It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

Projects in Belgut

Kapcheluch Secondary School

location
Kabianga (in Belgut)
year first funded
2003
action
Construction dining Hall/Kitchen
output
School Expansion To Accommodate More Students
implementation status
Ongoing
total cost
Ksh 2,200,000
estimate
Ksh 0

Chepkutung Secondary School

location
Kapsuser (in Belgut)
year first funded
2003
action
Construction Of Classrooms, Administration Block And Temporary Kitchen
output
School Expansion To Accommodate More Students
implementation status
Ongoing
total cost
Ksh 2,000,000
estimate
Ksh 0

Keben Secondary School

location
Waldai (in Belgut)
year first funded
2003
action
Construction Of Administration Block
output
Better Performance
implementation status
Ongoing
total cost
Ksh 1,750,000
estimate
Ksh 0

Cheribo Secondary School

location
Waldai (in Belgut)
year first funded
2004
action
Construction Of Administration Block
output
School Expansion To Accommodate More Teachers
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 0

Sosiot Girls Secondary School

location
Waldai (in Belgut)
year first funded
2004
action
Construction Of 2 Classrooms
output
Provide Conducive Learning Environment
implementation status
Ongoing
total cost
Ksh 1,300,000
estimate
Ksh 0

Kabianga Water Project

location
Kabianga (in Belgut)
year first funded
2005
action
Supply Of Storage Tanks And Pipes
output
Provision Of Safe And Clean Drinking /Reduction Of Waterborne Diseases
implementation status
On Going
total cost
Ksh 1,250,000
estimate
Ksh 0

Kendabei Water Project

location
Kabianga (in Belgut)
year first funded
2004
action
Supply Of Storage Tanks
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
Ongoing
total cost
Ksh 1,150,000
estimate
Ksh 0

Kiptere Secondary School

location
Kiptere (in Belgut)
year first funded
2005
action
Construction Of BoyS Dormitory
output
School Expansion To Accommodate More Students
implementation status
Complete
total cost
Ksh 1,100,000
estimate
Ksh 0

Cheptenye Secondary School

location
Waldai (in Belgut)
year first funded
2005
action
Construction Of BoyS Dormitory
output
Provide More Space For Conducive Learning
implementation status
Ongoing
total cost
Ksh 1,000,000
estimate
Ksh 0

Koiwalelach Water Project

location
Chemamul (in Belgut)
year first funded
2003
action
Spring Protection
output
Environmental Conservation And Provision Of Clean Water
implementation status
On Going
total cost
Ksh 770,000
estimate
Ksh 0

Keben Water Project

location
Waldai (in Belgut)
year first funded
2005
action
Rehabilitation Of Water Project
output
Environmental Conservation And Provision Of Clean Water
implementation status
Complete
total cost
Ksh 750,000
estimate
Ksh 0

Kapmaso

location
Kabianga (in Belgut)
year first funded
2004
action
Construction Of Laboratory
output
-
implementation status
Complete
total cost
Ksh 700,000
estimate
Ksh 0

Chemamul Secondary School

location
Chemamul (in Belgut)
year first funded
2004
action
Construction Of Dormitory
output
Provide Conducive Learning Environment
implementation status
Complete
total cost
Ksh 650,000
estimate
Ksh 0

Barmei Primary School

location
Kabianga (in Belgut)
year first funded
2004
action
Construction Of Classrooms
output
Accommodate Increased Enrolment
implementation status
Ongoing
total cost
Ksh 600,000
estimate
Ksh 0

Cheptarit Water Project

location
Kiptere (in Belgut)
year first funded
2004
action
Water Supply
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
Ongoing
total cost
Ksh 600,000
estimate
Ksh 0

Kabianga Secondary School

location
Kabianga (in Belgut)
year first funded
2007
action
Construction Of Library
output
Provide Learning Material To Students And The Teaching And Non Teaching Staff
implementation status
Ongoing
total cost
Ksh 600,000
estimate
Ksh 0

Chepkosilen Secondary School

location
Seretut (in Belgut)
year first funded
2003
action
Construction Of Classrooms
output
-
implementation status
Ongoing
total cost
Ksh 570,000
estimate
Ksh 0

Kapchebet Primary School

location
Kabianga (in Belgut)
year first funded
2005
action
Construction Of 4 Classrooms
output
Accommodate Increased Enrolment
implementation status
Ongoing
total cost
Ksh 550,000
estimate
Ksh 0

Teldet Primary School

location
Waldai (in Belgut)
year first funded
2003
action
Construction Of Administration Block
output
Accommodate Increased Enrolment
implementation status
Ongoing
total cost
Ksh 550,000
estimate
Ksh 0

Chepsagogo Water Project

location
Kabianga (in Belgut)
year first funded
2003
action
Storage Tanks
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
Complete
total cost
Ksh 516,180
estimate
Ksh 0

Sosiot Kondamet Water Project

location
Waldai (in Belgut)
year first funded
2004
action
Supply Pipes
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
Ongoing
total cost
Ksh 500,000
estimate
Ksh 0

Singoronik Secondary School

location
Kiptere (in Belgut)
year first funded
2005
action
Dormitory And Classrooms
output
Gather For The Growing School Population
implementation status
Dormitory Complete
total cost
Ksh 500,000
estimate
Ksh 0

Kiptome Secondary School

location
Chemamul (in Belgut)
year first funded
2007
action
Construction Of Administration Block
output
Provide Learning Material To Students And The Teaching And Non Teaching Staff
implementation status
Ongoin
total cost
Ksh 400,000
estimate
Ksh 0

Cheribo Primary School

location
Waldai (in Belgut)
year first funded
2006
action
Construction Of 7 Classrooms/Administration Block
output
Enhance Good Learning Environment
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Kakibei Primary School

location
Kiptere (in Belgut)
year first funded
2005
action
Renovation Of 5 Of Classrooms
output
Accommodate Increased Enrolment
implementation status
Ongoing
total cost
Ksh 400,000
estimate
Ksh 0

Kamas Primary School

location
Chemamul (in Belgut)
year first funded
2004
action
Construction Of New Classrooms
output
Improve The Learning Environment
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Kapcheluch Primary School

location
Kabianga (in Belgut)
year first funded
2004
action
Construction Of Administration Block
output
Improve The Performance Of The School
implementation status
Ongoing
total cost
Ksh 400,000
estimate
Ksh 0

Kapkitony Primary School

location
Chemamul (in Belgut)
year first funded
2004
action
Construction Of 4 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Kaplutiet Primary School

location
Kabianga (in Belgut)
year first funded
2004
action
Construction Of Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Kapmaso Milimani Primary School

location
Kabianga (in Belgut)
year first funded
2004
action
Construction Of 1 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Kapmaso Primary School

location
Kabianga (in Belgut)
year first funded
2005
action
Renovation Of 2 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Kapsewa Primary School

location
Kiptere (in Belgut)
year first funded
2006
action
Construction Of 4 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Kaptoboiti Primary School

location
Waldai (in Belgut)
year first funded
2005
action
Construction Of Library
output
Provision Conducive Atmosphere For Studies
implementation status
Ongoing
total cost
Ksh 400,000
estimate
Ksh 0

Kibingei Priamry

location
Kabianga (in Belgut)
year first funded
2004
action
Construction Of 2 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Singoronik Primary School

location
Kiptere (in Belgut)
year first funded
2005
action
Construction Of 2 Classrooms
output
Improve The Learning Environment
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Susumwet Primary School

location
Kapsuser (in Belgut)
year first funded
2005
action
Construction Of Administration Block And Classrooms
output
Improve The Learning Environment
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Koiwalelach Secondary School

location
Chemamul (in Belgut)
year first funded
2004
action
Construction Of 2 Classrooms
output
-
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 0

Chemamul Water Project

location
Chemamul (in Belgut)
year first funded
2007
action
Spring Protection
output
Environmental Conservation And Provision Of Clean Water
implementation status
Ongoing
total cost
Ksh 400,000
estimate
Ksh 0

Itondo Water Project

location
Chemamul (in Belgut)
year first funded
2004
action
Water Supply
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
On Going
total cost
Ksh 350,000
estimate
Ksh 0

Koiwalelach Primary School

location
Chemamul (in Belgut)
year first funded
2005
action
n/a
output
Accommodate Increased Enrolment
implementation status
Ongoing
total cost
Ksh 350,000
estimate
Ksh 0

Keben Primary School

location
Waldai (in Belgut)
year first funded
2005
action
Construction Of 2 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 350,000
estimate
Ksh 0

Chepkosilen Primary School

location
Seretut (in Belgut)
year first funded
2004
action
Construction Of 2 Classrooms
output
Accommodate Increased Enrolment
implementation status
Ongoing
total cost
Ksh 350,000
estimate
Ksh 0

Cheptigit Water Project

location
Chemamul (in Belgut)
year first funded
2005
action
Spring Protection
output
Environmental Conservation And Provision Of Clean Water
implementation status
Complete
total cost
Ksh 323,560
estimate
Ksh 0

Chesebet Water Project

location
Kabianga (in Belgut)
year first funded
2005
action
Storage Tank
output
-
implementation status
Complete
total cost
Ksh 300,000
estimate
Ksh 0

Kondamet Kapkoros Water Project

location
Waldai (in Belgut)
year first funded
2007
action
Supply Of Storage Tanks Pipes And Hydrum
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 0

Kaplong Water Project

location
Kabianga (in Belgut)
year first funded
2006
action
Spring Protection
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 0

Kalyongwet Secondary School

location
Kiptere (in Belgut)
year first funded
2007
action
Construction Of 2 Classrooms
output
Construction Of A New Secondary School Accommodate More Students In The Constituency
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 0

Kesainet Water Project

location
Kiptere (in Belgut)
year first funded
2005
action
Spring Protection And Supply
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
On Going
total cost
Ksh 250,000
estimate
Ksh 0

Iraa Primary School

location
Kiptere (in Belgut)
year first funded
2006
action
Renovation Of 3 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 250,000
estimate
Ksh 0

Kiplelgutik Primary School

location
Kiptere (in Belgut)
year first funded
2006
action
Construction Of 2 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Chebirirbei Primary School

location
Chemamul (in Belgut)
year first funded
2007
action
Construction Of 2 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Chemamul Primary School

location
Chemamul (in Belgut)
year first funded
2005
action
Renovation Of Class Rooms
output
Accommodate Increased Enrolment Of Pupils
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Chepkoin Primary School

location
Waldai (in Belgut)
year first funded
2004
action
Construction Of 2 Classrooms
output
Accommodate Increased Enrolment
implementation status
On-Going
total cost
Ksh 200,000
estimate
Ksh 0

Cheptenye Primary School

location
Waldai (in Belgut)
year first funded
2005
action
Renovation Of Classrooms
output
Improve The Learning Environment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Itondo Primary School

location
Chemamul (in Belgut)
year first funded
2006
action
Construction Of Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kabianga Primary School

location
Kabianga (in Belgut)
year first funded
2006
action
Construction Of Computer Laboratory
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kabungungwo Primary School

location
Kapsuser (in Belgut)
year first funded
2004
action
Construction Of 2 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kalyangwet Primary School

location
Kiptere (in Belgut)
year first funded
2004
action
Construction Of Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kapkeburu Primary School

location
Kiptere (in Belgut)
year first funded
2005
action
Construction Of 2 Classrooms
output
Improve The Learning Environment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kapkochei Primary School

location
Kiptere (in Belgut)
year first funded
2003
action
Completion Of 7 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kapkures Primary School

location
Chemamul (in Belgut)
year first funded
2006
action
n/a
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kapriro Primary School

location
Chemamul (in Belgut)
year first funded
2004
action
n/a
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kesainet Primary School

location
Kiptere (in Belgut)
year first funded
2004
action
Construction Of 2 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kimorogo Primary School

location
Kiptere (in Belgut)
year first funded
2005
action
n/a
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kiptaldal Primary School

location
Waldai (in Belgut)
year first funded
2005
action
Construction Of 4 Classrooms
output
Improve The Learning Environment
implementation status
Ongoing
total cost
Ksh 200,000
estimate
Ksh 0

Kiptere Primary School

location
Kiptere (in Belgut)
year first funded
2006
action
Completion Of 2 Classrooms
output
Improve The Learning Environment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Kiptome Primary School

location
Chemamul (in Belgut)
year first funded
2005
action
n/a
output
Improve The Learning Environment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Koitalel Primary School

location
Waldai (in Belgut)
year first funded
2005
action
n/a
output
Improve The Learning Environment
implementation status
Ongoing
total cost
Ksh 200,000
estimate
Ksh 0

Nyabangi Primary School

location
Kabianga (in Belgut)
year first funded
2005
action
Renovation Of 6 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Seretut Primary School

location
Seretut (in Belgut)
year first funded
2006
action
Construction Of Administration Block
output
Improve The Learning Environment
implementation status
Ongoing
total cost
Ksh 200,000
estimate
Ksh 0

Taiywet Primary School

location
Kiptere (in Belgut)
year first funded
2004
action
Construction Of 2 Classrooms
output
Accommodate Increased Enrolment
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 0

Cheptembe Water Project

location
Kabianga (in Belgut)
year first funded
2006
action
Spring Protection
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
Ongoing
total cost
Ksh 200,000
estimate
Ksh 0

Itanda Welfare Association Wate Project

location
Waldai (in Belgut)
year first funded
2007
action
Spring Protection, Supply Of Pipes And Water Tank
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
On Going
total cost
Ksh 200,000
estimate
Ksh 0

Kapkochei Water Project

location
Kiptere (in Belgut)
year first funded
2006
action
Spring Protection, Supply Of Pipes And Water Tank
output
Provision Of Clean And Safe Drinking Water, Ease Time For Women
implementation status
On Going
total cost
Ksh 200,000
estimate
Ksh 0

Museset Water Project

location
Waldai (in Belgut)
year first funded
2007
action
Spring Protection
output
Environmental Conservation And Provision Of Clean Water
implementation status
Ongoing
total cost
Ksh 200,000
estimate
Ksh 0

Kiptaldal Kwenet Water Project

location
Waldai (in Belgut)
year first funded
2005
action
Spring Protection
output
Provision Of Clean Water, Ease Time Consuming Chores For Women
implementation status
Complete
total cost
Ksh 168,400
estimate
Ksh 0

Chepkutung Primalry

location
Kapsuser (in Belgut)
year first funded
2006
action
Renovation Of Classrooms
output
Improve The Learning Environment
implementation status
Complete
total cost
Ksh 150,000
estimate
Ksh 0

Kalyet Primary School

location
Kiptere (in Belgut)
year first funded
2006
action
Construction Of Classrooms
output
Accommodate Increased Enrolment
implementation status
Ongoing
total cost
Ksh 150,000
estimate
Ksh 0

Kaptagas Samituk Water Project

location
Waldai (in Belgut)
year first funded
2006
action
Spring Protection
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
Complete
total cost
Ksh 150,000
estimate
Ksh 0

Kimorogo Water Project

location
Kiptere (in Belgut)
year first funded
2007
action
Spring Protection
output
Environmental Conservation And Provision Of Clean Water
implementation status
Ongoing
total cost
Ksh 150,000
estimate
Ksh 0

Lelaitich Boiyot Water Project

location
Waldai (in Belgut)
year first funded
2006
action
Storage Tank
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
Ongoing
total cost
Ksh 150,000
estimate
Ksh 0

Targambei Water Project

location
Kiptere (in Belgut)
year first funded
2006
action
Construction Of Water Tank And Distribution
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
On Going
total cost
Ksh 150,000
estimate
Ksh 0

Kapchemalan Water Project

location
Kiptere (in Belgut)
year first funded
2005
action
Spring Protection, Supply Of Pipes And Water Tank
output
Provision Of Clean Water And Safe Drinking Water Thus Reduction Water Borne Disease
implementation status
Complete
total cost
Ksh 103,800
estimate
Ksh 0

Kimunai Spring Water Project

location
Chemamul (in Belgut)
year first funded
2006
action
Spring Protection
output
Reduction Of Poverty And Prevalence Of Waterborne Diseases
implementation status
Complete
total cost
Ksh 100,000
estimate
Ksh 0

Kondamet Water Project

location
Waldai (in Belgut)
year first funded
2007
action
Spring Protection
output
Environmental Conservation And Provision Of Clean Water
implementation status
Ongoing
total cost
Ksh 100,000
estimate
Ksh 0

Cheribo Cattle Dip

location
Waldai (in Belgut)
year first funded
2006
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 100,000
estimate
Ksh 0

Kapsinendet Kiptul Cattle Dip

location
Waldai (in Belgut)
year first funded
2005
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 100,000
estimate
Ksh 0

Kiptome Cattle Dip

location
Chemamul (in Belgut)
year first funded
2006
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 100,000
estimate
Ksh 0

Meregure Cattle Dip

location
Waldai (in Belgut)
year first funded
2006
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 100,000
estimate
Ksh 0

Ngariet Cattle Dip

location
Waldai (in Belgut)
year first funded
2006
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 100,000
estimate
Ksh 0

Kapkeburu Cattle Dip

location
Kiptere (in Belgut)
year first funded
2006
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 80,000
estimate
Ksh 0

Kipyegon Cattle Dip

location
Chemamul (in Belgut)
year first funded
2005
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 75,000
estimate
Ksh 0

Changware Cattle Dip

location
Chemamul (in Belgut)
year first funded
2005
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 75,000
estimate
Ksh 0

Chemumbe Cattle Dip

location
Kabianga (in Belgut)
year first funded
2005
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 75,000
estimate
Ksh 0

Cheptigit Cattle Dip

location
Chemamul (in Belgut)
year first funded
2005
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 75,000
estimate
Ksh 0

Itondo Cattle Dip

location
Chemamul (in Belgut)
year first funded
2005
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 75,000
estimate
Ksh 0

Kabianga Cattle Dip

location
Kabianga (in Belgut)
year first funded
2005
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 75,000
estimate
Ksh 0

Kiptaldal Cattle Dip

location
Waldai (in Belgut)
year first funded
2005
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 75,000
estimate
Ksh 0

Kitoi Cattle Dip

location
Chemamul (in Belgut)
year first funded
2005
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 75,000
estimate
Ksh 0

Tuiyobei Cattle Dip

location
Chemamul (in Belgut)
year first funded
2005
action
Cattle Dip Renovation
output
Provide Good Animal Husbandry And Increase Productivity Hence Poverty Reduction
implementation status
Complete
total cost
Ksh 75,000
estimate
Ksh 0

Kiptui Water Project

location
Waldai (in Belgut)
year first funded
2005
action
Spring Protection
output
Provision Of Clean Water, Ease Time Consuming Chores For Women
implementation status
Ongoing
total cost
Ksh 64,960
estimate
Ksh 0