The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Nyamokenye D Dispensary
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2008
- action
- Construction of Dispensary
- output
- -
- implementation status
- Ongoing - Roofing Done.
- total cost
- Ksh 9,493,520
- estimate
- Ksh 8,337,987
Kenyoro Dispensary
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2008
- action
- Construction of Dispensary
- output
- -
- implementation status
- Ongoing - Roofing Done.
- total cost
- Ksh 7,473,340
- estimate
- Ksh 8,461,197
Nyabiosi Water Project
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2009
- action
- Provision Of Clean Water
- output
- Water Tank And Piping
- implementation status
- Ongoing
- total cost
- Ksh 5,817,222
- estimate
- Ksh 5,817,222
Nyamache Sub District Hospital
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2003
- action
- Repair Mortuary, Electrical Wiring, Purchase And Fix Mortuary Cold Storage Equipments
- output
- Working And Conditioned Mortuary.
- implementation status
- Stalled - Mortuary Machine Not Fixed. Final Repair Touches To Building Not Done
- total cost
- Ksh 4,352,878
- estimate
- Ksh 4,352,878
Constituency Office
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2004
- action
- Construction of Office
- output
- Provide A Sound Workin Place
- implementation status
- Complete & In Use
- total cost
- Ksh 3,300,000
- estimate
- Ksh 3,559,044
Nyamache Stadium
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Construction of A Stadium
- output
- Enhance Sports
- implementation status
- Ongoing - At Finishing Level.
- total cost
- Ksh 3,098,982
- estimate
- Ksh 3,496,360
Suguta Dispensary
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2009
- action
- Construction of Dispensary
- output
- Good Health Facility
- implementation status
- New
- total cost
- Ksh 3,000,000
- estimate
- Ksh 3,000,000
Riamakora/Riakerongo Box Culverts
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Box & Pipe Culverts
- output
- -
- implementation status
- Ongoing
- total cost
- Ksh 2,888,620
- estimate
- Ksh 4,984,636
Nyabisia/Nyamagundo
- location
-
Masige East
(in Bobasi)
- year first funded
- 2005
- action
- Lay Pipe Culverts
- output
- Ease Communication
- implementation status
- Complete & In Use
- total cost
- Ksh 2,638,825
- estimate
- Ksh 2,638,825
Nyamagwa Boys Secondary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2003
- action
- Construction of Dormitory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 2,600,000
- estimate
- Ksh 2,600,000
Nyamache Social Hall
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Repair The Social Hall
- output
- Provide A Sound Gathering Facility
- implementation status
- Complete & In Use
- total cost
- Ksh 2,042,795
- estimate
- Ksh 2,042,795
Motonto Dispensary
- location
-
Nangiti
(in Bobasi)
- year first funded
- 2009
- action
- Construction of Dispensary
- output
- Good Health Facility
- implementation status
- New
- total cost
- Ksh 2,000,000
- estimate
- Ksh 2,000,000
Rusinga Dispensary
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2006
- action
- Construction of 4 Roomed Out Patient Unit
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 1,954,323
- estimate
- Ksh 1,955,312
Mosora/Igare, Nyamache/Borangi P/ Mochengo,Nyacheki/Subugo,Nyamache/Gionseri/Nyabisia roads
- location
-
Masige East
(in Bobasi)
- year first funded
- 2006
- action
- Put Maram On Road, Grade & Shape
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 1,938,788
- estimate
- Ksh 2,005,788
Nyakegogi Dispensary
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 4 Roomed Out Patient Unit
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 1,907,130
- estimate
- Ksh 1,907,130
Omosaria Dispensary
- location
-
Masige West
(in Bobasi)
- year first funded
- 2004
- action
- Construction of Dispensary
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 1,907,129
- estimate
- Ksh 1,907,129
Gesure Dispensary
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Staff Houses
- output
- -
- implementation status
- Ongoing
- total cost
- Ksh 1,895,812
- estimate
- Ksh 1,940,000
Itibonge Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2003
- action
- Construction of 5 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 1,863,692
- estimate
- Ksh 500,000
Sameta Secondary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2006
- action
- Completion Of Social Hall
- output
- Improved Education Standards
- implementation status
- Ongoing
- total cost
- Ksh 1,600,000
- estimate
- Ksh 7,000,000
Kiobegi Dispensary
- location
-
Masige East
(in Bobasi)
- year first funded
- 2006
- action
- Construction of 4 Roomed Out Patient Unit
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 1,600,000
- estimate
- Ksh 1,600,000
Motonto Dispensary
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Twin Staff House
- output
- -
- implementation status
- Ongoing - Plumbing & Finishing Touches.
- total cost
- Ksh 1,578,577
- estimate
- Ksh 1,685,000
Kionyo Health Centre
- location
-
Masige East
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Twin Staff House
- output
- -
- implementation status
- Ongoing - Painting & Finishing Touches Not Done
- total cost
- Ksh 1,500,000
- estimate
- Ksh 1,500,000
Rigo Gravity Water Ph
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2006
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 1,499,000
- estimate
- Ksh 1,499,000
Nyansiaka Dispensary
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2004
- action
- Electrical Wiring & Electricty Connection
- output
- Improvedd Facility.
- implementation status
- Complete & In Use
- total cost
- Ksh 1,469,458
- estimate
- Ksh 1,469,458
Rigo Gravity Water Ph
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2004
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 1,464,857
- estimate
- Ksh 1,464,857
Kenyerere Dispensary
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Maternity Wing
- output
- -
- implementation status
- Ongoing - Plastering, Floor , Painting & Fixtures Not Yet Done
- total cost
- Ksh 1,200,000
- estimate
- Ksh 2,000,000
Riyabo Dispensary
- location
-
Masige West
(in Bobasi)
- year first funded
- 2006
- action
- Construction of 4 Roomed Out Patient Unit
- output
- -
- implementation status
- Ongoing - Painting & Finishing Touches Not Done
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,200,000
Mtondo Tea Nursery
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2005
- action
- Plant Tea Nursery
- output
- Poverty Eradication
- implementation status
- Complete & In Use
- total cost
- Ksh 1,184,154
- estimate
- Ksh 1,200,000
Sameta Secondary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2008
- action
- Repair 2 Dormitories Burnt Down By Arsonist
- output
- Avail Accomaodatiopn For Students
- implementation status
- Complete And In Use
- total cost
- Ksh 800,000
- estimate
- Ksh 0
Nyagancha Dok Secondary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2004
- action
- Laboratory Completion & Fiitings, Construction of One Class Room
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 800,000
- estimate
- Ksh 800,000
Gucha District Hospital
- location
-
Ogembo Township
(in Bobasi)
- year first funded
- 2004
- action
- Completion Of Wards
- output
- Increase The In Patient Facility
- implementation status
- Complete & In Use
- total cost
- Ksh 750,000
- estimate
- Ksh 750,000
Nyamokenye D Dispensary
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2008
- action
- Extra Costs - Excavation Of Hospital Site.
- output
- Bring Health Facility Close To The People
- implementation status
- Ongoing
- total cost
- Ksh 727,000
- estimate
- Ksh 0
Nyagesa - Gesure Road
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2007
- action
- Reshaping Of 7Kms Of The Road
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 700,000
- estimate
- Ksh 700,000
Nyamache Sub Dmortuary
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- Electrical Wiring
- output
- Improvedd Facility.
- implementation status
- Complete & Not In Use
- total cost
- Ksh 619,784
- estimate
- Ksh 619,784
Nyamagwa Girls Secondary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Borangi Secondary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2007
- action
- Construction of Library
- output
- -
- implementation status
- Ongoing
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Nyakondiere Deb Primary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 6 Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing - Plastering, Painting & Fixtures Not Done.
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
St. Teresas Nyangusu Girls Secondary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2006
- action
- Construction of One Floor -4 Classes On The Storied Building.
- output
- Improved Education Standards
- implementation status
- Ongoing - Slab Completed. Wall Structure, Fixtures And Finishing Not Done.
- total cost
- Ksh 600,000
- estimate
- Ksh 1,600,000
Rianchore Mixed Secondary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Nyakegogi Secondary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Mosora/Igare, Nyamache/Gionseri/Nyabisia roads
- location
-
Masige West
(in Bobasi)
- year first funded
- 2006
- action
- Clearing And Re Shaping
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 590,600
- estimate
- Ksh 590,600
Nyamuya Secondary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2003
- action
- Plastering and flooring for 5 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Ebiosi Secondary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- -
- implementation status
- Ongoing
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Ekeonga Secondary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2003
- action
- Floor & Plaster Classrooms, Fix 12 Windows & 3 Doors
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Gekongo Secondary School
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 3 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Gesure Secondary School
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Ongoing - Plastering, Painting Not Done.
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Kenyoro Dok Secondary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2004
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Nyangusu Secondary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2006
- action
- Construction of 4 Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Orogare Secondary School
- location
-
Masige West
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Ongoing - Fixtures ,Plastering & Painting Not Done.
- total cost
- Ksh 500,000
- estimate
- Ksh 1,200,000
Riobara Secondary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory, Plaster & Floor Four Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
St. Joseph's Nyachenge Secondary School
- location
-
Masige West
(in Bobasi)
- year first funded
- 2005
- action
- Construction of 3 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Sugubo Secondary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Ongoing
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Turwa Secondary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2003
- action
- Construction of Twin Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Nyabite Chiefs Camp
- location
-
Masige East
(in Bobasi)
- year first funded
- 2006
- action
- Construction of A Chief'S Office
- output
- Improved Security
- implementation status
- Stalled - Plastering, Floor , Painting & Fixtures Not Yet Done
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Nyamagwa High Access Road
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2006
- action
- Open Up Feeder Road
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 434,100
- estimate
- Ksh 443,100
Constituency Office
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2009
- action
- Repair Office, Paint, Complete Plumbing System
- output
- Provide A Sound Workin Place
- implementation status
- New
- total cost
- Ksh 417,291
- estimate
- Ksh 750,000
Riamarube Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Rianchaga Primary School
- location
-
Masige West
(in Bobasi)
- year first funded
- 2006
- action
- Construction of 3 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Rigena Adventist Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Rigena PPrimary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Riongoncho Primary School
- location
-
Masige West
(in Bobasi)
- year first funded
- 2005
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Riyabo Primary School
- location
-
Masige West
(in Bobasi)
- year first funded
- 2006
- action
- Construction of 6 Roomed Admn. Block
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Sindagogi Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2006
- action
- Construction of 4 Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing - Plastering, Painting & Fixtures Not Done.
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Nyachogochogo Dispensary
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2007
- action
- Plaster, Floor, Replace Worn Out Roof And Sanitation - Maternity Wing
- output
- -
- implementation status
- Ongoing - Plastering, Roof Replacement, Painting & Sanitation Not Done
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Birongo Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2006
- action
- Repair & Renovate 8 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Chiengu Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 6 Roomed Admni. Block
- output
- -
- implementation status
- Ongoing - At Lintel Stage
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Riamang'Erere Primary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 2 Classrooms & 3 Roomed Admnistration Block
- output
- Improved Education Standards
- implementation status
- Ongoing
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Riamanono Primary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 2 Classrooms & Office Block
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Obuya Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 4 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Bosansa Primary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2005
- action
- Construction of 5 Roomed Admn. Block
- output
- -
- implementation status
- Ongoing - Plastering, Painting & Fixtures Not Done.
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Giasaiga Deb Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2004
- action
- Plaster & Floor 4 Classrooms, Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing - At Lintel Stage
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Keera Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Mosasa Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- Construction of 3 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Nyaguku Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2004
- action
- Plaster & Floor 4 Classrooms & Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Nyaineke Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Nyakunguru Primary School
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2004
- action
- Construction of Ecd Classrooms & Complete 2 Classes
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Nyamatira Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Nyambunde Dok Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 2 Classrooms, Admni. Block
- output
- Improved Education Standards
- implementation status
- Ongoing - Plastering, Painting & Fixtures Not Done.
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Nyambunwa Primary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2005
- action
- Construction of 3 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Nyamokenye Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2003
- action
- Plastering and flooring for 4 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Nyamonema Primary School
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2006
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Nyangusu Springs
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2005
- action
- n/a
- output
- Provision Of Clean Water
- implementation status
- Stalled - Tank Not Done, A Fewest Pipes Laid, Spring Protection Done
- total cost
- Ksh 315,500
- estimate
- Ksh 1,600,000
Rusinga Secondary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Naikuru Secondary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Boitangare Secondary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Ebigogo Secondary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2003
- action
- Floor & Plaster 5 Classrooms, Fix 20 Windows & 5 Doors
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Emenwa Secondary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Laboratory
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Getai Secondary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 6 Roomed Admn. Block
- output
- Improved Education Standards
- implementation status
- Ongoing - At Lintel Stage.
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Getenga Primary School
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2005
- action
- Repair & Renovate 2 Classrooms,Construction of Admni Block
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Getenga Secondary School
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2007
- action
- Construction of Admnistration Block
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Ikenye Secondary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Itumbe Dok Secondary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2004
- action
- Floor, Plaster & Doors And Windows In 4 Classes And Office
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kegochi Secondary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 6 Roomed Admn. Block
- output
- Improved Education Standards
- implementation status
- Ongoing - At Foundation Stage.
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kenyerere Secondary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kiongongi Secondary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Maji-Mazuri Secondary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Mochengo Secondary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Mogonga Secondary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyabete Dok Secondary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2003
- action
- Lab Fiitings & Construction of Library
- output
- Improved Education Standards
- implementation status
- Ongoing - Library
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyabonge Secondary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyaboterere Secondary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing - Plastering, Paint Not Done.
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyachogochogo Aic Secondary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2004
- action
- Completion Of 4 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyagancha Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2005
- action
- Repair, Plaster & Floor 4 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyagiki Secondary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyaguku Secondary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2007
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyamonema Secondary School
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyangusu Advmixed Boarding Primary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2005
- action
- Renovation Of Dormitory
- output
- Improved Education Standards
- implementation status
- Ongoing
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyoera Secondary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Riambase Secondary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2007
- action
- Plaster & Floor 4 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Rigena Secondary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2003
- action
- Construction of Multi Purpose Hall
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Sameta Mixed Secondary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2007
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Ongoing- At Lintel Stage
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
St. Charles Kabeo Secondary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
St. Gabriel Riyabo Secondary School
- location
-
Masige West
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Suguta Secondary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Laboratory
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyansakia Water
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2003
- action
- n/a
- output
- -
- implementation status
- Stalled - Tank Poorly Build And In Complete.
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
St. Teresas Nyangusu Girls
- location
-
Rigena
(in Bobasi)
- year first funded
- 2004
- action
- Construction of Bore Hall
- output
- Provision Of Clean Water
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
St. Peter's Rianyachuba Secondary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2005
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Rogongo Secondary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2007
- action
- Plaster, Foor, Roof And Fixtures Of Multi Purpose Hall
- output
- Improved Education Facilities
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Constituency Office
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Build Constituency Office
- output
- Provide Woking Place
- implementation status
- Complete & In Use
- total cost
- Ksh 259,044
- estimate
- Ksh 259,044
Sugubo Secondary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2006
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyansakia Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing - Plastering, Painting & Fixtures Not Done.
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyantira Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyanuguti Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyaronge Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyoera Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2007
- action
- Plaster & Floor 8 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Oganda Primary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ombondo Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Omosaria Primary School
- location
-
Masige West
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Orogare Primary School
- location
-
Masige West
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 4 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Riakerongo Primary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Riambase Primary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2006
- action
- Plaster & Floor 8 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 400,000
Riamotari Primary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Rianchore Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Rianyachuba Primary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Rikura Primary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Riobara Primary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Riontweka Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Rogongo Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Admnistration Block
- output
- Improved Education Standards
- implementation status
- Ongoing - Inner Doors, Ceiling,Plastering, Floor & Painting Not Done.
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Rusinga Primary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Sameta BoardingPrimary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Sameta Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2007
- action
- Plaster, Floor & Fixtures For 4 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
St. Joseph's Nyamagwa Mixed Primary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Sugubo Primary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Suguta Dok Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2004
- action
- Floor, Plaster, Fix Doors And Windows In 6 Classes
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Turwa Primary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing - Plastering, Painting & Fixtures Not Done.
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Mokwerero Chiefs Office
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2007
- action
- Construction of A Chief'S Office
- output
- -
- implementation status
- Stalled - 3 Rooms Plastering & Painting Not Done
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyamagwa Girls Brimary
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2006
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Metengero Dok Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2006
- action
- Complete Classrooms
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Constituency Office
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2009
- action
- Construct Office Toilets
- output
- Provide A Sound Workin Place
- implementation status
- New
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Bendere Primary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2004
- action
- Construction of Admnistration Block
- output
- Avail Working Space
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Boitangare Primary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2007
- action
- Construction of Classrooms
- output
- -
- implementation status
- Ongoing
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Bonyancha Primary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Borangi Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 2 Roomed Ecd Class
- output
- -
- implementation status
- Ongoing - Plastering, Painting & Fixtures Not Done.
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ebigogo Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ebiosi Primary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2007
- action
- Plaster & Floor 8 Classrooms
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Eburi Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Plaster & Floor 7 Classes
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ekenyoru Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- Construction of 2 Classrooms
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ekeonga Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 7 Roomed Admin. Block
- output
- -
- implementation status
- Ongoing - At Lintel Stage
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Emenwa Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 2 Roomed Ecd Class
- output
- -
- implementation status
- Ongoing - Plastering, Painting & Fixtures Not Done.
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ensoko Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Gekongo Sda Primary School
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 9 Toilets
- output
- Improved Hygiene
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Gesure Primary School
- location
-
Nyang'Ti
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Getai Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Getare Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Getunwa Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Goroba Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2007
- action
- Plaster & Floor 8 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ikenye Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing - Plastering, Painting & Fixtures Not Done
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Itumbe Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2007
- action
- Plaster & Floor 8 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kegochi Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Keigamere Primary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kenyerere Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kenyoro Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2007
- action
- Plaster, Floor & Fixtures For 5 Classrooms, Roof 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kionduso Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kiongeti Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2004
- action
- Construction of 3 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kiongongi Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Maji-Mazuri Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Mitengero Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Mochengo Pag Primary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2004
- action
- Floor & Plaster 7 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Mogonga Primary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2007
- action
- Plaster & Paint 8 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Mokarate Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2004
- action
- Construction of Administration Block
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Naikuru Primary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2007
- action
- Floor & Plaster 5 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyabigonkoru Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2004
- action
- Completion Of 4 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyabiosi Sda Primary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2004
- action
- Floor & Plaster 9 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyabite Dok Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2006
- action
- Plaster 4 Classrooms And Repair Roof
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyabonge Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyaboterere Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2004
- action
- Construction of Admnistration Block
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyachogochogo Primary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyagesa Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2003
- action
- Floor & Plaster 6 Classrooms, Fix 24 Windows & 6 Doors
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyakegarakemo Primary School
- location
-
Masige West
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyakegogi Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2003
- action
- Floor & Plaster 4 Classrooms, 8 Steel Windows & 4 Doors
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyakona Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyamagwa Girls BPrimary School
- location
-
Bassi Boitangare
(in Bobasi)
- year first funded
- 2003
- action
- Construction of Kitchen, Water Tank
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyamarambe Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2006
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyamaruma Primary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyamisaro Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyamuya Primary School
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyamware Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyachenge Primary School
- location
-
Masige West
(in Bobasi)
- year first funded
- 2007
- action
- Construction of 2 Classrooms
- output
- Improved Education Standards
- implementation status
- Ongoing - Plastering, Painting & Fixtures Not Done.
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyangusu Day Primary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Getome Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2005
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Nyangusu Police Staff House
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2008
- action
- Roofing Of Staff House
- output
- Improved Security
- implementation status
- Ongoing - Roof Not Completed
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Mortuary
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- Connect Electricty
- output
- Improved Facility.
- implementation status
- Complete & Not In Use
- total cost
- Ksh 116,085
- estimate
- Ksh 116,085
Nyabite Secondary School
- location
-
Masige East
(in Bobasi)
- year first funded
- 2004
- action
- Connect Electricty To School
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kenyoro Dok Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2004
- action
- Plaster 2 Classrooms
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Nyamware Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2004
- action
- Repair Classes Blown Off By Winds.
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Itumbe Dok Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2004
- action
- Renovate & Repair Classrooms
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Bendere Primary School
- location
-
Bassi Bogetaorio
(in Bobasi)
- year first funded
- 2005
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Nyamarambe Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2005
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Riamarube Primary School
- location
-
Mokwerero
(in Bobasi)
- year first funded
- 2005
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Nyagiki Sda Primary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2005
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Rogongo Primary School
- location
-
Rigena
(in Bobasi)
- year first funded
- 2006
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Riontweka Dok Primary School
- location
-
0
(in Bobasi)
- year first funded
- 2006
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Ensoko Primary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- n/a
- output
- -
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Gionseri Youth Polytechnic
- location
-
Masige West
(in Bobasi)
- year first funded
- 2007
- action
- Roof, Plaster And Put Fixtures To 2 Classrooms
- output
- -
- implementation status
- Stalled - Plastering, Fixtures, Painting Not Done.
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Bassi Borabu Chiefs Office
- location
-
Bassi Borabu
(in Bobasi)
- year first funded
- 2007
- action
- Construction of A Chief'S Office
- output
- -
- implementation status
- Stalled - Materials On Ground.
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Bassi Chache Chiefs Office
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2007
- action
- Construction of A Chief'S Office
- output
- -
- implementation status
- Stalled - 3 Rooms At Lintel Stage
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Rigena Chiefs Office
- location
-
Rigena
(in Bobasi)
- year first funded
- 2007
- action
- Construction of A Chief'S Office
- output
- -
- implementation status
- Stalled - 3 Rooms At Lintel Stage
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
St. Kayuse Nyakegogi Dispensary
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2007
- action
- Completion & Purchase Furniture For Dispensary
- output
- Provision Of Health Services
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Sameta Mixed Secondary School
- location
-
Bassi Chache
(in Bobasi)
- year first funded
- 2005
- action
- Connect Electricty To School
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Maji Mazuri Secondary School
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2005
- action
- Connect Electricty To School
- output
- Improved Education Standards
- implementation status
- Complete & In Use
- total cost
- Ksh 47,560
- estimate
- Ksh 47,560
Constituency Office
- location
-
Bassi Central
(in Bobasi)
- year first funded
- 2006
- action
- Connect Electricty
- output
- Improved Facility.
- implementation status
- Comlete & In Use
- total cost
- Ksh 38,640
- estimate
- Ksh 38,640
Itumbe Dispensary
- location
-
Bassi Central
(in Bobasi)
- action
- Construction of Staff Houses
- output
- -
- implementation status
- New
- total cost
- Ksh 0
- estimate
- Ksh 500,000
Nyangusu Dispensary
- location
-
Bassi Bogetaorio
(in Bobasi)
- action
- Construction of Dispensary
- output
- Bring Health Facility Close To The People
- implementation status
- New
- total cost
- Ksh 0
- estimate
- Ksh 1,200,000
St. Kizito Youth Polytechnic
- location
-
Bassi Boitangare
(in Bobasi)
- action
- Purchase Equipments
- output
- Improved Education Standards
- implementation status
- New
- total cost
- Ksh 0
- estimate
- Ksh 200,000
Isamwera Youth Polytechnic
- location
-
Nyang'Ti
(in Bobasi)
- action
- Construction of A Workshop & Classroom
- output
- Provide Necessary Skills
- implementation status
- New
- total cost
- Ksh 0
- estimate
- Ksh 300,000
Nyangusu Police Post
- location
-
Bassi Bogetaorio
(in Bobasi)
- action
- Construction of A Police Post
- output
- -
- implementation status
- New
- total cost
- Ksh 0
- estimate
- Ksh 1,000,000
Subugo Dispensary
- location
-
Bassi Borabu
(in Bobasi)
- action
- Construction of Dispensary
- output
- -
- implementation status
- New
- total cost
- Ksh 0
- estimate
- Ksh 1,200,000