected
total cost
Ksh 300,000
estimate
Ksh 400,000

Koibeiyot Primary School

location
Kapsaos (in Ainamoi)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
procurement stage
total cost
Ksh 300,000
estimate
Ksh 400,000

Kapcheptoror Primary School

location
Ainamoi (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 300,000
estimate
Ksh 300,000

Kaigaron Primary School

location
Kapsaos (in Ainamoi)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 300,000
estimate
Ksh 450,000

Kabore Primary School

location
Soin (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 300,000
estimate
Ksh 1,376,980

Chesiche Primary School

location
Kapsegut (in Ainamoi)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 300,000
estimate
Ksh 400,000

Chemagaldit Primary School

location
Kapsaos (in Ainamoi)
year first funded
2009
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 300,000
estimate
Ksh 600,000

Baregeiwet Primary Schooloo

location
Soin (in Ainamoi)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 300,000
estimate
Ksh 350,000

Chemagaldit/Samoei Electricity

location
Kapsaos (in Ainamoi)
year first funded
2008
action
Electricity Connection
output
-
implementation status
Completed
total cost
Ksh 300,000
estimate
Ksh 350,000

Soliat Dispensary

location
Soliat (in Ainamoi)
year first funded
2006
action
Construction Of Dispensary
output
-
implementation status
In Progress
total cost
Ksh 300,000
estimate
Ksh 600,000

Chepkoiyo Dispensary

location
Poiwek (in Ainamoi)
year first funded
2005
action
Construction Of Dispensary
output
-
implementation status
In Progress
total cost
Ksh 300,000
estimate
Ksh 500,000

Ainamoi Tea Buying Centre

location
Ainamoi (in Ainamoi)
year first funded
2009
action
Completion Of Community T.B. Centre
output
-
implementation status
Yet To Receive Funds
total cost
Ksh 300,000
estimate
Ksh 300,000

Kapchebwai Primary School

location
Koitaburot (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 280,000
estimate
Ksh 280,000

Koitaburot Primary School

location
Koitaburot (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
purchased
total cost
Ksh 280,000
estimate
Ksh 300,000

Torsogek Primary School

location
Kenegut (in Ainamoi)
year first funded
2007
action
Construction Of Classrooms
output
-
implementation status
purchased
total cost
Ksh 250,000
estimate
Ksh 300,000

Sombicho Primary School

location
Kaitui (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
procurement stage
total cost
Ksh 250,000
estimate
Ksh 1,200,000

Nyaberi Primary School

location
Soin (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
roofed
total cost
Ksh 250,000
estimate
Ksh 250,000

Motero Primary School

location
Soliat (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
maternity to painting,placenter not yet funded
total cost
Ksh 250,000
estimate
Ksh 500,000

Maso Primary School

location
Kapsaos (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
funds realocated
total cost
Ksh 250,000
estimate
Ksh 300,000

Kiptugumo Primary School

location
Kaitui (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
roofed
total cost
Ksh 250,000
estimate
Ksh 250,000

Kipkocheiyat Pre School

location
Kaitui (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
In Progress
total cost
Ksh 250,000
estimate
Ksh 300,000

Torsogek Pre School

location
Kenegut (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 250,000
estimate
Ksh 250,000

Kaptalamwa Primary School

location
Soin (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 250,000
estimate
Ksh 250,000

Kaboswa Primary School

location
Kaitui (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 250,000
estimate
Ksh 600,000

Kejiriet Primary School

location
Koitaburot (in Ainamoi)
year first funded
2004
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 250,000
estimate
Ksh 500,000

Kapkitony Pre School

location
Kapsoit (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
In Progress
total cost
Ksh 250,000
estimate
Ksh 300,000

Chebigen Primary School

location
Kapsaos (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 250,000
estimate
Ksh 250,000

Kapsegut Primary School

location
Kapsegut (in Ainamoi)
year first funded
2004
action
Repair Roof Blown By Wind
output
-
implementation status
not known
total cost
Ksh 226,500
estimate
Ksh 76,500

Mulgelwet Water Project

location
Ainamoi (in Ainamoi)
year first funded
2008
action
New Water Project
output
-
implementation status
on going
total cost
Ksh 200,000
estimate
Ksh 250,000

Itibet Tea Buying Centre

location
Ainamoi (in Ainamoi)
year first funded
2009
action
Completion Of Community T.B. Centre
output
-
implementation status
Yet To Receive Funds
total cost
Ksh 200,000
estimate
Ksh 50,000

Kapsoit Dispensary

location
Kapsoit (in Ainamoi)
year first funded
2005
action
Improve Facilities
output
-
implementation status
Completed
total cost
Ksh 200,000
estimate
Ksh 1,200,000

Chepyegon Pre School

location
Soliat (in Ainamoi)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
In Progress
total cost
Ksh 200,000
estimate
Ksh 300,000

Kapsaos Chief's Office

location
Kapsaos (in Ainamoi)
year first funded
2008
action
Construction Of Chief'S Office
output
-
implementation status
adm block painted,class floor slab level
total cost
Ksh 200,000
estimate
Ksh 500,000

Kenegut - Lemeiywet Road

location
Kenegut (in Ainamoi)
year first funded
2008
action
Opening Of Access Road
output
-
implementation status
on going
total cost
Ksh 186,000
estimate
Ksh 200,000

Koitabmat Road

location
Ainamoi (in Ainamoi)
year first funded
2008
action
Opening Of Access Road
output
-
implementation status
complete
total cost
Ksh 150,000
estimate
Ksh 150,000

Torit Pre School

location
Kapsoit (in Ainamoi)
year first funded
2006
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 150,000
estimate
Ksh 300,000

Nyinyitiet Water Project

location
Ainamoi (in Ainamoi)
year first funded
2008
action
New Water Project
output
-
implementation status
to start
total cost
Ksh 100,000
estimate
Ksh 150,000

Kaboswa Dip

location
Kapsoit (in Ainamoi)
year first funded
2005
action
Rehabilitation / Purchase Of Acaricides
output
-
implementation status
Completed
total cost
Ksh 100,000
estimate
Ksh 150,000

Ketipyese Dip

location
Ainamoi (in Ainamoi)
year first funded
2005
action
Rehabilitation / Purchase Of Acaricides
output
-
implementation status
Completed
total cost
Ksh 100,000
estimate
Ksh 100,000

Kongeren Dip

location
Soliat (in Ainamoi)
year first funded
2005
action
Rehabilitation / Purchase Of Acaricides
output
-
implementation status
Completed
total cost
Ksh 100,000
estimate
Ksh 370,050

Mogonjet Dip

location
Soin (in Ainamoi)
year first funded
2006
action
Rehabilitation / Purchase Of Acaricides
output
-
implementation status
Completed
total cost
Ksh 100,000
estimate
Ksh 100,000

Lemeiywet Dip

location
Kenegut (in Ainamoi)
year first funded
2004
action
Rehabilitation / Purchase Of Acaricides
output
-
implementation status
Completed
total cost
Ksh 100,000
estimate
Ksh 100,000

Soliat Primary School

location
Soliat (in Ainamoi)
year first funded
2005
action
Construction Of Classrooms
output
-
implementation status
funds to be realocated
total cost
Ksh 100,000
estimate
Ksh 799,000

Soliat Chief's' Office

location
Soliat (in Ainamoi)
year first funded
2008
action
Construction Of Chief'S Office
output
-
implementation status
floor slab level
total cost
Ksh 100,000
estimate
Ksh 400,000

Maso Primary Schooloo Field Leveling

location
Kapsaos (in Ainamoi)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
land puychased class on going
total cost
Ksh 80,000
estimate
Ksh 80,000

Kapkitony Road

location
Kenegut (in Ainamoi)
year first funded
2008
action
Opening Of Access Road
output
-
implementation status
procurement
total cost
Ksh 50,000
estimate
Ksh 50,000

Kipsitet Dip

location
Soin (in Ainamoi)
year first funded
2004
action
Rehabilitation / Purchase Of Acaricides
output
-
implementation status
Completed
total cost
Ksh 50,000
estimate
Ksh 348,380

Kapsiagi Dip

location
Ainamoi (in Ainamoi)
year first funded
2004
action
Rehabilitation / Purchase Of Acaricides
output
-
implementation status
Completed
total cost
Ksh 50,000
estimate
Ksh 50,000

Kabokyek Dip

location
Kapsegut (in Ainamoi)
year first funded
2004
action
Rehabilitation / Purchase Of Acaricides
output
-
implementation status
Completed
total cost
Ksh 50,000
estimate
Ksh 50,000

Chemitan Dip

location
Kaitui (in Ainamoi)
year first funded
2006
action
Rehabilitation / Purchase Of Acaricides
output
-
implementation status
Completed
total cost
Ksh 50,000
estimate
Ksh 50,000