The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.

It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

Projects in Butere

Bursary

location
Butere (in Butere)
year first funded
2005
action
n/a
output
-
implementation status
not known
total cost
Ksh 11,000,000
estimate
Ksh 0

Emergency Fund

location
Butere (in Butere)
year first funded
2004
action
n/a
output
-
implementation status
Work satisfactorily done
total cost
Ksh 8,172,595
estimate
Ksh 0

Water And Boreholes

location
Butere (in Butere)
year first funded
2004
action
Protection Of Springs
output
Springs
implementation status
Ongoing
total cost
Ksh 7,000,000
estimate
Ksh 5,000,000

Imanga Market

location
Marama Central (in Butere)
year first funded
2005
action
Power Connection To The Market.
output
Electricity
implementation status
Complete
total cost
Ksh 6,000,000
estimate
Ksh 1,000,000

Mabole Health Centre

location
Shianda (in Butere)
year first funded
2005
action
Construction Of Health Centre Service Block
output
Health Centre Block
implementation status
Nearing Completion
total cost
Ksh 6,000,000
estimate
Ksh 3,500,000

Electrof Projects

location
Butere (in Butere)
year first funded
2007
action
n/a
output
-
implementation status
Money to be recovered
total cost
Ksh 5,000,000
estimate
Ksh 0

Muyundi, Mukangu Bridge

location
Marenyo (in Butere)
year first funded
2005
action
Construction Of A Bridge
output
Bridge
implementation status
Complete
total cost
Ksh 5,000,000
estimate
Ksh 3,000,000

Eshimukoko Health Centre

location
Marama North (in Butere)
year first funded
2005
action
Construction Of Health Centre Service Block And Doctors Quarters
output
Health Centre Service Block And Doctors Quarters
implementation status
Health Centreservice Block Is Complete Is Complete. Doctors Quters Is Nearing Completion
total cost
Ksh 5,000,000
estimate
Ksh 3,500,000

Lukohe Health Centre

location
Marama North (in Butere)
year first funded
2005
action
Construction Of A Health Centre Service Block
output
Health Centre
implementation status
Complete
total cost
Ksh 5,000,000
estimate
Ksh 3,500,000

Office Administration

location
Butere (in Butere)
year first funded
2003
action
Office Expenditure
output
Office Expenditure
implementation status
Second hand deep freezers not cold storage
total cost
Ksh 4,940,597
estimate
Ksh 0

Butere District Hospital

location
Township (in Butere)
year first funded
2005
action
Construction Of X-Ray Building
output
X-Ray Building
implementation status
Complete
total cost
Ksh 4,000,000
estimate
Ksh 1,500,000

Eshitsitswi Health Centre

location
Marama Central (in Butere)
year first funded
2004
action
Construction Of Health Centre Service Block
output
Health Centre Service Block
implementation status
Complete
total cost
Ksh 3,000,000
estimate
Ksh 3,500,000

Monitoring And Evaluation

location
Butere (in Butere)
year first funded
2006
action
n/a
output
-
implementation status
PMC are yet to start spending the last Ksh.500,000
total cost
Ksh 2,950,000
estimate
Ksh 0

Shianda Primary School

location
Shianda (in Butere)
year first funded
2005
action
Construction Of 8 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 2,800,000
estimate
Ksh 2,400,000

Bukolwe Secondary School

location
Marama Central (in Butere)
year first funded
2005
action
Construction Of A Dining Hall
output
Dining Hall
implementation status
Nearing Completion
total cost
Ksh 2,500,000
estimate
Ksh 1,500,000

Buchenya Girls' Secondary School

location
Marama West (in Butere)
year first funded
2004
action
Construction Of A Hall And Renovation Of 8 Classrooms
output
Hall And 8 Clasrooms
implementation status
Complete
total cost
Ksh 2,500,000
estimate
Ksh 2,500,000

Eshisisia Primary School

location
Marenyo (in Butere)
year first funded
2006
action
Construction Of 8 Classrooms And An Administration Block
output
Classrooms And Administration Block
implementation status
4 Classrooms Are Complete. The Other 4 And Administration Block Are Nearing Completeion
total cost
Ksh 2,400,000
estimate
Ksh 2,300,000

Emashere Primary School

location
Marama North (in Butere)
year first funded
2006
action
Construction Of 8 Classrooms
output
Classrooms
implementation status
Nearing Completion
total cost
Ksh 2,300,000
estimate
Ksh 2,300,000

St. shikunga Secondary School

location
Marenyo (in Butere)
year first funded
2004
action
Construction Of 3 Classrooms And Renovation 6 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 2,200,000
estimate
Ksh 600,000

Mwilala Primary School

location
Marama North (in Butere)
year first funded
2006
action
Construction Of 6 Classrooms
output
Classrooms
implementation status
Nearing Completion
total cost
Ksh 2,200,000
estimate
Ksh 1,500,000

Mabole Primary School

location
Shianda (in Butere)
year first funded
2006
action
Construction Of 5 Classrooms
output
Classrooms
implementation status
Nearing Completion
total cost
Ksh 2,100,000
estimate
Ksh 700,000

Eshikholobe Primary School

location
Marama North (in Butere)
year first funded
2006
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Nearing Completion
total cost
Ksh 2,100,000
estimate
Ksh 1,500,000

Iranda Primary School

location
Marama West (in Butere)
year first funded
2005
action
Construction Of 4 Classrooms And An Administration Block
output
Classrooms And Administration Block
implementation status
Complete
total cost
Ksh 2,090,000
estimate
Ksh 1,290,000

Shiraha Secondary School

location
Marama North (in Butere)
year first funded
2005
action
Construction Of A Laboratory And 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 2,050,000
estimate
Ksh 1,500,000

Ibokolo Secondary School

location
Marama Central (in Butere)
year first funded
2005
action
Power Connection To The School
output
Electricity
implementation status
Complete
total cost
Ksh 2,040,760
estimate
Ksh 2,040,760

Eshisaba Health Centre

location
Marama West (in Butere)
year first funded
2007
action
Construction Of A Health Centre Service Block
output
Health Centre
implementation status
Roofed,Floor Slab Casted, Doors And Windows Fixed,Walls Plastered
total cost
Ksh 2,000,000
estimate
Ksh 2,000,000

Mukoye Girls Secondary School

location
Manyala (in Butere)
year first funded
2008
action
Construction Of A Storey Classrooms
output
Storey Classrooms
implementation status
At Substructure Level
total cost
Ksh 2,000,000
estimate
Ksh 1,000,000

Manyala Secondary School

location
Manyala (in Butere)
year first funded
2006
action
Construction Of A Library
output
Library
implementation status
Complete
total cost
Ksh 2,000,000
estimate
Ksh 500,000

Ikokwa Primary School

location
Shianda (in Butere)
year first funded
2006
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 2,000,000
estimate
Ksh 700,000

Iranda Health Centre

location
Marama West (in Butere)
year first funded
2008
action
Construction Of A Health Centre Service Block
output
Health Centre
implementation status
At Ring Beam Level
total cost
Ksh 2,000,000
estimate
Ksh 4,000,000

Shibimbi Health Centre

location
Marama North (in Butere)
year first funded
2008
action
Construction Of A Health Centre Service Block
output
Health Centre
implementation status
Ongoing
total cost
Ksh 2,000,000
estimate
Ksh 4,500,000

Eshikomere GSecondary School

location
Marama North (in Butere)
year first funded
2008
action
Construction Of Storey Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 2,000,000
estimate
Ksh 5,000,000

Lukohe Primary School

location
Marama North (in Butere)
year first funded
2007
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Nearing Completion
total cost
Ksh 2,000,000
estimate
Ksh 1,600,000

Shiraha Primary School

location
Marama North (in Butere)
year first funded
2007
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
At Roof Work Level
total cost
Ksh 2,000,000
estimate
Ksh 1,600,000

Manyika Primary School

location
Marama West (in Butere)
year first funded
2006
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,900,000
estimate
Ksh 700,000

Shitari Primary School

location
Marama West (in Butere)
year first funded
2006
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,900,000
estimate
Ksh 700,000

Bulanda Rc Primary School

location
Marama North (in Butere)
year first funded
2007
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Roofed, Floor Slab Casted
total cost
Ksh 1,900,000
estimate
Ksh 1,400,000

Etatira Primary School

location
Manyala (in Butere)
year first funded
2004
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,900,000
estimate
Ksh 700,000

Elukokho Primary School

location
Marama Central (in Butere)
year first funded
2003
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,800,000
estimate
Ksh 500,000

Ematende Primary School

location
Marama West (in Butere)
year first funded
2008
action
Acquistion Of A Land Title Deed And Construction Of 4 Classrooms
output
Title Deed And 4 Classrooms
implementation status
At Wall Plastering Level
total cost
Ksh 1,800,000
estimate
Ksh 1,600,000

Inaya Secondary School

location
Marama North (in Butere)
year first funded
2005
action
Construction Of A Library
output
Library
implementation status
At Plastering Stage
total cost
Ksh 1,800,000
estimate
Ksh 1,000,000

Mahondo Secondary School

location
Marama South (in Butere)
year first funded
2006
action
Completion Of 5 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,800,000
estimate
Ksh 800,000

Eshishebu Primary School

location
Marama South (in Butere)
year first funded
2006
action
Construction Of 5 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,800,000
estimate
Ksh 1,000,000

Eshinamwenyuli Secondary School

location
Township (in Butere)
year first funded
2005
action
Construction Of A Laboratory
output
Laboratory
implementation status
Nearing Completion
total cost
Ksh 1,800,000
estimate
Ksh 700,000

Environmental Conservation

location
Butere (in Butere)
year first funded
2004
action
Tree Planting
output
Improved Improvement
implementation status
Ongoing
total cost
Ksh 1,703,675
estimate
Ksh 0

Bulanda A Secondary School

location
Marama Central (in Butere)
year first funded
2005
action
Construction Of A Library
output
Library
implementation status
Complete
total cost
Ksh 1,700,000
estimate
Ksh 500,000

Education Tour

location
Butere (in Butere)
year first funded
2006
action
Education Tour
output
-
implementation status
funds paid out to non existent project.
total cost
Ksh 1,700,000
estimate
Ksh 1,700,000

Ekendero Primary School

location
Marama South (in Butere)
year first funded
2005
action
Construction Of 6 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,700,000
estimate
Ksh 1,700,000

Ebukhokoro Primary School

location
Manyala (in Butere)
year first funded
2004
action
Construction Of 6 Classrooms
output
Classrooms
implementation status
Copmlete
total cost
Ksh 1,700,000
estimate
Ksh 900,000

Emunuku Primary School

location
Marama West (in Butere)
year first funded
2006
action
Construction Of 6 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,650,000
estimate
Ksh 1,250,000

Bulanda Ac Primary School

location
Marama Central (in Butere)
year first funded
2007
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
At Roof Work Level
total cost
Ksh 1,600,000
estimate
Ksh 1,600,000

Bukolwe Secondary School

location
Marama Central (in Butere)
year first funded
2005
action
Power Connection To The School
output
Electricity
implementation status
Complete
total cost
Ksh 1,521,645
estimate
Ksh 1,521,635

Bumamu Secondary School

location
Marama West (in Butere)
year first funded
2005
action
Construction Of A Library
output
Library
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 500,000

Ebushitnji Drift

location
Marama North (in Butere)
year first funded
2004
action
Construction Of A Drift And Opening Of The Road On Both Sides
output
Drift
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Ebukuti Primary School

location
Manyala (in Butere)
year first funded
2007
action
Construction Of 5 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 1,600,000

Mabole Secondary School

location
Shianda (in Butere)
year first funded
2008
action
Acquistion Of Title Deed, Construction Of 4 Classrooms - Storey
output
Title Deed And 4 Classrooms
implementation status
At Procurement Stages
total cost
Ksh 1,500,000
estimate
Ksh 3,000,000

Eshilunyire Primary School

location
Marama West (in Butere)
year first funded
2005
action
Construction Of 2 Classrooms And An Administration Block
output
Classrooms And Administration Block
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 500,000

Lunza Secondary School

location
Marama West (in Butere)
year first funded
2007
action
Construction Of A Dining Hall
output
Dining Hall
implementation status
Roofed,Floor Slab Casted, Doors And Windows Fixed
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Eshibimbi Primary School

location
Marama North (in Butere)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,400,000
estimate
Ksh 700,000

Bumamu Primary School

location
Marama West (in Butere)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Roofed,Floor Slab Casted
total cost
Ksh 1,400,000
estimate
Ksh 700,000

Nyenyesi Primary School

location
Marama Central (in Butere)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,400,000
estimate
Ksh 700,000

Eshikulu Primary School

location
Manyala (in Butere)
year first funded
2006
action
Construction Of 3 Classrooms And Renovation Of 2 Class
output
Clasrooms
implementation status
Complete
total cost
Ksh 1,400,000
estimate
Ksh 800,000

Shiatsa Ds Office

location
Marama South (in Butere)
year first funded
2008
action
Construction Of Do.S Office
output
D.Os Office
implementation status
Ongoing
total cost
Ksh 1,400,000
estimate
Ksh 3,000,000

Shiatsala D's Office

location
Marama South (in Butere)
year first funded
2008
action
Construction Of D.O'S Office
output
D.O'S Office
implementation status
At Roof Work Level
total cost
Ksh 1,400,000
estimate
Ksh 3,000,000

Buboko Primary School

location
Marenyo (in Butere)
year first funded
2006
action
Construction Of Verandah
output
Verandah
implementation status
Complete
total cost
Ksh 1,300,000
estimate
Ksh 700,000

Ebubala Primary School

location
Shianda (in Butere)
year first funded
2006
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,300,000
estimate
Ksh 500,000

Lunza Primary School

location
Marama West (in Butere)
year first funded
2007
action
Construction Of A Veranda
output
Verandah
implementation status
Complete
total cost
Ksh 1,300,000
estimate
Ksh 300,000

Eshihanza Primary School

location
Marama Central (in Butere)
year first funded
2005
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,300,000
estimate
Ksh 500,000

Shitsitswi Primary School

location
Marama Central (in Butere)
year first funded
2007
action
Renovation And Construction Of 2 Classrooms
output
Classrooms
implementation status
Renovation Complete, Construction Of 2 Classrooms- Roofed, Floor Slab Casted
total cost
Ksh 1,300,000
estimate
Ksh 1,200,000

Shinamwenyuli Primary School

location
Township (in Butere)
year first funded
2006
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,200,000
estimate
Ksh 700,000

Bululwe Primary School

location
Marama West (in Butere)
year first funded
2006
action
Construction Of 3 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,200,000
estimate
Ksh 700,000

Inaya Primary School

location
Marama North (in Butere)
year first funded
2007
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Roofed,Floor Slab Casted,Doors And Windows Fixed.
total cost
Ksh 1,200,000
estimate
Ksh 1,600,000

Shikunga Primary School

location
Marenyo (in Butere)
year first funded
2007
action
Construction Of 3 Classrooms
output
Classrooms
implementation status
At Wall Plastering Level
total cost
Ksh 1,200,000
estimate
Ksh 1,050,000

Butere Primary School

location
Township (in Butere)
year first funded
2006
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
2 Classroom Are Complete, 2 Arenearing Completion
total cost
Ksh 1,200,000
estimate
Ksh 700,000

Muyundi Primary School

location
Marenyo (in Butere)
year first funded
2007
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
At Wall Plastering Level
total cost
Ksh 1,200,000
estimate
Ksh 1,000,000

Ebukuti Primary School

location
Manyala (in Butere)
year first funded
2006
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,200,000
estimate
Ksh 1,000,000

Shiatsala Primary School

location
Marama South (in Butere)
year first funded
2006
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,200,000
estimate
Ksh 1,200,000

Bumamu Secondary School

location
Marama West (in Butere)
year first funded
2004
action
Power Connection To The School
output
Electricity
implementation status
Complete
total cost
Ksh 1,174,822
estimate
Ksh 1,174,822

Mutoma Primary School

location
Township (in Butere)
year first funded
2004
action
Construction Of 2 Classroms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,100,000
estimate
Ksh 500,000

Masaba Primary School

location
Marama South (in Butere)
year first funded
2007
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
At Roof Work Level
total cost
Ksh 1,100,000
estimate
Ksh 800,000

Shibembe Primary School

location
Marama South (in Butere)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,100,000
estimate
Ksh 500,000

Shianda Chief's Office

location
Shianda (in Butere)
year first funded
2008
action
Construction Of A Chief'S Office
output
Chief'S Office
implementation status
Ongiong
total cost
Ksh 1,100,000
estimate
Ksh 1,600,000

Mutoma Primary School

location
Township (in Butere)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,100,000
estimate
Ksh 500,000

Eshirembe Primary School

location
Township (in Butere)
year first funded
2004
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,100,000
estimate
Ksh 1,000,000

Eshitoyi Primary School

location
Marama West (in Butere)
year first funded
2005
action
Construction Of 2 Classrooms And Completion Of Office Block
output
Classrooms And Administration Block
implementation status
2 Classroms Are Complete, Office Block Is Nearing Completion
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Imanga Health Centre

location
Marama Central (in Butere)
year first funded
2009
action
Construction Of A Health Centre Service Block
output
Health Centre
implementation status
At Procurement Stages
total cost
Ksh 1,000,000
estimate
Ksh 4,500,000

Emauko Primary School

location
Marama South (in Butere)
year first funded
2006
action
Renovation Of 8 Classrooms And Construction Of Toilets
output
Classrooms And Toilets
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 800,000

Manyala Primary School

location
Manyala (in Butere)
year first funded
2006
action
Renovation Of 8 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 500,000

Eshitsakha Primary School

location
Shianda (in Butere)
year first funded
2005
action
Construction Of 4 Classrooms
output
Classooms
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Eshirumba Primary School

location
Marenyo (in Butere)
year first funded
2005
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Bukolwe Primary School

location
Marama Central (in Butere)
year first funded
2008
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
At Procurement Stages
total cost
Ksh 1,000,000
estimate
Ksh 800,000

Ituti Primary School

location
Marama West (in Butere)
year first funded
2005
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Emukangu Primary School

location
Marama West (in Butere)
year first funded
2005
action
Construction Of 1 Classroom And Renovation Of 6 Classrooms
output
Classroom
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 500,000

Lunz Ds Office

location
Marama West (in Butere)
year first funded
2009
action
Construction Of Ad.Os Office
output
D.Os Office
implementation status
Work Yet To Start
total cost
Ksh 1,000,000
estimate
Ksh 3,000,000

Ibokolo Ds Office

location
Marama Central (in Butere)
year first funded
2005
action
Construction Of A D.Os Office Block
output
Office Block
implementation status
Complete
total cost
Ksh 994,000
estimate
Ksh 625,000

Shiatsala Secondary School

location
Marama South (in Butere)
year first funded
2006
action
Construction Of A Library
output
Library
implementation status
Complete
total cost
Ksh 950,000
estimate
Ksh 450,000

Muluwa Primary School

location
Marama Central (in Butere)
year first funded
2004
action
Renovation Of 3 Classroomsand Construction of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 905,000
estimate
Ksh 585,000

Lufumbo Primary School

location
Marama North (in Butere)
year first funded
2007
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Roofed,Floor Slab Casted, Doors And Windows Fixed
total cost
Ksh 900,000
estimate
Ksh 700,000

Marenyo Primary School

location
Marenyo (in Butere)
year first funded
2006
action
Renovation Of 8 Classrooms
output
Classroom
implementation status
Complete
total cost
Ksh 900,000
estimate
Ksh 500,000

Shinyulu Primary School

location
Marenyo (in Butere)
year first funded
2004
action
Purchase Of 200 Iron Sheets And Renovation Of 2 Classroos
output
Classrooms
implementation status
Complete
total cost
Ksh 900,000
estimate
Ksh 300,000

Ibokolo Primary School

location
Marama Central (in Butere)
year first funded
2007
action
Construction Of 2 Clsaarooms
output
Classrooms
implementation status
Complete
total cost
Ksh 900,000
estimate
Ksh 500,000

Bukura Primary School

location
Marama North (in Butere)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Roofed,Floor Slab Casted
total cost
Ksh 900,000
estimate
Ksh 700,000

Jua Kali Sheds

location
Butere (in Butere)
year first funded
2004
action
n/a
output
-
implementation status
not known
total cost
Ksh 850,000
estimate
Ksh 0

Ematawa Primary School

location
Marama Central (in Butere)
year first funded
2004
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 700,000

Mukoye Primary School

location
Manyala (in Butere)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 800,000

Ebutsetse Primary School

location
Shianda (in Butere)
year first funded
2009
action
Construction Of 8 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 800,000
estimate
Ksh 2,800,000

Shibanga Primary School

location
Marama Central (in Butere)
year first funded
2008
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Roofed,Floor Slab Casted, Doors And Windows Fixed
total cost
Ksh 800,000
estimate
Ksh 800,000

Imanga Primary School

location
Marama West (in Butere)
year first funded
2005
action
Renovation Of 8 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 600,000

Ebutayi Primary School

location
Marama North (in Butere)
year first funded
2008
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
At Plastering Stage
total cost
Ksh 800,000
estimate
Ksh 800,000

Eshirakalu Primary School

location
Marama North (in Butere)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 700,000

Eshilunyire Primary School

location
Marama West (in Butere)
year first funded
2008
action
Construction Of An Adminstration Block
output
Adminstration Block
implementation status
Complete
total cost
Ksh 700,000
estimate
Ksh 700,000

Butunyi Primary School

location
Marama North (in Butere)
year first funded
2007
action
Renovation Of 8 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 700,000
estimate
Ksh 800,000

Manyulia Primary School

location
Shianda (in Butere)
year first funded
2005
action
Renovation Of 8 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 685,000
estimate
Ksh 685,000

Purchase Of Motor Cycles

location
Butere (in Butere)
year first funded
2005
action
Purchase Of 2 Motor Cycles
output
Motor Cycles
implementation status
Complete
total cost
Ksh 629,498
estimate
Ksh 629,498

Mahondo Primary School

location
Marama South (in Butere)
year first funded
2007
action
Renovation Of Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 600,000
estimate
Ksh 600,000

Ibokolo Secondary School

location
Marama Central (in Butere)
year first funded
2003
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 600,000
estimate
Ksh 600,000

Eshikomere Primary School

location
Marama North (in Butere)
year first funded
2006
action
Construction Of 2 Clsassrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 600,000
estimate
Ksh 500,000

Eshikolobe Primary School

location
Marama North (in Butere)
year first funded
2005
action
Construction Of Water Well And Instalation Of Water Pump
output
Water
implementation status
Complete
total cost
Ksh 579,000
estimate
Ksh 79,000

Emusunguri Primary School

location
Marama North (in Butere)
year first funded
2005
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 500,000

Shitari Secondary School

location
Marama West (in Butere)
year first funded
2008
action
Completion Of The Adminstration Block
output
Adminstration Block
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 800,000

Bumamu Secondary School

location
Marama West (in Butere)
year first funded
2009
action
Construction Of A Library
output
A Library
implementation status
At Ring Beam Level
total cost
Ksh 500,000
estimate
Ksh 1,500,000

Marama South Youth Polytechnic

location
Marama South (in Butere)
year first funded
2009
action
Construction Of 2 Workshops
output
Workshops And Equipments
implementation status
Work Yet To Start
total cost
Ksh 500,000
estimate
Ksh 3,000,000

Ekendero Primary School

location
Marama South (in Butere)
year first funded
2008
action
Construction Of Adminstration Block
output
Adminstration Block
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 500,000

Butere Primary School

location
Township (in Butere)
year first funded
2008
action
Completion Of Painting, Starting Of A Classroom
output
Classroom
implementation status
At Roof Work Level
total cost
Ksh 500,000
estimate
Ksh 500,000

Bulanda Youth Polytechnic

location
Marama Central (in Butere)
year first funded
2009
action
Construction Of 2 Workshops
output
Workshops And Equipments
implementation status
Work Yet To Start
total cost
Ksh 500,000
estimate
Ksh 1,000,000

Shibanga Secondary School

location
Marama Central (in Butere)
year first funded
2008
action
Renovation Of 2 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 500,000

Imanga Youth Polytechnic

location
Marama West (in Butere)
year first funded
2009
action
Construction Of 2 Workshops
output
Workshops And Equipments
implementation status
Work Yet To Start
total cost
Ksh 500,000
estimate
Ksh 1,000,000

Shibanga Primary School

location
(in Butere)
year first funded
2004
action
Connection Of Power To The School
output
Electricity
implementation status
Complete
total cost
Ksh 453,000
estimate
Ksh 453,000

Lunza Secondary School

location
Marama West (in Butere)
year first funded
2005
action
Power Connection To The School
output
Electricity
implementation status
Complete
total cost
Ksh 312,960
estimate
Ksh 312,960

Eshirumba Primary School

location
Marenyo (in Butere)
year first funded
2008
action
Construction Of Verandah For 4 Classrooms
output
Verandah
implementation status
Complete
total cost
Ksh 300,000
estimate
Ksh 300,000

Motor Cycle Maintenance

location
Butere (in Butere)
year first funded
2008
action
Maintenance Of 2 Motor Cyles
output
Motor Cycles
implementation status
Minor repairs and some paintings were done on site.
total cost
Ksh 300,000
estimate
Ksh 0

Musere Primary School

location
Marama Central (in Butere)
year first funded
2008
action
Construction Of Verandah For 4 Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 300,000
estimate
Ksh 300,000

Eshirakalu Water Pump

location
Marama North (in Butere)
year first funded
2005
action
Repair Of A Water Pump And Digging Of A Water Well
output
Water
implementation status
Stalled
total cost
Ksh 200,000
estimate
Ksh 200,000

Eshihanza Water Project

location
Marama Central (in Butere)
year first funded
2008
action
Digging Of Water Well
output
Water Well
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 200,000

Shikunga Water Project

location
Marenyo (in Butere)
year first funded
2005
action
Construction Of Weir And Watchman'S House
output
Weir And Watcman'S House
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 320,000

Eshitsitsw Secondary School

location
Marama Central (in Butere)
year first funded
2009
action
Completion Of 2 Classrooms
output
Classrooms
implementation status
Nearing Completion
total cost
Ksh 200,000
estimate
Ksh 200,000

Shibanga Water Project

location
Marama Central (in Butere)
year first funded
2006
action
Diging Of Water Well And Installation Of Water Pump.
output
Water Well And Water Pump
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 200,000

Ebutayi Shallow Well

location
Marama North (in Butere)
year first funded
2005
action
Digging Of Water Well
output
Water
implementation status
Stalled
total cost
Ksh 150,000
estimate
Ksh 150,000

Buchenya Girls' Secondary School

location
Marama West (in Butere)
year first funded
2005
action
Power Connection To The School
output
Electricity
implementation status
Complete
total cost
Ksh 121,000
estimate
Ksh 121,000

Lunza Primary School

location
Marama West (in Butere)
year first funded
2005
action
Power Connection To The School
output
Electricity
implementation status
Complete
total cost
Ksh 121,000
estimate
Ksh 121,000

Buchenya Primary School

location
Marama West (in Butere)
year first funded
2005
action
Power Connection To The School
output
Electricity
implementation status
Copmlete
total cost
Ksh 121,000
estimate
Ksh 121,000

Inaya Secondary School

location
Butere (in Butere)
year first funded
2005
action
Power Connection To The School
output
Electricity
implementation status
Complete
total cost
Ksh 118,839
estimate
Ksh 118,839

Bukura Water Project

location
Marama North (in Butere)
year first funded
2004
action
Diging Of Water Well And Installation Of Water Pump.
output
Water Well And Water Pump
implementation status
Complete
total cost
Ksh 79,000
estimate
Ksh 79,000

Emasuba Community Water Project

location
Marama South (in Butere)
year first funded
2006
action
Construction Of Pump House
output
Pump House
implementation status
Complete
total cost
Ksh 38,520
estimate
Ksh 38,520

Masaba Market Water Project

location
Marama South (in Butere)
year first funded
2006
action
Construction Of Pump House
output
Pump House
implementation status
Complete
total cost
Ksh 38,520
estimate
Ksh 38,520

Lufumbo Community Water Project

location
Marama North (in Butere)
year first funded
2005
action
Purchase And Instalation Of Water Pump
output
Water Pump
implementation status
Complete
total cost
Ksh 35,775
estimate
Ksh 35,775

Mabole Health Centre

location
Shianda (in Butere)
action
Power Connection To The Health Centre
output
Electricity
implementation status
Connection In Progress
total cost
Ksh 0
estimate
Ksh 3,020,000

Honey Refinery Plant

location
Marama West (in Butere)
action
Purchase Of Land
output
Honery Refinery
implementation status
Title Deed Not Colected
total cost
Ksh 0
estimate
Ksh 1,100,000

Elukaka Market

location
Marama North (in Butere)
action
Power Connection To The Market.
output
Electricity
implementation status
Complete
total cost
Ksh 0
estimate
Ksh 2,100,000