It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Projects in Kaiti
Mukuyuni Mortuary
- location
-
Ukia
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Mortuary
- output
- Improve Health
- implementation status
- Ongoing
- total cost
- Ksh 3,500,000
- estimate
- Ksh 7,000,000
Mutungu Mortuary
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Mortuary
- output
- Improved Health
- implementation status
- Complete
- total cost
- Ksh 3,500,000
- estimate
- Ksh 7,000,000
Wautu Youth Poly
- location
-
Ilima
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Classes
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 3,000,000
- estimate
- Ksh 1,500,000
Dispensary
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2004
- action
- Construction Work
- output
- Improve Health
- implementation status
- Ongoing
- total cost
- Ksh 3,000,000
- estimate
- Ksh 1,500,000
Mituvu Dam
- location
-
Kilala
(in Kaiti)
- year first funded
- 2006
- action
- Survey Work, Excavation, Scooping
- output
- Increase Water Source
- implementation status
- Complete
- total cost
- Ksh 2,900,000
- estimate
- Ksh 1,500,000
Kilungu Divisional Headquarters
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Office
- output
- Improved Security
- implementation status
- Complete
- total cost
- Ksh 2,900,000
- estimate
- Ksh 2,500,000
Nursery Schools
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2004
- action
- Rehabilitation Of 19 Classes
- output
- Improve Education
- implementation status
- Complete
- total cost
- Ksh 2,550,000
- estimate
- Ksh 1,800,000
Mutulani Dam
- location
-
Watema
(in Kaiti)
- year first funded
- 2008
- action
- Survey Work, Construction
- output
- Improve Water
- implementation status
- Complete
- total cost
- Ksh 2,378,750
- estimate
- Ksh 0
Kemanzi Dam
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2008
- action
- Survey Work, Construction
- output
- Improve Water
- implementation status
- Complete
- total cost
- Ksh 2,378,750
- estimate
- Ksh 0
Kwa Nthekani Dam
- location
-
Watema
(in Kaiti)
- year first funded
- 2008
- action
- Survey Work, Construction
- output
- Improve Water
- implementation status
- Complete
- total cost
- Ksh 2,378,750
- estimate
- Ksh 0
Wautu Dam
- location
-
Ilima
(in Kaiti)
- year first funded
- 2008
- action
- Survey Work, Construction
- output
- Improve Water
- implementation status
- Complete
- total cost
- Ksh 2,378,750
- estimate
- Ksh 0
Mbooni Dam
- location
-
Kee
(in Kaiti)
- year first funded
- 2006
- action
- Survey Work, Scooping, Excavation
- output
- Increase Water Source
- implementation status
- Complete
- total cost
- Ksh 2,378,750
- estimate
- Ksh 2,500,000
Kilala Hill Dam
- location
-
Kilala
(in Kaiti)
- year first funded
- 2008
- action
- Survey Work, Construction
- output
- Improve Water
- implementation status
- Complete
- total cost
- Ksh 2,378,750
- estimate
- Ksh 0
Kinyuani Dam
- location
-
Kilala
(in Kaiti)
- year first funded
- 2008
- action
- Survey Work, Construction
- output
- Improve Water
- implementation status
- Complete
- total cost
- Ksh 2,378,750
- estimate
- Ksh 0
Nthonzweni Dam
- location
-
Kee
(in Kaiti)
- year first funded
- 2008
- action
- Survey Work, Construction
- output
- Improve Water
- implementation status
- Complete
- total cost
- Ksh 2,378,750
- estimate
- Ksh 0
Kwa Kivinda Dam
- location
-
Watema
(in Kaiti)
- year first funded
- 2008
- action
- Survey Work, Construction
- output
- Improve Water
- implementation status
- Complete
- total cost
- Ksh 2,378,750
- estimate
- Ksh 0
Kyanduu Dam
- location
-
Watema
(in Kaiti)
- year first funded
- 2008
- action
- Survey Work, Construction
- output
- Improve Water
- implementation status
- Ongoing
- total cost
- Ksh 2,378,750
- estimate
- Ksh 0
Kee Divisional Headquarters
- location
-
Kee
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Office
- output
- Improved Security
- implementation status
- Complete
- total cost
- Ksh 2,100,000
- estimate
- Ksh 2,500,000
Kavata Nzou Dispensary
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Houses
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 1,850,000
- estimate
- Ksh 1,800,000
Inyokoni Secondary School
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Computer Room
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 1,700,000
- estimate
- Ksh 4,000,000
Ehabilitation Of Primary Schools
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Classes
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 1,620,000
- estimate
- Ksh 3,500,000
Ehabilitaion Of Primary School
- location
-
Kikoko
(in Kaiti)
- year first funded
- 2005
- action
- Rehabilitation Of A Cost Of 100 Per School
- output
- Better Education Facilities
- implementation status
- Complete
- total cost
- Ksh 1,600,000
- estimate
- Ksh 4,800,000
Usi Uasa Water Project
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2003
- action
- Construction Of Water With Piping Works Survey
- output
- Improved Water Use
- implementation status
- Complete
- total cost
- Ksh 1,582,000
- estimate
- Ksh 2,500,000
Ilovoto Water Project
- location
-
Kikoko
(in Kaiti)
- year first funded
- 2003
- action
- Construction Of Water Intake, Piping Works, Survey Works
- output
- Improved Sanitation
- implementation status
- Ongoing
- total cost
- Ksh 1,582,000
- estimate
- Ksh 2,000,000
Nthangu Borehole
- location
-
Kilala
(in Kaiti)
- year first funded
- 2004
- action
- Survey Works, Piping Water
- output
- Increase Water Project
- implementation status
- Ongoing
- total cost
- Ksh 1,500,000
- estimate
- Ksh 3,000,000
Kee Comm Dispensary
- location
-
Kee
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of A Dispensary
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 1,400,000
- estimate
- Ksh 1,500,000
Matundu Water Project
- location
-
Watema
(in Kaiti)
- year first funded
- 2004
- action
- Survey Work, Construction Of Water Intake
- output
- Increase Water Use
- implementation status
- Ongoing
- total cost
- Ksh 1,300,000
- estimate
- Ksh 3,500,000
Ehabilitation Of Seven Secondary School
- location
-
Watema
(in Kaiti)
- year first funded
- 2005
- action
- Rehabilitation Of Classes
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 1,300,000
- estimate
- Ksh 5,600,000
Kikonde Dam
- location
-
Kee
(in Kaiti)
- year first funded
- 2003
- action
- Expansion Of The Dam, Piping Works, Survey Works
- output
- Improved Water
- implementation status
- Complete
- total cost
- Ksh 1,291,000
- estimate
- Ksh 2,500,000
Meithui Water Project
- location
-
Watema
(in Kaiti)
- year first funded
- 2004
- action
- Survey Work, Construction Of Water Intake
- output
- Increase Water Use
- implementation status
- Complete
- total cost
- Ksh 1,250,000
- estimate
- Ksh 4,000,000
Inyoonywa Water Project
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2006
- action
- Survey Work
- output
- Increase Water Source
- implementation status
- Complete
- total cost
- Ksh 1,200,000
- estimate
- Ksh 6,000,000
Ehabilitation Of Secondary School
- location
-
Kikoko
(in Kaiti)
- year first funded
- 2006
- action
- Rehabilitation At A Cost Of 300,000/=
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 1,200,000
- estimate
- Ksh 3,200,000
Kithuni Dispensary
- location
-
Kee
(in Kaiti)
- year first funded
- 2003
- action
- Construction Of Houses
- output
- Improve Health
- implementation status
- Ongoing
- total cost
- Ksh 1,121,000
- estimate
- Ksh 1,000,500
Mwaani Dispensary
- location
-
Ilima
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Houses
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 1,100,000
- estimate
- Ksh 2,500,000
Primary School s
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2004
- action
- Rehabilitation Of Schools At A Cost Of 100,000/= Each.
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 1,100,000
- estimate
- Ksh 3,300,000
Seven Primary School
- location
-
Kee
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Classes
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 1,100,000
- estimate
- Ksh 2,100,000
Ehabilitation Of Schools
- location
-
Kilala
(in Kaiti)
- year first funded
- 2005
- action
- Rehabilitation Of Cost Of 100,000/= Per School
- output
- Improve Education
- implementation status
- Ongoing
- total cost
- Ksh 1,100,000
- estimate
- Ksh 4,500,000
Musyani Water Project
- location
-
Ilima
(in Kaiti)
- year first funded
- 2003
- action
- Construction Of Water Weir, Survey Work
- output
- Improved Water Use
- implementation status
- Ongoing
- total cost
- Ksh 1,082,000
- estimate
- Ksh 400,000
Kilala Borehole
- location
-
Kilala
(in Kaiti)
- year first funded
- 2003
- action
- Distribution Of Water Piping Works. Construction Of Water Breathers
- output
- Improved Water Use
- implementation status
- Complete
- total cost
- Ksh 1,032,000
- estimate
- Ksh 3,000,000
Watema Borehole
- location
-
Watema
(in Kaiti)
- year first funded
- 2004
- action
- Survey Work, Water Drilling Of The Borehole
- output
- Increase Water Use
- implementation status
- Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 600,000
Mangala Dispensary
- location
-
Watema
(in Kaiti)
- year first funded
- 2003
- action
- Construction For Both Dispensary And Residential Houses
- output
- Improved Health Facility
- implementation status
- Complete
- total cost
- Ksh 932,000
- estimate
- Ksh 2,000,000
Iuani Dispensary
- location
-
Iuani
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of House
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 900,000
- estimate
- Ksh 200,000
Komu Secondary School
- location
-
Ilima
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Classes
- output
- Improve Education Facility
- implementation status
- Complete
- total cost
- Ksh 900,000
- estimate
- Ksh 3,000,000
Thomeandu Secondary School
- location
-
Kikoko
(in Kaiti)
- year first funded
- 2004
- action
- Rehabilitation Of Classes
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 800,000
- estimate
- Ksh 2,000,000
Ndolo Primary School
- location
-
Ilima
(in Kaiti)
- year first funded
- 2005
- action
- Rehabilitation Of Classes
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 800,000
- estimate
- Ksh 3,000,000
Kyambeke Dispensary
- location
-
Ilima
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Houses
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 800,000
- estimate
- Ksh 4,000,000
Mbooni Water Project
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2006
- action
- Survey Work, Construction
- output
- Increase Water Source
- implementation status
- Complete
- total cost
- Ksh 800,000
- estimate
- Ksh 5,000,000
Dispensary
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2006
- action
- Construction Houses
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 800,000
- estimate
- Ksh 2,000,000
Kyumani Water Project
- location
-
Kikoko
(in Kaiti)
- year first funded
- 2004
- action
- Survey Work, Construction Of Intake
- output
- Increase Water Use
- implementation status
- Operrational
- total cost
- Ksh 800,000
- estimate
- Ksh 3,500,000
Musalala Dispensary
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Lab / Residential House
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 800,000
- estimate
- Ksh 2,500,000
Ngangaithe Drift
- location
-
Kilala
(in Kaiti)
- year first funded
- 2005
- action
- Survey Work, Construction Drift
- output
- Ease Transport
- implementation status
- Complete
- total cost
- Ksh 800,000
- estimate
- Ksh 2,000,000
Ndulu Drift
- location
-
Watema
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Drift
- output
- Ease Transport
- implementation status
- Complete
- total cost
- Ksh 800,000
- estimate
- Ksh 6,000,000
Uthunzuuni Water Project
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Dam
- output
- Increase Water Source
- implementation status
- Complete
- total cost
- Ksh 800,000
- estimate
- Ksh 4,000,000
Kyambeke Chiefs Office
- location
-
Ilima
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Office
- output
- Improve Security
- implementation status
- Ongoing
- total cost
- Ksh 750,000
- estimate
- Ksh 1,000,000
Kyuasini Dispensary
- location
-
Ukia
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Houses
- output
- Improve Houses
- implementation status
- Complete
- total cost
- Ksh 700,000
- estimate
- Ksh 800,000
Ikalyoni Dispensary
- location
-
Ukia
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Houses
- output
- Improve Health
- implementation status
- Ongoing
- total cost
- Ksh 700,000
- estimate
- Ksh 800,000
Kaiti Drift
- location
-
Kee
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Drift
- output
- Improve Transportation
- implementation status
- Complete
- total cost
- Ksh 700,000
- estimate
- Ksh 6,000,000
Wautu Assistant Chief Office
- location
-
Ilima
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Office
- output
- Improve Security
- implementation status
- Complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,000,000
Kaumoni Dam
- location
-
Kilala
(in Kaiti)
- year first funded
- 2005
- action
- Survey Work, Excavation / Scooping
- output
- Increase Water Use
- implementation status
- Ongoing
- total cost
- Ksh 700,000
- estimate
- Ksh 1,500,000
Mwaani Secondary School
- location
-
Ilima
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Classes
- output
- Improve Education Facilities
- implementation status
- Ongoing
- total cost
- Ksh 700,000
- estimate
- Ksh 2,000,000
Kitandi Kwa Mbuvi Water Project
- location
-
Watema
(in Kaiti)
- year first funded
- 2006
- action
- Survey Work, Excavation, Scooping
- output
- Improve Access To Water
- implementation status
- Complete
- total cost
- Ksh 650,000
- estimate
- Ksh 1,500,000
Ndumani Dam
- location
-
Watema
(in Kaiti)
- year first funded
- 2006
- action
- Survey Work, Excavation, Scooping
- output
- Increase Water Resources
- implementation status
- Complete
- total cost
- Ksh 650,000
- estimate
- Ksh 1,500,000
Ap Line
- location
-
Kikoko
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Office
- output
- Improve Security
- implementation status
- Complete
- total cost
- Ksh 600,000
- estimate
- Ksh 1,000,000
Water
- location
-
Kikoko
(in Kaiti)
- year first funded
- 2004
- action
- Survey Work, Construction
- output
- Increase Water Resource
- implementation status
- Ongoing
- total cost
- Ksh 600,000
- estimate
- Ksh 3,000,000
Kaiti Youth Poly
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Classes
- output
- Improve Technical Facilities
- implementation status
- Complete
- total cost
- Ksh 600,000
- estimate
- Ksh 2,000,000
Ithemboni Dam
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2003
- action
- Excavation/Scooping
- output
- Improved Water
- implementation status
- Complete
- total cost
- Ksh 582,000
- estimate
- Ksh 8,000,000
Mukuyuni Health Centre
- location
-
Ukia
(in Kaiti)
- year first funded
- 2003
- action
- Installation Of Electrical Fittings / Rehabilitation Of Residential Houses
- output
- Improved Health
- implementation status
- Complete
- total cost
- Ksh 582,000
- estimate
- Ksh 2,000,000
Kilala Dip
- location
-
Kilala
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of A Dip
- output
- Reduce Disease Outbreak
- implementation status
- Complete
- total cost
- Ksh 525,000
- estimate
- Ksh 1,000,000
Kinyuani Dam
- location
-
Kilala
(in Kaiti)
- year first funded
- 2006
- action
- Excavation And Scooping
- output
- Increase Water Source
- implementation status
- Ongoing
- total cost
- Ksh 500,000
- estimate
- Ksh 1,500,000
Ndolo Secondary School
- location
-
Ilima
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Lab
- output
- Enhance Education
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 2,000,000
Kivani Dispensary
- location
-
Kivani
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Lab
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 1,500,000
Youth Poly
- location
-
Kilala
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Houses
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 800,000
Nthangu Dispensary
- location
-
Kilala
(in Kaiti)
- year first funded
- 2004
- action
- Survey Works, Drilling Borehole, Piping Water
- output
- Improve Health Facility
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 2,000,000
Kithembe Chief Office
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Office
- output
- Improve Security
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 700,000
Dispensary
- location
-
Ukia
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Houses
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 2,000,000
Kee Secondary School
- location
-
Kee
(in Kaiti)
- year first funded
- 2006
- action
- Completion Of D/Hall
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 1,200,000
Access Road
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2006
- action
- Bush Clearing / Leveling
- output
- Ease Transport
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 400,000
Kyanthuli Dam
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2004
- action
- Survey Work, Water Drilling Of The Borehole
- output
- Increase Water Use
- implementation status
- Complete
- total cost
- Ksh 450,000
- estimate
- Ksh 2,000,000
Kasunguni Water Project
- location
-
Watema
(in Kaiti)
- year first funded
- 2006
- action
- Survey Work, Piping
- output
- Increase Water Source
- implementation status
- Ongoing
- total cost
- Ksh 400,000
- estimate
- Ksh 2,000,000
Nthimbani Dispensary
- location
-
Iuani
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Houses
- output
- Provide Health
- implementation status
- Ongoing
- total cost
- Ksh 400,000
- estimate
- Ksh 1,500,000
Kyanzenzeni Dispensary
- location
-
Ilima
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of A House
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 3,500,000
Nguluni Water Project
- location
-
Watema
(in Kaiti)
- year first funded
- 2005
- action
- Survey Work And Expansion
- output
- Increase Water Use
- implementation status
- Ongoing
- total cost
- Ksh 400,000
- estimate
- Ksh 3,000,000
Ikalyoni Dam
- location
-
Kee
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Dam
- output
- Prevent Soil Loss
- implementation status
- Ongoing
- total cost
- Ksh 400,000
- estimate
- Ksh 4,000,000
Kee Secondary School
- location
-
Kee
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Lab
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 2,000,000
Kavata Nzou Cattle Dip
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2006
- action
- Construction And Purchase Of Acaracides
- output
- Reduce Disease Outbreak
- implementation status
- Ongoing
- total cost
- Ksh 400,000
- estimate
- Ksh 1,500,000
Itithini Dispensary
- location
-
Iuani
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of House
- output
- Improve Health
- implementation status
- Ongoing
- total cost
- Ksh 400,000
- estimate
- Ksh 2,000,000
Kalongo Kivoko Electrical Line
- location
-
Kikoko
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Electricity
- output
- Improve Electricity
- implementation status
- Ongoing
- total cost
- Ksh 400,000
- estimate
- Ksh 850,000
Kaumoni Ap Line
- location
-
Kilala
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Houses
- output
- Improve Security
- implementation status
- Complete
- total cost
- Ksh 350,000
- estimate
- Ksh 1,500,000
Ikalyoni Secondary School
- location
-
Kee
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Classes
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 350,000
- estimate
- Ksh 700,000
Ikalyoni Assistant Chiefs Offices
- location
-
Kee
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Ass. ChiefS Office
- output
- Improve Security
- implementation status
- Ongoing
- total cost
- Ksh 300,000
- estimate
- Ksh 800,000
Kilala Ap Line
- location
-
Kilala
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Houses
- output
- Improve Security
- implementation status
- Ongoing
- total cost
- Ksh 300,000
- estimate
- Ksh 1,500,000
Itandi Primary School
- location
-
Kilala
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Classes
- output
- Improve Education Facilities
- implementation status
- Ongoing
- total cost
- Ksh 300,000
- estimate
- Ksh 3,000,000
Kavata Nzou Kathuli Kiniu Roa
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2004
- action
- Bush Clearing And Leveling Of The Road
- output
- Ease Transport
- implementation status
- Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 2,500,000
Planting
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2006
- action
- Purchase Tree Seedling
- output
- Increase Vegetation Cover
- implementation status
- Complete
- total cost
- Ksh 278,000
- estimate
- Ksh 1,500,000
Kanga Primary School
- location
-
Ilima
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Classes
- output
- Improve Education
- implementation status
- Complete
- total cost
- Ksh 260,000
- estimate
- Ksh 900,000
Kambuku Primary School
- location
-
Ilima
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Classes
- output
- Improve Education Facility
- implementation status
- Ongoing
- total cost
- Ksh 250,000
- estimate
- Ksh 2,000,000
Isovya Youth Poly
- location
-
Ilima
(in Kaiti)
- year first funded
- 2006
- action
- Construction
- output
- Improve Education
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 800,000
Isovya Secondary School
- location
-
Ilima
(in Kaiti)
- year first funded
- 2004
- action
- Construction Of Class
- output
- Improve Education
- implementation status
- Ongoing
- total cost
- Ksh 200,000
- estimate
- Ksh 2,200,000
Kilala Electricity
- location
-
Kilala
(in Kaiti)
- year first funded
- 2004
- action
- Installation Of Electricity
- output
- Improve Electricity
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 1,000,000
Electricity
- location
-
Kilala
(in Kaiti)
- year first funded
- 2006
- action
- Installation Of Electricity
- output
- Enhance Access To Electricity
- implementation status
- Ongoing
- total cost
- Ksh 200,000
- estimate
- Ksh 2,000,000
Kiluluini Primary School
- location
-
Ilima
(in Kaiti)
- year first funded
- 2006
- action
- Rehabilitation Of Classes
- output
- Improve Education
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 800,000
Kaumoni Cattle Dip
- location
-
Kilala
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of A Dip
- output
- Reduce Disease Outbreak
- implementation status
- Complete
- total cost
- Ksh 175,000
- estimate
- Ksh 1,000,000
Kwa Kali Dam
- location
-
Watema
(in Kaiti)
- year first funded
- 2006
- action
- Fencing Of The Dam
- output
- Improve Water Sanitation
- implementation status
- Ongoing
- total cost
- Ksh 150,000
- estimate
- Ksh 4,000,000
Kee Chiefs Office
- location
-
Kee
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Office
- output
- Improve Security
- implementation status
- Ongoing
- total cost
- Ksh 150,000
- estimate
- Ksh 400,000
Kee Assistant Chiefs Office
- location
-
Kee
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Office
- output
- Improve Security
- implementation status
- Ongoing
- total cost
- Ksh 150,000
- estimate
- Ksh 200,000
Watema Dam
- location
-
Watema
(in Kaiti)
- year first funded
- 2006
- action
- Fencing Of The Dam
- output
- Improve Water Sanitation
- implementation status
- Ongoing
- total cost
- Ksh 150,000
- estimate
- Ksh 4,000,000
Kayumba Dam
- location
-
Kee
(in Kaiti)
- year first funded
- 2006
- action
- Construction / Fencing Of Dam
- output
- Increase Water Resource
- implementation status
- Ongoing
- total cost
- Ksh 150,000
- estimate
- Ksh 800,000
Ehabilitation Of Secondary Schools
- location
-
Kithembe
(in Kaiti)
- year first funded
- 2005
- action
- Rehabilitation Of A Cost Of 4,000,000/= Per School
- output
- Improve Education Facilities
- implementation status
- Complete
- total cost
- Ksh 120,000
- estimate
- Ksh 3,000,000
Chiefs Office Mutulani
- location
-
Watema
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Office
- output
- Improve Security
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 500,000
Maluunda, Mwaani / Wautu Dispensary
- location
-
Ilima
(in Kaiti)
- year first funded
- 2006
- action
- Rehabilitation / Acaracides
- output
- Reduce Disease Outbreak
- implementation status
- Ongoing
- total cost
- Ksh 100,000
- estimate
- Ksh 900,000
Chief Office Kaumoni
- location
-
Kilala
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Office
- output
- Improve Security
- implementation status
- Ongoing
- total cost
- Ksh 100,000
- estimate
- Ksh 800,000
Wautu Assistant Chief Office
- location
-
Ilima
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Office
- output
- Improve Security
- implementation status
- Ongoing
- total cost
- Ksh 100,000
- estimate
- Ksh 800,000
Chief Office
- location
-
Kilala
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Office
- output
- Improve Security
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 1,000,000
Chief Office
- location
-
Kilungu
(in Kaiti)
- year first funded
- 2005
- action
- Construction Of Office
- output
- Improve Health
- implementation status
- Complete
- total cost
- Ksh 80,000
- estimate
- Ksh 200,000
Chiefs Office Kilala
- location
-
Kilala
(in Kaiti)
- year first funded
- 2006
- action
- Construction Of Office
- output
- Increase Security
- implementation status
- Ongoing
- total cost
- Ksh 50,000
- estimate
- Ksh 800,000