The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Kajembe Secondary School
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2003
- action
- Construction Of 2 Labs, Class Rooms, Toilets, Offices, An Ark, Perimeter Wall & Purchase Of Furniture,
- output
- Better Education Facilities.
- implementation status
- Complete And In Use
- total cost
- Ksh 20,700,000
- estimate
- Ksh 35,000,000
Bursary Fund
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2006
- action
- Assistance To Needy Students In The Constituency
- output
- -
- implementation status
- Ongoing
- total cost
- Ksh 16,263,116
- estimate
- Ksh 0
Supply Of Floodlights In The Constituency
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2006
- action
- Put 3 Poles Of Floodlights
- output
- Lit Dark Areas
- implementation status
- Complete And In Use
- total cost
- Ksh 8,700,000
- estimate
- Ksh 0
Kajembe Secondary School
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2007
- action
- Construction Of Multipurpose Hall
- output
- Better Educational Facilities
- implementation status
- Top Slab
- total cost
- Ksh 8,700,000
- estimate
- Ksh 5,000,000
Assistance To Tudor, Khamisi, Baptist, Changamwe, St Charles Lwanga & Miritini Secondary School s
- location
-
Tudor
(in Changamwe)
- year first funded
- 2005
- action
- 1 Classroom Construction For Each School
- output
- Better Education Facilities
- implementation status
- Complete And In Use
- total cost
- Ksh 6,000,000
- estimate
- Ksh 6,000,000
Proposed Construction Of Mrkt At Chaani
- location
-
Kipevu
(in Changamwe)
- year first funded
- 2006
- action
- Construction Of A Market
- output
- Availability Of Clean Market Facilities
- implementation status
- Ongoing
- total cost
- Ksh 5,000,000
- estimate
- Ksh 420,000,000
Electricity
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2009
- action
- Supply Of Electricity Poles At Kwa Shee, Ganahola, Mwakidemu, Airport,Jomvu Kuu, Jomvu Misheni, Mtaa Wa Swahili, Chamunyu Road, Magongo Market, Chaani Market, Changamwe Market, Miritini Health Centre, Bokole Health Centre And Jitengeni
- output
- Lit Dark Areas
- implementation status
- Tendering
- total cost
- Ksh 4,650,000
- estimate
- Ksh 6,000,000
Tudor Social Hall
- location
-
Tudor
(in Changamwe)
- year first funded
- 2009
- action
- Construction Of A Social Hall
- output
- A Gathering Place For Social Cultural Activities
- implementation status
- Tendering
- total cost
- Ksh 4,050,000
- estimate
- Ksh 6,000,000
Construction Of Mwidani Social Hall
- location
-
Portreitz
(in Changamwe)
- year first funded
- 2007
- action
- Hall Construction
- output
- A Gathering Place For Social Cultural Activities
- implementation status
- Complete
- total cost
- Ksh 4,000,000
- estimate
- Ksh 4,500,000
Construction Of A Social Hall At National Housing
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2008
- action
- Hall Construction
- output
- A Gathering Place For Social Cultural Activities
- implementation status
- Tendering
- total cost
- Ksh 4,000,000
- estimate
- Ksh 6,000,000
Market At Changamwe
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2005
- action
- Construction Of A Public Market Grill Gates Construction
- output
- Availability/ Of Clean Market Facilities.
- implementation status
- Complete And Not In Use
- total cost
- Ksh 3,772,639
- estimate
- Ksh 3,272,639
St. Marys Bangladesh
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2007
- action
- Construction Of Classrooms
- output
- Better Educational Facilities
- implementation status
- Ongoing
- total cost
- Ksh 3,500,000
- estimate
- Ksh 3,000,000
Streets Light Supply In The Constituency
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2007
- action
- Fixing Electric Poles
- output
- Power Supply
- implementation status
- Complete And In Use
- total cost
- Ksh 3,200,000
- estimate
- Ksh 3,500,000
Bokole Health Centre
- location
-
Bokole
(in Changamwe)
- year first funded
- 2004
- action
- Construction Of A Health Centre
- output
- Improved Health Facilities
- implementation status
- Ongoing
- total cost
- Ksh 3,000,000
- estimate
- Ksh 4,200,000
Miritini Health Centre
- location
-
Miritini
(in Changamwe)
- year first funded
- 2004
- action
- Construction Of A Health Centre.
- output
- Improved Health Facilities
- implementation status
- On-Going
- total cost
- Ksh 3,000,000
- estimate
- Ksh 4,200,000
Potreitz Medical Training College
- location
-
Portreitz
(in Changamwe)
- year first funded
- 2008
- action
- Construction Of 2 Special Classrooms
- output
- Increase Intake Especially For The Qualified Residents Of Changamwe Constituency
- implementation status
- Classrooms' Contruction In Progress
- total cost
- Ksh 3,000,000
- estimate
- Ksh 3,500,000
Mombasa Polytechnic Generator
- location
-
Tudor
(in Changamwe)
- year first funded
- 2005
- action
- Purchase Of A Generator
- output
- Longer Learning Hrs For Students
- implementation status
- Complete And In Use
- total cost
- Ksh 3,000,000
- estimate
- Ksh 3,000,000
Recurrent Expenses
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2008
- action
- Maintenance Of Office Equipment
- output
- Better Working Condition For The Office
- implementation status
- Ongoing
- total cost
- Ksh 2,507,128
- estimate
- Ksh 0
Storm Water Drains At Wayani
- location
-
Portreitz Wayani
(in Changamwe)
- year first funded
- 2006
- action
- Construction Of Drainage Systems
- output
- To Prevent Floods
- implementation status
- Complete And In Use
- total cost
- Ksh 2,500,000
- estimate
- Ksh 4,000,000
Stlwanga Secondary School s Bus
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2008
- action
- To Purchase School Bus
- output
- Assists Teachers & Students During Educational Tours
- implementation status
- Ongoing
- total cost
- Ksh 2,200,000
- estimate
- Ksh 5,000,000
Kajembe Secondary School s Bus
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2008
- action
- To Purchase School Bus
- output
- Assists Teachers & Students During Educational Tours
- implementation status
- Ongoing
- total cost
- Ksh 2,200,000
- estimate
- Ksh 5,000,000
Miritini Secondary School s Bus
- location
-
Miritini
(in Changamwe)
- year first funded
- 2008
- action
- To Purchase School Bus
- output
- Assists Teachers & Students During Educational Tours
- implementation status
- Ongoing
- total cost
- Ksh 2,200,000
- estimate
- Ksh 5,000,000
Changamwe Secondary School
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2008
- action
- To Purchase School Bus
- output
- Assists Teachers & Students During Educational Tours
- implementation status
- Ongoing
- total cost
- Ksh 2,200,000
- estimate
- Ksh 5,000,000
Equipments For Miritini Health Centre
- location
-
Miritini
(in Changamwe)
- year first funded
- 2007
- action
- Equipping Health Facilities And Digging Placenta Pit And Incinerator
- output
- Better Health Facilities
- implementation status
- 10Metre By 7.5 Metres? Septic Tank Dug, Ceiling, Power Fixation And Water Metre In Progress Soak Pit Dug, Equipped With Furniture
- total cost
- Ksh 2,188,602
- estimate
- Ksh 2,000,000
Equipments For Miritini Health Centre
- location
-
Miritini
(in Changamwe)
- year first funded
- 2007
- action
- Equipping Health Facilities And Digging Placenta Pit And Incinerator
- output
- Better Health Facilities
- implementation status
- 10Metre By 7.5 Metres? Septic Tank Dug, Ceiling, Power Fixation And Water Metre In Progress Soak Pit Dug, Equipped With Furniture
- total cost
- Ksh 2,188,602
- estimate
- Ksh 2,000,000
School's Fence At Amani Primary School
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2007
- action
- Fencing The School With Perimeter Wall
- output
- Conducive Learning Environment
- implementation status
- Ongoing 150 Meters By 2.1 Meters Wall Constructed
- total cost
- Ksh 2,000,000
- estimate
- Ksh 1,000,000
Kajembe Secondary School
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2005
- action
- Purchase Of Furniture
- output
- Creation Of A Conducive Learning Environment
- implementation status
- Complete And In Use
- total cost
- Ksh 2,000,000
- estimate
- Ksh 2,000,000
Road Barriers
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2009
- action
- Construction Of Four Barriers To Protect Heavy Commercial Vehicles From Destroying The Town Plan
- output
- Maintain The Roads
- implementation status
- Tendering
- total cost
- Ksh 2,000,000
- estimate
- Ksh 2,000,000
Mreroni School
- location
-
Miritini
(in Changamwe)
- year first funded
- 2008
- action
- 2 Classrooms Construction
- output
- Better Educational Facilities
- implementation status
- Tendering
- total cost
- Ksh 2,000,000
- estimate
- Ksh 1,000,000
Streets Lights Supply Bangladesh
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2008
- action
- n/a
- output
- Lit Dark Areas
- implementation status
- Tendering
- total cost
- Ksh 1,814,031
- estimate
- Ksh 1,200,000
Sports Activities
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2008
- action
- Purchase Of Balls And Other Sports Facilities, Repairing Sports Facilities And Sports Trucks
- output
- Better Working Environment & Sports Facilities For The Constituency Sports Teams
- implementation status
- Ongoing
- total cost
- Ksh 1,728,291
- estimate
- Ksh 0
Environmental Activities
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2008
- action
- Sensitization Workshop On Maintaining Good Environment
- output
- -
- implementation status
- Cleaning Sewarage System At Bokole And Changamwe Estate ,Planting Trees At Mikindani Primary, Jomvu Kuu Primary
- total cost
- Ksh 1,728,291
- estimate
- Ksh 0
Lab Equipments For Kajembe Secondary School
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2005
- action
- Equipping Of School Lab With Furniture & Other Experimental Materials
- output
- Conducive Environment For The Students When Doing Their Practical Sessions
- implementation status
- Complete And In Use
- total cost
- Ksh 1,500,000
- estimate
- Ksh 1,500,000
Marycliff Primary School
- location
-
Tudor
(in Changamwe)
- year first funded
- 2006
- action
- SchoolS Renovation
- output
- Better Educational Facilities.
- implementation status
- Complete And In Use
- total cost
- Ksh 1,500,000
- estimate
- Ksh 1,500,000
Building A Centre For Women Development
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2004
- action
- Construction Of A Centre For Women
- output
- Meeting Place For Women
- implementation status
- Complete And In Use
- total cost
- Ksh 1,239,497
- estimate
- Ksh 1,500,000
Tudor Social Hall Rehabilitation
- location
-
Tudor
(in Changamwe)
- year first funded
- 2006
- action
- Renovation Of The Hall & Toilets
- output
- Better Social Facilities
- implementation status
- Complete And In Use
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,200,000
Kajembe Secondary School
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2004
- action
- Provision Of School'S Furniture & Computers
- output
- Better Learning Facilities
- implementation status
- Complete And In Use
- total cost
- Ksh 1,026,667
- estimate
- Ksh 0
Generator For Potreitz Hospital
- location
-
Portreitz
(in Changamwe)
- year first funded
- 2009
- action
- Power Back For Kepi Store
- output
- Better Facility For The Hospital
- implementation status
- Tendering
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Akamba Handcraft
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2004
- action
- Renovation Of Akamba Handcraft Centres
- output
- Better Working Facility To Community
- implementation status
- Complete And In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,500,000
Ziwani School For The Deaf
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2005
- action
- Construction Of One Classroom
- output
- Better Education Facilities
- implementation status
- Complete And In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,200,000
Staugustine Primary School Roof Renovation
- location
-
Tudor
(in Changamwe)
- year first funded
- 2005
- action
- RoofingS Renovation
- output
- Better Education Facilities
- implementation status
- Complete And In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,051,627
Girls Hostel At Mikindani Teachers Training College
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2005
- action
- Construction Of Girls Hostel
- output
- Better Educational Facilities
- implementation status
- Complete & In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Mikindani Primary School
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2006
- action
- Construction Of One Classroom
- output
- Conducive Learning Environment
- implementation status
- Complete And In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 100,000,000
Miritini Primary School
- location
-
Miritini
(in Changamwe)
- year first funded
- 2006
- action
- Construction Of One Classroom
- output
- Better Learning Facilities
- implementation status
- Complete And In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Ziwani School For The Deaf
- location
-
Tudor
(in Changamwe)
- year first funded
- 2006
- action
- Construction Of One Classroom
- output
- Better Educational Fcilities?
- implementation status
- Complete And In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 110,000,000
Mikanjuni Maternity
- location
-
Jomvu Kuu
(in Changamwe)
- year first funded
- 2008
- action
- Construction Of Examination, Antenatal & ChildrenS Welfare Room, Placenta Pit, Incinerator, Kitchen/Laundry,Drying Lines & Pit Latrines
- output
- Better Health Facilities
- implementation status
- Ongoing
- total cost
- Ksh 1,000,000
- estimate
- Ksh 15,000,000
Tudor Primary School
- location
-
Tudor
(in Changamwe)
- year first funded
- 2007
- action
- Changed From Classroom Construction To School Renovation
- output
- Better Educational Facilities
- implementation status
- Complete & In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Mwijabu Primary School
- location
-
Portreitz
(in Changamwe)
- year first funded
- 2007
- action
- Construction Of 1 Classroom
- output
- Better Educational Facilities
- implementation status
- Complete And In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Changamwe Adventist School
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2007
- action
- Construction Of 1 Classroom
- output
- Better Educational Facilities
- implementation status
- Complete & In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Ward Construction At Portreitz District Hospital
- location
-
Portreitz
(in Changamwe)
- year first funded
- 2007
- action
- Ward Construction
- output
- Better Health Facilities
- implementation status
- Complete But Not In Use Awaits Power Back Up
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,500,000
Changamwe Secondary School
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2009
- action
- Classroom Construction
- output
- Better Educational Facilities
- implementation status
- Tendering
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,200,000
Chiefs Office At Mikindani
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2009
- action
- Constructing A Chief'S Oofice
- output
- Better Services To The Community And Good Working Environment For The Administartion
- implementation status
- Tendering
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,500,000
Furniture Supply At Kwashee Social Hall
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2007
- action
- Equipping The Hall With Furniture
- output
- A Conducive Social Place
- implementation status
- Complete & In Use
- total cost
- Ksh 900,000
- estimate
- Ksh 900,000
Social Hall At Kwashee
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2008
- action
- Hall Construction
- output
- Gathering For Cultural Activities / Meetings For The Community
- implementation status
- Complete And In Use
- total cost
- Ksh 530,345
- estimate
- Ksh 5,000,000
Staffroom S Construction At Miritini Primary School
- location
-
Miritini
(in Changamwe)
- year first funded
- 2007
- action
- Construction Of A Staffroom
- output
- Better Educational Facilities
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 1,500,000
Boreholes At Tudor Estate
- location
-
Tudor
(in Changamwe)
- year first funded
- 2004
- action
- Boreholes Construction
- output
- Availability Of Clean Water
- implementation status
- Complete And One In Use.
- total cost
- Ksh 500,000
- estimate
- Ksh 550,000
Buying Plot For Bokole Health Centre
- location
-
Bokole
(in Changamwe)
- year first funded
- 2004
- action
- Purchase Of Lamd For Health Centre
- output
- Health Centre For The Community
- implementation status
- Ongoing
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Boreholes In Tudor Location
- location
-
Tudor
(in Changamwe)
- year first funded
- 2003
- action
- Drilling Borehole
- output
- Provision Of Clean Drinking Water
- implementation status
- Re-Tendering
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Electricity Supply At Chamunyu
- location
-
Miritini
(in Changamwe)
- year first funded
- 2007
- action
- Fixing Electric Poles
- output
- Power Supply
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 700,000
Construction Of Public Toilets At Tudor Estate
- location
-
Tudor
(in Changamwe)
- year first funded
- 2007
- action
- Toilets Construction
- output
- Better Health Facilities
- implementation status
- To Start Soon
- total cost
- Ksh 450,000
- estimate
- Ksh 500,000
Construction Of A Well At Kwashee
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2008
- action
- Drilling Of A Well
- output
- Availability Of Water
- implementation status
- Tendering
- total cost
- Ksh 400,000
- estimate
- Ksh 500,000
Gorofani Estate
- location
-
Tudor
(in Changamwe)
- year first funded
- 2009
- action
- Digging And Constructing A Well
- output
- Availability Of Water
- implementation status
- Tendering
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Miritini Health Centre
- location
-
Miritini
(in Changamwe)
- year first funded
- 2009
- action
- Digging And Constructing A Well
- output
- Availability Of Water
- implementation status
- Tendering
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Drilling Of A Well At Chaani Primary School
- location
-
Kipevu
(in Changamwe)
- year first funded
- 2008
- action
- Drilling Of A Well
- output
- Availability Of Water
- implementation status
- Complete And In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 500,000
Construction Of A Well At Tudor Health Centre
- location
-
Tudor
(in Changamwe)
- year first funded
- 2008
- action
- Drilling Of A Well
- output
- Availability Of Water
- implementation status
- Complete And In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 450,000
Construction Of Public Toilets At Changamwe Estate
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2007
- action
- Toilets Construction
- output
- Better Health Facilities
- implementation status
- Tendering Process
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Assistance To Community Schools Mreroni, Miliman
- location
-
Miritini
(in Changamwe)
- year first funded
- 2003
- action
- Rehabilitation Of Community School
- output
- Better Learning Environment
- implementation status
- Complete And In Use
- total cost
- Ksh 320,000
- estimate
- Ksh 40,000,000
Well At Kiziwi
- location
-
Tudor
(in Changamwe)
- year first funded
- 2005
- action
- Construction Of A Well
- output
- Provision Of Clean Water To The Community
- implementation status
- Complete And In Use
- total cost
- Ksh 300,483
- estimate
- Ksh 350,000
Renovation Of Chiefs Office In Tudor
- location
-
Tudor
(in Changamwe)
- year first funded
- 2005
- action
- Renovation Of Chiefs Office
- output
- Better Service/Improved Security
- implementation status
- Complete And In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Renovation Of Disability Awareness Development & Reliefs Building
- location
-
Portreitz
(in Changamwe)
- year first funded
- 2008
- action
- Renovation Of The Building
- output
- -
- implementation status
- Tendering
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Wells Construction At Spaki Primary School
- location
-
Tudor
(in Changamwe)
- year first funded
- 2007
- action
- Drilling Of A Well
- output
- Availability Of Clean Water
- implementation status
- 6 Classrooms Renovated
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Wells Construction At Mreroni Primary School
- location
-
Miritini
(in Changamwe)
- year first funded
- 2007
- action
- Drilling Of A Well
- output
- Availability Of Clean Water
- implementation status
- Well Drilling On The Process
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Wells Construction At Umoja Primary School
- location
-
Kipevu
(in Changamwe)
- year first funded
- 2007
- action
- Drilling Of A Well
- output
- Availability Of Clean Water
- implementation status
- Complete But No Water
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Wells Construction At Charles Luanga Primary School
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2007
- action
- Drilling Of A Well
- output
- Availability Of Clean Water
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
School Desks For Kipevu
- location
-
Kipevu
(in Changamwe)
- year first funded
- 2006
- action
- Purchase Of Desks
- output
- Better Educational Facilities.
- implementation status
- Complete And In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
School Desks For Magongo Primary School
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2006
- action
- Purchase Of Desks
- output
- Better Educational Facilities.
- implementation status
- Complete And In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Msikiti Noor St Light
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2005
- action
- n/a
- output
- Lit Dark Streets
- implementation status
- Tendering
- total cost
- Ksh 300,000
- estimate
- Ksh 50,000,000
Water Project
- location
-
Portreitz Wayani
(in Changamwe)
- year first funded
- 2006
- action
- Extension Of Pipes
- output
- Availability Of Clean Water
- implementation status
- Complete And In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 30,000,000
Borehole At Kipevu Primary School
- location
-
Kipevu
(in Changamwe)
- year first funded
- 2005
- action
- Borehole Drilling
- output
- Provision Of Clean Drinking Water
- implementation status
- Complete And In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Borehole In Miritinimwamla
- location
-
Miritini
(in Changamwe)
- year first funded
- 2003
- action
- Drilling Borehole
- output
- Provision Of Clean Drinking Water
- implementation status
- Complete And In Use
- total cost
- Ksh 250,000
- estimate
- Ksh 300,000
Chaani Primary School
- location
-
Kipevu
(in Changamwe)
- year first funded
- 2009
- action
- Supply Of School'S Desks
- output
- Beeter Educational Facilities
- implementation status
- Tendering
- total cost
- Ksh 250,000
- estimate
- Ksh 300,000
Stary's Primary School
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2009
- action
- Supply Of Chairs And Tables
- output
- Better Educational Facilities
- implementation status
- Tendering
- total cost
- Ksh 250,000
- estimate
- Ksh 300,000
Water Project In Portreitz
- location
-
Portreitz
(in Changamwe)
- year first funded
- 2003
- action
- Laying Of Pipes To Get Fresh Water
- output
- Provision Of Clean Drinking Water
- implementation status
- Complete And In Use
- total cost
- Ksh 250,000
- estimate
- Ksh 500,000
Borehole In Changamwe
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2003
- action
- Drilling Borehole
- output
- Provision Of Clean Drinking Water
- implementation status
- Complete And In Use
- total cost
- Ksh 250,000
- estimate
- Ksh 300,000
Boreholes Completion At Mikadini Primary School
- location
-
Kipevu
(in Changamwe)
- year first funded
- 2007
- action
- Borehole Drilling Construction
- output
- Availability Of Clean Water
- implementation status
- Complete But No Water
- total cost
- Ksh 200,000
- estimate
- Ksh 250,000
Toilets Renovation At Changamwe Estate Market
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2008
- action
- Toilets Renovation
- output
- Better Health Facilities
- implementation status
- Tendering
- total cost
- Ksh 200,000
- estimate
- Ksh 250,000
Tudor Day Secondary School
- location
-
Tudor
(in Changamwe)
- year first funded
- 2009
- action
- Assistance To The School To Enable Them Re- Posses Their School Bus
- output
- Assists Teachers & Students During Educational Tours
- implementation status
- not known
- total cost
- Ksh 200,000
- estimate
- Ksh 1,000,000
Khamis Secondary School
- location
-
Tudor
(in Changamwe)
- year first funded
- 2009
- action
- Assistance To The School To Enable Them Re- Posses Their School Bus
- output
- A School Bus For Educational Tours
- implementation status
- not known
- total cost
- Ksh 200,000
- estimate
- Ksh 800,000
Ganahola Water Project
- location
-
Mikindani
(in Changamwe)
- year first funded
- 2005
- action
- Pipes Laying
- output
- Availability Of Clean Water
- implementation status
- Tendering
- total cost
- Ksh 150,000
- estimate
- Ksh 20,000,000
Burhaniya Primary School
- location
-
Tudor
(in Changamwe)
- year first funded
- 2009
- action
- Installation Of Grill Doors And Windows
- output
- A Secured Computer Classroom
- implementation status
- Tendering
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Equipment For Blind People In Changamwe
- location
-
Changamwe
(in Changamwe)
- year first funded
- 2005
- action
- n/a
- output
- To Assist Blind People
- implementation status
- Complete And In Use
- total cost
- Ksh 84,348
- estimate