The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
    It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
    It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
    Projects in Fafi
    
        
            
            Galmagala Boarding School
            
            
                - location
- 
                        Galmagala
                        (in Fafi)
                    
- year first funded
- 2003
- action
- Construction Of Boarding Facility
- output
- Complete Boarding School
- implementation status
- Complete
- total cost
- Ksh 11,820,000
- estimate
- Ksh 1,163,500
 
    
        
            
            Construction Of Cdf Office At Bura
            
            
                - location
- 
                        Bura
                        (in Fafi)
                    
- year first funded
- 2007
- action
- n/a
- output
- Complete Office
- implementation status
- Complete
- total cost
- Ksh 4,716,000
- estimate
- Ksh 4,716,000
 
    
        
            
            Kamuthe School
            
            
                - location
- 
                        Kamuthe
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Construction Of Dormitory
- output
- Dormitory
- implementation status
- Complete
- total cost
- Ksh 4,133,052
- estimate
- Ksh 3,500,000
 
    
        
            
            Construction Of Dispensary At Amuma
            
            
                - location
- 
                        
                        (in Fafi)
                    
- year first funded
- 2008
- action
- Construction of House
- output
- Provision Of Health Service
- implementation status
- Complete
- total cost
- Ksh 4,000,000
- estimate
- Ksh 0
 
    
        
            
            Hulugho Inpatient Ward At Hulugho
            
            
                - location
- 
                        Hulugho
                        (in Fafi)
                    
- year first funded
- 2007
- action
- Construction Of Hulugho Inpatient Ward
- output
- Construction Of Hulugho Inpatient Ward
- implementation status
- ?Complete
- total cost
- Ksh 4,000,000
- estimate
- Ksh 3,400,000
 
    
        
            
            Kitchen & Dining Hall Bura Sec
            
            
                - location
- 
                        Bura
                        (in Fafi)
                    
- year first funded
- 2004
- action
- Construction Of Kitchen,Dining Hall
- output
- Kitchen And dininghall
- implementation status
- Complete
- total cost
- Ksh 3,413,047
- estimate
- Ksh 4,379,723
 
    
        
            
            Galmagala Dispensary With Staff Quarters
            
            
                - location
- 
                        Galmagala
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Construction Of Dispensary
- output
- Dispensary
- implementation status
- Complete
- total cost
- Ksh 2,800,000
- estimate
- Ksh 2,800,000
 
    
        
            
            Nanighi Primary School
            
            
                - location
- 
                        Nanighi
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Construction Of Classes
- output
- 6 Classrooms
- implementation status
- Complete
- total cost
- Ksh 2,594,210
- estimate
- Ksh 2,594,210
 
    
        
            
            Constrution Of Dispensary At Fafi
            
            
                - location
- 
                        Fafi
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Constrution Of Dispensary
- output
- Dispensary
- implementation status
- Complete
- total cost
- Ksh 2,500,000
- estimate
- Ksh 2,500,000
 
    
        
            
            Construction Of Maternity Wing At Bura
            
            
                - location
- 
                        Bura
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Construction Of Maternity Wing
- output
- Maternity Block
- implementation status
- Complete
- total cost
- Ksh 2,500,000
- estimate
- Ksh 2,500,000
 
    
        
            
            Bura District Hospital Staff Housing
            
            
                - location
- 
                        
                        (in Fafi)
                    
- year first funded
- 2008
- action
- Construction of 1 Unit Staff House
- output
- Provision Of Housing
- implementation status
- Complete
- total cost
- Ksh 2,260,561
- estimate
- Ksh 0
 
    
        
            
            Construction Of Dispensary At H/Dera
            
            
                - location
- 
                        Hagardera
                        (in Fafi)
                    
- year first funded
- 2007
- action
- Construction Of Dispensary
- output
- Construction Of Dispensary
- implementation status
- ?Complete
- total cost
- Ksh 2,200,000
- estimate
- Ksh 2,200,000
 
    
        
            
            Bush Clearing Fafi-Katama Road
            
            
                - location
- 
                        Fafi
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Bush Clearing
- output
- Access Road
- implementation status
- Complete
- total cost
- Ksh 2,000,000
- estimate
- Ksh 2,000,000
 
    
        
            
            Construction Of Dispensary At Mansabubu
            
            
                - location
- 
                        Mansabubu
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Construction Of Dispensary
- output
- Dispensary
- implementation status
- Complete
- total cost
- Ksh 1,800,000
- estimate
- Ksh 1,800,000
 
    
        
            
            Construction Of Do Residence At Gmg
            
            
                - location
- 
                        Galmagala
                        (in Fafi)
                    
- year first funded
- 2004
- action
- Construction Of D.Os Residence
- output
- -
- implementation status
- not known
- total cost
- Ksh 1,800,000
- estimate
- Ksh 1,800,000
 
    
        
            
            Construction Of Do Office At Gmg
            
            
                - location
- 
                        Galmagala
                        (in Fafi)
                    
- year first funded
- 2004
- action
- Construction Of D.Os Office
- output
- -
- implementation status
- -
- total cost
- Ksh 1,700,000
- estimate
- Ksh 1,700,000
 
    
        
            
            Bura Secondary School
            
            
                - location
- 
                        Bura
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Completion Of Kitchen & dining
- output
- Euipped dininghall
- implementation status
- Complete
- total cost
- Ksh 1,700,000
- estimate
- Ksh 900,000
 
    
        
            
            Yumbis Dispensary
            
            
                - location
- 
                        Yumbis
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Construction Of Dispensary
- output
- Dispensary
- implementation status
- Complete
- total cost
- Ksh 1,654,000
- estimate
- Ksh 2,141,057
 
    
        
            
            Construction Of Yumbis Ap Line
            
            
                - location
- 
                        Yumbis
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Construction Of Ap Houses
- output
- Housing Facilities
- implementation status
- Complete
- total cost
- Ksh 1,600,000
- estimate
- Ksh 1,600,000
 
    
        
            
            Renovation Of Mansabubu Water Supply And Servicing Of Engine
            
            
                - location
- 
                        Mansabubu
                        (in Fafi)
                    
- year first funded
- 2007
- action
- n/a
- output
- Renovation Of Mansabubu Water Supply
- implementation status
- ?Complete
- total cost
- Ksh 1,600,000
- estimate
- Ksh 600,000
 
    
        
            
            Galmagala Ap Line
            
            
                - location
- 
                        Galmagala
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Construction Of Ap Houses
- output
- Housing Facilities
- implementation status
- Complete
- total cost
- Ksh 1,491,500
- estimate
- Ksh 1,491,500
 
    
        
            
            Kamuthey Dispensary
            
            
                - location
- 
                        
                        (in Fafi)
                    
- year first funded
- 2009
- action
- Construction of Staff Housing Units
- output
- -
- implementation status
- To Commence
- total cost
- Ksh 1,450,000
- estimate
- Ksh 0
 
    
        
            
            Kamithe Ap Line
            
            
                - location
- 
                        Kamuthe
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Construction Of Ap Houses
- output
- Housing Facilities
- implementation status
- Complete
- total cost
- Ksh 1,400,000
- estimate
- Ksh 1,400,000
 
    
        
            
            Gubi Secondary Schoold
            
            
                - location
- 
                        Gubis
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Construction Of 2 Classrooms
- output
- 2 Equipped Classrooms
- implementation status
- Complete
- total cost
- Ksh 1,250,000
- estimate
- Ksh 1,250,000
 
    
        
            
            Bush Clearing Mansabub - Garasweino Road
            
            
                - location
- 
                        Mansabubu
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Bush Clearing
- output
- Access Road
- implementation status
- Complete
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,200,000
 
    
        
            
            Mansabubu Primary School
            
            
                - location
- 
                        Mansabubu
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Construction Of 2 Classrooms
- output
- 2 Equipped Classrooms
- implementation status
- Complete
- total cost
- Ksh 1,199,280
- estimate
- Ksh 1,199,280
 
    
        
            
            Rehabilitation Of C/Rooms At Hulugho Primary School
            
            
                - location
- 
                        Hulugho
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Rehabilitation Of 7 Classrooms
- output
- Renovated Classes
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
 
    
        
            
            Welmerer Primary School
            
            
                - location
- 
                        Welmarer
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Construction Of Classes
- output
- 2 Classrooms
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
 
    
        
            
            Hulugho DivPrimary School
            
            
                - location
- 
                        Hulugho
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Equiping Of School
- output
- Provision Of Desks
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
 
    
        
            
            Amuma Dispensary
            
            
                - location
- 
                        
                        (in Fafi)
                    
- year first funded
- 2009
- action
- Plastering, Roofing & Fixing Doors/ Windows
- output
- Provision Of Health Facility
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 0
 
    
        
            
            Renovation Of Bura Youth Politechnic
            
            
                - location
- 
                        Bura
                        (in Fafi)
                    
- year first funded
- 2007
- action
- n/a
- output
- Renovation Of Bura Youth Politechnic
- implementation status
- ?Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
 
    
        
            
            Renovation Of Do House At Bura
            
            
                - location
- 
                        Bura
                        (in Fafi)
                    
- year first funded
- 2007
- action
- n/a
- output
- Renovated House
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
 
    
        
            
            Bush Clearing Of Galamgala - Hulugho Road
            
            
                - location
- 
                        Galmagala
                        (in Fafi)
                    
- year first funded
- 2007
- action
- Bush Clearing
- output
- Bush Clearing
- implementation status
- ?Complete
- total cost
- Ksh 900,000
- estimate
- Ksh 900,000
 
    
        
            
            Dhouse At Galmagala
            
            
                - location
- 
                        Galmagala
                        (in Fafi)
                    
- year first funded
- 2007
- action
- n/a
- output
- Housing Facility
- implementation status
- Complete
- total cost
- Ksh 680,000
- estimate
- Ksh 680,000
 
    
        
            
            Bush Clearing Galmagala To Gubis
            
            
                - location
- 
                        Galmagala
                        (in Fafi)
                    
- year first funded
- 2004
- action
- Bush Clearing
- output
- Access Road
- implementation status
- Complete
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
 
    
        
            
            Rehibilitation Of Kamuthe Water Supply
            
            
                - location
- 
                        Kamuthe
                        (in Fafi)
                    
- year first funded
- 2006
- action
- n/a
- output
- Dispensary
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
 
    
        
            
            Completion Of Galmagala Ap Line
            
            
                - location
- 
                        Galmagala
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Completion Of Galmagala Ap Line
- output
- Housing Facilities
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
 
    
        
            
            Bush Clearing Welmerer Amuma
            
            
                - location
- 
                        Welmarer
                        (in Fafi)
                    
- year first funded
- 2004
- action
- Bush Clearing
- output
- Access Road
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
 
    
        
            
            Bura Secondary School
            
            
                - location
- 
                        Bura
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Provision Of Desks
- output
- Provision Of Desks
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
 
    
        
            
            Bura Primary School
            
            
                - location
- 
                        Bura
                        (in Fafi)
                    
- year first funded
- 2005
- action
- Provision Of Desks
- output
- Provision Of Desks
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
 
    
        
            
            Survying Of Damaka Farm And Canal Raising
            
            
                - location
- 
                        Damaka
                        (in Fafi)
                    
- year first funded
- 2007
- action
- Survying Of Damaka Farm And Canal Raising
- output
- Survying Of Damaka Farm And Canal Raising
- implementation status
- ?Complete
- total cost
- Ksh 450,000
- estimate
- Ksh 450,000
 
    
        
            
            Rehabilitation Of C/Rooms At Yumbis Primary School
            
            
                - location
- 
                        Yumbis
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Rehabilitation Of 4 Classrooms
- output
- Renovated Classes
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
 
    
        
            
            Completion Of Yumbis Dispensary
            
            
                - location
- 
                        Yumbis
                        (in Fafi)
                    
- year first funded
- 2004
- action
- n/a
- output
- -
- implementation status
- -
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
 
    
        
            
            Galmagala Community Water Pan
            
            
                - location
- 
                        Galmagala
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Digging Water Pan
- output
- Provision Of Water
- implementation status
- Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
 
    
        
            
            Welmarer Primary School
            
            
                - location
- 
                        Welmarer
                        (in Fafi)
                    
- year first funded
- 2007
- action
- n/a
- output
- Construction Of 2 Toilets And Equip Of 2 Classes At
- implementation status
- ?Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
 
    
        
            
            Completion Of Yumbis Ap Line
            
            
                - location
- 
                        Yumbis
                        (in Fafi)
                    
- year first funded
- 2006
- action
- Completion Of Yumbis Ap Line
- output
- Housing Facilities
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000