It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

Projects in Fafi

Galmagala Boarding School

location
Galmagala (in Fafi)
year first funded
2003
action
Construction Of Boarding Facility
output
Complete Boarding School
implementation status
Complete
total cost
Ksh 11,820,000
estimate
Ksh 1,163,500

Construction Of Cdf Office At Bura

location
Bura (in Fafi)
year first funded
2007
action
n/a
output
Complete Office
implementation status
Complete
total cost
Ksh 4,716,000
estimate
Ksh 4,716,000

Kamuthe School

location
Kamuthe (in Fafi)
year first funded
2006
action
Construction Of Dormitory
output
Dormitory
implementation status
Complete
total cost
Ksh 4,133,052
estimate
Ksh 3,500,000

Construction Of Dispensary At Amuma

location
(in Fafi)
year first funded
2008
action
Construction of House
output
Provision Of Health Service
implementation status
Complete
total cost
Ksh 4,000,000
estimate
Ksh 0

Hulugho Inpatient Ward At Hulugho

location
Hulugho (in Fafi)
year first funded
2007
action
Construction Of Hulugho Inpatient Ward
output
Construction Of Hulugho Inpatient Ward
implementation status
?Complete
total cost
Ksh 4,000,000
estimate
Ksh 3,400,000

Kitchen & Dining Hall Bura Sec

location
Bura (in Fafi)
year first funded
2004
action
Construction Of Kitchen,Dining Hall
output
Kitchen And dininghall
implementation status
Complete
total cost
Ksh 3,413,047
estimate
Ksh 4,379,723

Galmagala Dispensary With Staff Quarters

location
Galmagala (in Fafi)
year first funded
2006
action
Construction Of Dispensary
output
Dispensary
implementation status
Complete
total cost
Ksh 2,800,000
estimate
Ksh 2,800,000

Nanighi Primary School

location
Nanighi (in Fafi)
year first funded
2005
action
Construction Of Classes
output
6 Classrooms
implementation status
Complete
total cost
Ksh 2,594,210
estimate
Ksh 2,594,210

Constrution Of Dispensary At Fafi

location
Fafi (in Fafi)
year first funded
2006
action
Constrution Of Dispensary
output
Dispensary
implementation status
Complete
total cost
Ksh 2,500,000
estimate
Ksh 2,500,000

Construction Of Maternity Wing At Bura

location
Bura (in Fafi)
year first funded
2006
action
Construction Of Maternity Wing
output
Maternity Block
implementation status
Complete
total cost
Ksh 2,500,000
estimate
Ksh 2,500,000

Bura District Hospital Staff Housing

location
(in Fafi)
year first funded
2008
action
Construction of 1 Unit Staff House
output
Provision Of Housing
implementation status
Complete
total cost
Ksh 2,260,561
estimate
Ksh 0

Construction Of Dispensary At H/Dera

location
Hagardera (in Fafi)
year first funded
2007
action
Construction Of Dispensary
output
Construction Of Dispensary
implementation status
?Complete
total cost
Ksh 2,200,000
estimate
Ksh 2,200,000

Bush Clearing Fafi-Katama Road

location
Fafi (in Fafi)
year first funded
2005
action
Bush Clearing
output
Access Road
implementation status
Complete
total cost
Ksh 2,000,000
estimate
Ksh 2,000,000

Construction Of Dispensary At Mansabubu

location
Mansabubu (in Fafi)
year first funded
2006
action
Construction Of Dispensary
output
Dispensary
implementation status
Complete
total cost
Ksh 1,800,000
estimate
Ksh 1,800,000

Construction Of Do Residence At Gmg

location
Galmagala (in Fafi)
year first funded
2004
action
Construction Of D.Os Residence
output
-
implementation status
not known
total cost
Ksh 1,800,000
estimate
Ksh 1,800,000

Construction Of Do Office At Gmg

location
Galmagala (in Fafi)
year first funded
2004
action
Construction Of D.Os Office
output
-
implementation status
-
total cost
Ksh 1,700,000
estimate
Ksh 1,700,000

Bura Secondary School

location
Bura (in Fafi)
year first funded
2006
action
Completion Of Kitchen & dining
output
Euipped dininghall
implementation status
Complete
total cost
Ksh 1,700,000
estimate
Ksh 900,000

Yumbis Dispensary

location
Yumbis (in Fafi)
year first funded
2005
action
Construction Of Dispensary
output
Dispensary
implementation status
Complete
total cost
Ksh 1,654,000
estimate
Ksh 2,141,057

Construction Of Yumbis Ap Line

location
Yumbis (in Fafi)
year first funded
2005
action
Construction Of Ap Houses
output
Housing Facilities
implementation status
Complete
total cost
Ksh 1,600,000
estimate
Ksh 1,600,000

Renovation Of Mansabubu Water Supply And Servicing Of Engine

location
Mansabubu (in Fafi)
year first funded
2007
action
n/a
output
Renovation Of Mansabubu Water Supply
implementation status
?Complete
total cost
Ksh 1,600,000
estimate
Ksh 600,000

Galmagala Ap Line

location
Galmagala (in Fafi)
year first funded
2005
action
Construction Of Ap Houses
output
Housing Facilities
implementation status
Complete
total cost
Ksh 1,491,500
estimate
Ksh 1,491,500

Kamuthey Dispensary

location
(in Fafi)
year first funded
2009
action
Construction of Staff Housing Units
output
-
implementation status
To Commence
total cost
Ksh 1,450,000
estimate
Ksh 0

Kamithe Ap Line

location
Kamuthe (in Fafi)
year first funded
2005
action
Construction Of Ap Houses
output
Housing Facilities
implementation status
Complete
total cost
Ksh 1,400,000
estimate
Ksh 1,400,000

Gubi Secondary Schoold

location
Gubis (in Fafi)
year first funded
2006
action
Construction Of 2 Classrooms
output
2 Equipped Classrooms
implementation status
Complete
total cost
Ksh 1,250,000
estimate
Ksh 1,250,000

Bush Clearing Mansabub - Garasweino Road

location
Mansabubu (in Fafi)
year first funded
2005
action
Bush Clearing
output
Access Road
implementation status
Complete
total cost
Ksh 1,200,000
estimate
Ksh 1,200,000

Mansabubu Primary School

location
Mansabubu (in Fafi)
year first funded
2006
action
Construction Of 2 Classrooms
output
2 Equipped Classrooms
implementation status
Complete
total cost
Ksh 1,199,280
estimate
Ksh 1,199,280

Rehabilitation Of C/Rooms At Hulugho Primary School

location
Hulugho (in Fafi)
year first funded
2006
action
Rehabilitation Of 7 Classrooms
output
Renovated Classes
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Welmerer Primary School

location
Welmarer (in Fafi)
year first funded
2005
action
Construction Of Classes
output
2 Classrooms
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Hulugho DivPrimary School

location
Hulugho (in Fafi)
year first funded
2005
action
Equiping Of School
output
Provision Of Desks
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Amuma Dispensary

location
(in Fafi)
year first funded
2009
action
Plastering, Roofing & Fixing Doors/ Windows
output
Provision Of Health Facility
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 0

Renovation Of Bura Youth Politechnic

location
Bura (in Fafi)
year first funded
2007
action
n/a
output
Renovation Of Bura Youth Politechnic
implementation status
?Complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Renovation Of Do House At Bura

location
Bura (in Fafi)
year first funded
2007
action
n/a
output
Renovated House
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Bush Clearing Of Galamgala - Hulugho Road

location
Galmagala (in Fafi)
year first funded
2007
action
Bush Clearing
output
Bush Clearing
implementation status
?Complete
total cost
Ksh 900,000
estimate
Ksh 900,000

Dhouse At Galmagala

location
Galmagala (in Fafi)
year first funded
2007
action
n/a
output
Housing Facility
implementation status
Complete
total cost
Ksh 680,000
estimate
Ksh 680,000

Bush Clearing Galmagala To Gubis

location
Galmagala (in Fafi)
year first funded
2004
action
Bush Clearing
output
Access Road
implementation status
Complete
total cost
Ksh 600,000
estimate
Ksh 600,000

Rehibilitation Of Kamuthe Water Supply

location
Kamuthe (in Fafi)
year first funded
2006
action
n/a
output
Dispensary
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 500,000

Completion Of Galmagala Ap Line

location
Galmagala (in Fafi)
year first funded
2006
action
Completion Of Galmagala Ap Line
output
Housing Facilities
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 500,000

Bush Clearing Welmerer Amuma

location
Welmarer (in Fafi)
year first funded
2004
action
Bush Clearing
output
Access Road
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 500,000

Bura Secondary School

location
Bura (in Fafi)
year first funded
2005
action
Provision Of Desks
output
Provision Of Desks
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 500,000

Bura Primary School

location
Bura (in Fafi)
year first funded
2005
action
Provision Of Desks
output
Provision Of Desks
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 500,000

Survying Of Damaka Farm And Canal Raising

location
Damaka (in Fafi)
year first funded
2007
action
Survying Of Damaka Farm And Canal Raising
output
Survying Of Damaka Farm And Canal Raising
implementation status
?Complete
total cost
Ksh 450,000
estimate
Ksh 450,000

Rehabilitation Of C/Rooms At Yumbis Primary School

location
Yumbis (in Fafi)
year first funded
2006
action
Rehabilitation Of 4 Classrooms
output
Renovated Classes
implementation status
Complete
total cost
Ksh 400,000
estimate
Ksh 400,000

Completion Of Yumbis Dispensary

location
Yumbis (in Fafi)
year first funded
2004
action
n/a
output
-
implementation status
-
total cost
Ksh 400,000
estimate
Ksh 400,000

Galmagala Community Water Pan

location
Galmagala (in Fafi)
year first funded
2006
action
Digging Water Pan
output
Provision Of Water
implementation status
Complete
total cost
Ksh 300,000
estimate
Ksh 300,000

Welmarer Primary School

location
Welmarer (in Fafi)
year first funded
2007
action
n/a
output
Construction Of 2 Toilets And Equip Of 2 Classes At
implementation status
?Complete
total cost
Ksh 300,000
estimate
Ksh 300,000

Completion Of Yumbis Ap Line

location
Yumbis (in Fafi)
year first funded
2006
action
Completion Of Yumbis Ap Line
output
Housing Facilities
implementation status
Complete
total cost
Ksh 200,000
estimate
Ksh 200,000