The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Projects in Fafi
Galmagala Boarding School
- location
-
Galmagala
(in Fafi)
- year first funded
- 2003
- action
- Construction Of Boarding Facility
- output
- Complete Boarding School
- implementation status
- Complete
- total cost
- Ksh 11,820,000
- estimate
- Ksh 1,163,500
Construction Of Cdf Office At Bura
- location
-
Bura
(in Fafi)
- year first funded
- 2007
- action
- n/a
- output
- Complete Office
- implementation status
- Complete
- total cost
- Ksh 4,716,000
- estimate
- Ksh 4,716,000
Kamuthe School
- location
-
Kamuthe
(in Fafi)
- year first funded
- 2006
- action
- Construction Of Dormitory
- output
- Dormitory
- implementation status
- Complete
- total cost
- Ksh 4,133,052
- estimate
- Ksh 3,500,000
Construction Of Dispensary At Amuma
- location
-
(in Fafi)
- year first funded
- 2008
- action
- Construction of House
- output
- Provision Of Health Service
- implementation status
- Complete
- total cost
- Ksh 4,000,000
- estimate
- Ksh 0
Hulugho Inpatient Ward At Hulugho
- location
-
Hulugho
(in Fafi)
- year first funded
- 2007
- action
- Construction Of Hulugho Inpatient Ward
- output
- Construction Of Hulugho Inpatient Ward
- implementation status
- ?Complete
- total cost
- Ksh 4,000,000
- estimate
- Ksh 3,400,000
Kitchen & Dining Hall Bura Sec
- location
-
Bura
(in Fafi)
- year first funded
- 2004
- action
- Construction Of Kitchen,Dining Hall
- output
- Kitchen And dininghall
- implementation status
- Complete
- total cost
- Ksh 3,413,047
- estimate
- Ksh 4,379,723
Galmagala Dispensary With Staff Quarters
- location
-
Galmagala
(in Fafi)
- year first funded
- 2006
- action
- Construction Of Dispensary
- output
- Dispensary
- implementation status
- Complete
- total cost
- Ksh 2,800,000
- estimate
- Ksh 2,800,000
Nanighi Primary School
- location
-
Nanighi
(in Fafi)
- year first funded
- 2005
- action
- Construction Of Classes
- output
- 6 Classrooms
- implementation status
- Complete
- total cost
- Ksh 2,594,210
- estimate
- Ksh 2,594,210
Constrution Of Dispensary At Fafi
- location
-
Fafi
(in Fafi)
- year first funded
- 2006
- action
- Constrution Of Dispensary
- output
- Dispensary
- implementation status
- Complete
- total cost
- Ksh 2,500,000
- estimate
- Ksh 2,500,000
Construction Of Maternity Wing At Bura
- location
-
Bura
(in Fafi)
- year first funded
- 2006
- action
- Construction Of Maternity Wing
- output
- Maternity Block
- implementation status
- Complete
- total cost
- Ksh 2,500,000
- estimate
- Ksh 2,500,000
Bura District Hospital Staff Housing
- location
-
(in Fafi)
- year first funded
- 2008
- action
- Construction of 1 Unit Staff House
- output
- Provision Of Housing
- implementation status
- Complete
- total cost
- Ksh 2,260,561
- estimate
- Ksh 0
Construction Of Dispensary At H/Dera
- location
-
Hagardera
(in Fafi)
- year first funded
- 2007
- action
- Construction Of Dispensary
- output
- Construction Of Dispensary
- implementation status
- ?Complete
- total cost
- Ksh 2,200,000
- estimate
- Ksh 2,200,000
Bush Clearing Fafi-Katama Road
- location
-
Fafi
(in Fafi)
- year first funded
- 2005
- action
- Bush Clearing
- output
- Access Road
- implementation status
- Complete
- total cost
- Ksh 2,000,000
- estimate
- Ksh 2,000,000
Construction Of Dispensary At Mansabubu
- location
-
Mansabubu
(in Fafi)
- year first funded
- 2006
- action
- Construction Of Dispensary
- output
- Dispensary
- implementation status
- Complete
- total cost
- Ksh 1,800,000
- estimate
- Ksh 1,800,000
Construction Of Do Residence At Gmg
- location
-
Galmagala
(in Fafi)
- year first funded
- 2004
- action
- Construction Of D.Os Residence
- output
- -
- implementation status
- not known
- total cost
- Ksh 1,800,000
- estimate
- Ksh 1,800,000
Construction Of Do Office At Gmg
- location
-
Galmagala
(in Fafi)
- year first funded
- 2004
- action
- Construction Of D.Os Office
- output
- -
- implementation status
- -
- total cost
- Ksh 1,700,000
- estimate
- Ksh 1,700,000
Bura Secondary School
- location
-
Bura
(in Fafi)
- year first funded
- 2006
- action
- Completion Of Kitchen & dining
- output
- Euipped dininghall
- implementation status
- Complete
- total cost
- Ksh 1,700,000
- estimate
- Ksh 900,000
Yumbis Dispensary
- location
-
Yumbis
(in Fafi)
- year first funded
- 2005
- action
- Construction Of Dispensary
- output
- Dispensary
- implementation status
- Complete
- total cost
- Ksh 1,654,000
- estimate
- Ksh 2,141,057
Construction Of Yumbis Ap Line
- location
-
Yumbis
(in Fafi)
- year first funded
- 2005
- action
- Construction Of Ap Houses
- output
- Housing Facilities
- implementation status
- Complete
- total cost
- Ksh 1,600,000
- estimate
- Ksh 1,600,000
Renovation Of Mansabubu Water Supply And Servicing Of Engine
- location
-
Mansabubu
(in Fafi)
- year first funded
- 2007
- action
- n/a
- output
- Renovation Of Mansabubu Water Supply
- implementation status
- ?Complete
- total cost
- Ksh 1,600,000
- estimate
- Ksh 600,000
Galmagala Ap Line
- location
-
Galmagala
(in Fafi)
- year first funded
- 2005
- action
- Construction Of Ap Houses
- output
- Housing Facilities
- implementation status
- Complete
- total cost
- Ksh 1,491,500
- estimate
- Ksh 1,491,500
Kamuthey Dispensary
- location
-
(in Fafi)
- year first funded
- 2009
- action
- Construction of Staff Housing Units
- output
- -
- implementation status
- To Commence
- total cost
- Ksh 1,450,000
- estimate
- Ksh 0
Kamithe Ap Line
- location
-
Kamuthe
(in Fafi)
- year first funded
- 2005
- action
- Construction Of Ap Houses
- output
- Housing Facilities
- implementation status
- Complete
- total cost
- Ksh 1,400,000
- estimate
- Ksh 1,400,000
Gubi Secondary Schoold
- location
-
Gubis
(in Fafi)
- year first funded
- 2006
- action
- Construction Of 2 Classrooms
- output
- 2 Equipped Classrooms
- implementation status
- Complete
- total cost
- Ksh 1,250,000
- estimate
- Ksh 1,250,000
Bush Clearing Mansabub - Garasweino Road
- location
-
Mansabubu
(in Fafi)
- year first funded
- 2005
- action
- Bush Clearing
- output
- Access Road
- implementation status
- Complete
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,200,000
Mansabubu Primary School
- location
-
Mansabubu
(in Fafi)
- year first funded
- 2006
- action
- Construction Of 2 Classrooms
- output
- 2 Equipped Classrooms
- implementation status
- Complete
- total cost
- Ksh 1,199,280
- estimate
- Ksh 1,199,280
Rehabilitation Of C/Rooms At Hulugho Primary School
- location
-
Hulugho
(in Fafi)
- year first funded
- 2006
- action
- Rehabilitation Of 7 Classrooms
- output
- Renovated Classes
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Welmerer Primary School
- location
-
Welmarer
(in Fafi)
- year first funded
- 2005
- action
- Construction Of Classes
- output
- 2 Classrooms
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Hulugho DivPrimary School
- location
-
Hulugho
(in Fafi)
- year first funded
- 2005
- action
- Equiping Of School
- output
- Provision Of Desks
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Amuma Dispensary
- location
-
(in Fafi)
- year first funded
- 2009
- action
- Plastering, Roofing & Fixing Doors/ Windows
- output
- Provision Of Health Facility
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 0
Renovation Of Bura Youth Politechnic
- location
-
Bura
(in Fafi)
- year first funded
- 2007
- action
- n/a
- output
- Renovation Of Bura Youth Politechnic
- implementation status
- ?Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Renovation Of Do House At Bura
- location
-
Bura
(in Fafi)
- year first funded
- 2007
- action
- n/a
- output
- Renovated House
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Bush Clearing Of Galamgala - Hulugho Road
- location
-
Galmagala
(in Fafi)
- year first funded
- 2007
- action
- Bush Clearing
- output
- Bush Clearing
- implementation status
- ?Complete
- total cost
- Ksh 900,000
- estimate
- Ksh 900,000
Dhouse At Galmagala
- location
-
Galmagala
(in Fafi)
- year first funded
- 2007
- action
- n/a
- output
- Housing Facility
- implementation status
- Complete
- total cost
- Ksh 680,000
- estimate
- Ksh 680,000
Bush Clearing Galmagala To Gubis
- location
-
Galmagala
(in Fafi)
- year first funded
- 2004
- action
- Bush Clearing
- output
- Access Road
- implementation status
- Complete
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Rehibilitation Of Kamuthe Water Supply
- location
-
Kamuthe
(in Fafi)
- year first funded
- 2006
- action
- n/a
- output
- Dispensary
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Completion Of Galmagala Ap Line
- location
-
Galmagala
(in Fafi)
- year first funded
- 2006
- action
- Completion Of Galmagala Ap Line
- output
- Housing Facilities
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Bush Clearing Welmerer Amuma
- location
-
Welmarer
(in Fafi)
- year first funded
- 2004
- action
- Bush Clearing
- output
- Access Road
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Bura Secondary School
- location
-
Bura
(in Fafi)
- year first funded
- 2005
- action
- Provision Of Desks
- output
- Provision Of Desks
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Bura Primary School
- location
-
Bura
(in Fafi)
- year first funded
- 2005
- action
- Provision Of Desks
- output
- Provision Of Desks
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Survying Of Damaka Farm And Canal Raising
- location
-
Damaka
(in Fafi)
- year first funded
- 2007
- action
- Survying Of Damaka Farm And Canal Raising
- output
- Survying Of Damaka Farm And Canal Raising
- implementation status
- ?Complete
- total cost
- Ksh 450,000
- estimate
- Ksh 450,000
Rehabilitation Of C/Rooms At Yumbis Primary School
- location
-
Yumbis
(in Fafi)
- year first funded
- 2006
- action
- Rehabilitation Of 4 Classrooms
- output
- Renovated Classes
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Completion Of Yumbis Dispensary
- location
-
Yumbis
(in Fafi)
- year first funded
- 2004
- action
- n/a
- output
- -
- implementation status
- -
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Galmagala Community Water Pan
- location
-
Galmagala
(in Fafi)
- year first funded
- 2006
- action
- Digging Water Pan
- output
- Provision Of Water
- implementation status
- Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Welmarer Primary School
- location
-
Welmarer
(in Fafi)
- year first funded
- 2007
- action
- n/a
- output
- Construction Of 2 Toilets And Equip Of 2 Classes At
- implementation status
- ?Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Completion Of Yumbis Ap Line
- location
-
Yumbis
(in Fafi)
- year first funded
- 2006
- action
- Completion Of Yumbis Ap Line
- output
- Housing Facilities
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000