The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Kilgoris Girls Secondary School
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2003
- action
- Completion of 4 Classes 1 Dorm
- output
- Complete 2 classes
- implementation status
- 2nd allocation
- total cost
- Ksh 5,500,000
- estimate
- Ksh 2,500,000
CDF Office Extension & Furniture
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2009
- action
- Complete and furnish an extension of one storey office block currently on going
- output
- -
- implementation status
- not known
- total cost
- Ksh 4,000,000
- estimate
- Ksh 4,000,000
Siria High School
- location
-
Moyoi
(in Kilgoris)
- year first funded
- 2003
- action
- Roofing the Dormitory
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 3,200,000
- estimate
- Ksh 0
Enoosaen Girls
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2005
- action
- Completion of 4 classrooms and 1 Dormitory
- output
- Complete 4 classes 1 dorm
- implementation status
- On going
- total cost
- Ksh 2,900,000
- estimate
- Ksh 200,000
Kaplecho Girls Secondary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 4 classes
- output
- Complete 24 Class
- implementation status
- On going
- total cost
- Ksh 2,700,000
- estimate
- Ksh 1,400,000
Pirrar Girls Secondary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2005
- action
- Con 4 Cl 6 Pit Latrines
- output
- Complete and in use
- implementation status
- On going
- total cost
- Ksh 2,400,000
- estimate
- Ksh 1,400,000
Kilgoris Youth Polytechnic
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2008
- action
- To construct 4 classes
- output
- To complete 4 classes
- implementation status
- not known
- total cost
- Ksh 2,000,000
- estimate
- Ksh 3,000,000
Sosio Secondary school
- location
-
Ololchani
(in Kilgoris)
- year first funded
- 2008
- action
- Construction to completion of 4 classes
- output
- To complete 4 classes
- implementation status
- On going
- total cost
- Ksh 2,000,000
- estimate
- Ksh 4,500,000
Poroko secondary School
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 4 C 2 Pit La
- output
- Completeand in use
- implementation status
- 2nd allocation
- total cost
- Ksh 1,800,000
- estimate
- Ksh 1,400,000
Nkararo Secondary School
- location
-
Nkararo
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 2 classes
- output
- Complete 2 Classes
- implementation status
- On going
- total cost
- Ksh 1,700,000
- estimate
- Ksh 700,000
Oldonyo Orok secondary School
- location
-
Angata
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 3 Classes
- output
- Complete Classes
- implementation status
- On going
- total cost
- Ksh 1,600,000
- estimate
- Ksh 1,050,000
Enolkupelia Primary School
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 3 classes
- output
- Complete 3 Classes
- implementation status
- 2nd Alloction
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,050,000
Enekeshui primary Schooloo
- location
-
Kapune
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 4 Classes
- output
- Complete 4 Classes
- implementation status
- On going
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,400,000
Shankoe Secondary School
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 4 Classes 2
- output
- Complete 3 classes
- implementation status
- 2nd allocation
- total cost
- Ksh 1,150,000
- estimate
- Ksh 1,400,000
Oloibor Soito primary School
- location
-
Olomismis
(in Kilgoris)
- year first funded
- 2003
- action
- Complete 4 Classrooms
- output
- Complete 1 classes
- implementation status
- Complete
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,400,000
Nkararo Health Centre
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of dispensary Block
- output
- Complete Disp Block
- implementation status
- On going
- total cost
- Ksh 1,100,000
- estimate
- Ksh 0
Murkan Secondary School
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2003
- action
- Construct1,1 dom
- output
- Complete, 1 dorm
- implementation status
- On going
- total cost
- Ksh 1,100,000
- estimate
- Ksh 2,350,000
E/Dikirr Secondary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of Dom
- output
- Complete of Dorm.
- implementation status
- On going
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,000,000
Nkararo Primary School
- location
-
Nkararo
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 3 classes
- output
- Complete 3 Classes
- implementation status
- On going
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,050,000
Tororek Dispensary
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of Staff House
- output
- Complete Staff House
- implementation status
- 2nd Allocation
- total cost
- Ksh 1,100,000
- estimate
- Ksh 400,000
Kilena primary school
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2007
- action
- Completion of 2 classes currently at slab level
- output
- To complete the 2 class
- implementation status
- On going
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,150,000
Nkoirienito Primary School
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 1 Class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 1,000,000
- estimate
- Ksh 0
Mutenkuarr primary School
- location
-
Olomismis
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 3 Classes
- output
- Complete Classes
- implementation status
- not known
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,050,000
Olalui Primary School
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2003
- action
- Renovate 8 Classrooms
- output
- Complete 2 classes
- implementation status
- 2nd allocation
- total cost
- Ksh 1,000,000
- estimate
- Ksh 400,000
Mashangwa primary School
- location
-
Angata
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 2 Classess
- output
- Complete 3 classes
- implementation status
- 2nd allocation
- total cost
- Ksh 1,000,000
- estimate
- Ksh 700,000
Masurura Comm. H/ C
- location
-
Masurura
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of health center
- output
- complete H/C
- implementation status
- On going
- total cost
- Ksh 950,000
- estimate
- Ksh 600,000
Moita Primary School
- location
-
Nkararo
(in Kilgoris)
- year first funded
- 2004
- action
- Construct8 classes
- output
- Complete 8 Classes
- implementation status
- On going
- total cost
- Ksh 900,000
- estimate
- Ksh 2,800,000
Nyasita Primary School
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 3 Classes
- output
- Complete Classes
- implementation status
- On going
- total cost
- Ksh 900,000
- estimate
- Ksh 1,050,000
Mashangwa Disp
- location
-
Angata
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of Disp Block
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 900,000
- estimate
- Ksh 600,000
Ilkerin Secondary school
- location
-
Ilkerin
(in Kilgoris)
- year first funded
- 2008
- action
- Construction of 1 classes
- output
- To complete the 1 class
- implementation status
- On going
- total cost
- Ksh 900,000
- estimate
- Ksh 2,000,000
Enoosaen Boys Secondary school
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 2 classes
- output
- To complete the 2 class
- implementation status
- On going
- total cost
- Ksh 900,000
- estimate
- Ksh 350,000
Olmelil secondary School
- location
-
Kapune
(in Kilgoris)
- year first funded
- 2003
- action
- Construction 1 Class
- output
- complete 1 Class
- implementation status
- On going
- total cost
- Ksh 900,000
- estimate
- Ksh 1,200,000
Nailare Primary School
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 2 Classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 800,000
- estimate
- Ksh 700,000
Enkipai Primary School
- location
-
Emarti
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 2 classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 800,000
- estimate
- Ksh 700,000
Kapweria secondary School
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2003
- action
- Dorm Construction
- output
- Complete dorm
- implementation status
- On going
- total cost
- Ksh 800,000
- estimate
- Ksh 700,000
Angata Barrikoi Secondary School
- location
-
Angata
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 2 Classess
- output
- Complete Classes
- implementation status
- On going
- total cost
- Ksh 800,000
- estimate
- Ksh 700,000
Kondamet Dieps
- location
-
Angata
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of Disp Block
- output
- Complete Dispensary Block
- implementation status
- On going
- total cost
- Ksh 800,000
- estimate
- Ksh 600,000
Olmotonyi primary School
- location
-
Moyoi
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 2 Classess
- output
- Complete 2 classes
- implementation status
- 2nd allocation
- total cost
- Ksh 750,000
- estimate
- Ksh 700,000
Kamermeru primarySchool
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 class
- output
- complete 1 Class
- implementation status
- On going
- total cost
- Ksh 737,000
- estimate
- Ksh 350,000
Sitoka Primary School
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 2 classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 719,285
- estimate
- Ksh 700,000
Abbosi - Kelonget Road
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2005
- action
- Open Access Road
- output
- Complete Ac Rd
- implementation status
- On going
- total cost
- Ksh 700,000
- estimate
- Ksh 300,000
Naarolong Dispensary
- location
-
Masurura
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of dispensary Block
- output
- Complete Disp Block
- implementation status
- On going
- total cost
- Ksh 700,000
- estimate
- Ksh 600,000
Enoosaen Boys Secondary
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 1 class
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 700,000
- estimate
- Ksh 350,000
Kinyibol primary School
- location
-
Masurura
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 5 classes
- output
- Complete 5 Classes
- implementation status
- On going
- total cost
- Ksh 700,000
- estimate
- Ksh 1,750,000
Kiletien secondary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 700,000
- estimate
- Ksh 0
Isokon Primary School
- location
-
Oloirien
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 2 Classess
- output
- Complete Classes
- implementation status
- On going
- total cost
- Ksh 700,000
- estimate
- Ksh 700,000
Olmaram Nyasita Road
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2005
- action
- Open Access Road
- output
- Complete Ac RD
- implementation status
- Complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,200,000
Shankoe primary School
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2003
- action
- Renovate 8 Classrooms
- output
- Complete 2 classes
- implementation status
- Complete
- total cost
- Ksh 700,000
- estimate
- Ksh 400,000
Olkiloriti primary School
- location
-
Moyoi
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 4 Classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 650,000
- estimate
- Ksh 1,400,000
Chesoen Kaplecho Emarti RD
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2007
- action
- Open Access Road
- output
- complete Access RD
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 0
Ndamama Primary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of Classes
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 0
Olonkolin Primary School
- location
-
Emarti
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 4 classes
- output
- Complete 4 classes
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 1,400,000
Sosiana Primary School
- location
-
kimintet
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 2 classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 1,050,000
Mogondo Secondary School
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 4 classes
- output
- Complete 4 classes
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 1,400,000
Emarti primary School
- location
-
Emarti
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 350,000
Soget Primary School
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 350,000
Kurankuriki Dispensary
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of dispensaryBlock
- output
- Complete Disp Block
- implementation status
- Complete
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Olereko Primary School
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2004
- action
- Rehabilated 8 classes
- output
- Complete Rehabi
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 400,000
Naarolong Primary School
- location
-
Masurura
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 2 classes
- output
- Complete 2 Classes
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 700,000
Ndoinyo Primary School
- location
-
Masurura
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 2 classes
- output
- Complete 2 Classes
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 700,000
Ndamama secondary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2003
- action
- Roofing of classes
- output
- Complete roofing
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 350,000
Romosha Secondary School
- location
-
Kapune
(in Kilgoris)
- year first funded
- 2005
- action
- 4 Construction of Classes
- output
- 45% Complete
- implementation status
- Stalled
- total cost
- Ksh 600,000
- estimate
- Ksh 0
Osonkoroi Secondary School
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of 1 Class
- output
- Complete Ac RD
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 0
Angata Barrikoi primary School
- location
-
Angata
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 2 Classes
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 600,000
- estimate
- Ksh 700,000
Ole Malit primary School
- location
-
Moyoi
(in Kilgoris)
- year first funded
- 2005
- action
- Costruct 1 Class
- output
- Complete 1 class
- implementation status
- 2nd allocation
- total cost
- Ksh 600,000
- estimate
- Ksh 350,000
Ololchani Dispensary
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of Disp Block
- output
- Complete 1 class
- implementation status
- Complete
- total cost
- Ksh 550,000
- estimate
- Ksh 700,000
Oronkai primary School
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2005
- action
- 2 Cl & Adm Office
- output
- 75% completete
- implementation status
- On going
- total cost
- Ksh 550,000
- estimate
- Ksh 0
Tororek Primary School
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 1 class
- output
- complete 1 Class
- implementation status
- On going
- total cost
- Ksh 550,000
- estimate
- Ksh 350,000
Tumpelian Primary School
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 4 Classes
- output
- Complete Classes
- implementation status
- Well Done
- total cost
- Ksh 550,000
- estimate
- Ksh 0
Angata Disp
- location
-
Angata
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of Disp Block
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 600,000
Olepoipoi primary School
- location
-
Moyoi
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 3 Classes
- output
- Complete 2 classes
- implementation status
- 2nd allocation
- total cost
- Ksh 500,000
- estimate
- Ksh 1,050,000
Olopikidong'oi D.E.B mixed Primary school
- location
-
Oloirien
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of classrooms
- output
- Complete Classes
- implementation status
- not known
- total cost
- Ksh 500,000
- estimate
- Ksh 0
Snr Chief Nkoidilla Primary School
- location
-
Oloirien
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 2 Class
- output
- Complete Classes
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 0
Olkiloriti- Osupukiai- Isokoni Rd
- location
-
oloirien
(in Kilgoris)
- year first funded
- 2006
- action
- Open Access Road
- output
- Complete Dispensary Block
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 400,000
Township primary School
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 Classroom
- output
- Complete 4 classes
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 400,000
Nganayio dispensary
- location
-
Olomismis
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of health centerentre
- output
- Complete Dispensary Block
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 700,000
Osinoni Primary School
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 Class
- output
- Complete Spring
- implementation status
- Ongoing
- total cost
- Ksh 500,000
- estimate
- Ksh 0
Saparinko primary School
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 Class
- output
- Complete 1 class
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 350,000
Oltanki primary school
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2007
- action
- Constructing a new class
- output
- To complete 1 class
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 200,000
Olpopong Primary School
- location
-
Emarti
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 4 classes
- output
- Complete 4 classes
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 700,000
Kapsasian Primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 2 classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 700,000
Sosianoi Dispensary
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of dispensaryBlock
- output
- Complete Disp Block
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 600,000
Ilpashire Primary School
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 2 classes
- output
- Complete 2 Classes
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 700,000
Oloontare Primary School
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 3 classes
- output
- Complete 3 Classes
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 1,050,000
Enoosaen Primary School
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 3 classes
- output
- Complete 3 Classes
- implementation status
- complete
- total cost
- Ksh 500,000
- estimate
- Ksh 1,050,000
Empurkel Primary School
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 1 class
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 350,000
Enoosaen Health Centre
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of dispensary Block
- output
- Complete Disp Block
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 600,000
OlenKare W/P
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2004
- action
- Spring Protection
- output
- Complete spring protection
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 300,000
Kisiara primary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 2 Classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 700,000
Shartuka secondary School
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2005
- action
- Adm. Block
- output
- Complete Adm. Block
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Kapune Dispenasry
- location
-
Kapune
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of Disp Block
- output
- Complete Dispensary Block
- implementation status
- Alocate more funds
- total cost
- Ksh 500,000
- estimate
- Ksh 600,000
Endonyo Onkopit primary School
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 2 Classes
- output
- Complete Classes
- implementation status
- not known
- total cost
- Ksh 500,000
- estimate
- Ksh 700,000
CDF Water tank
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2009
- action
- to purchase water to be used in the new office
- output
- -
- implementation status
- not known
- total cost
- Ksh 455,285
- estimate
- Ksh 455,285
Enooretet Primary School
- location
-
Nkararo
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 2 classes
- output
- Complete 2 Classes
- implementation status
- On going
- total cost
- Ksh 450,000
- estimate
- Ksh 700,000
Ildolisho Enolkupelian Rd
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2006
- action
- Open Acess Road
- output
- complete access road
- implementation status
- On going
- total cost
- Ksh 450,000
- estimate
- Ksh 500,000
Romosha Dispensary
- location
-
Kapune
(in Kilgoris)
- year first funded
- 2004
- action
- Construction Disp Block
- output
- Complete Dispensary Block
- implementation status
- On going
- total cost
- Ksh 450,000
- estimate
- Ksh 600,000
Mapashi primary School
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 class
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 444,636
- estimate
- Ksh 350,000
Tagitech Dispensary
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of Disp Block
- output
- Complete and in use
- implementation status
- Done
- total cost
- Ksh 437,000
- estimate
- Ksh 600,000
Nashili Enkare WP
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2006
- action
- Spring Protection
- output
- Complete Spring
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 0
Olengoloto Dispensary
- location
-
Olomismis
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of Disp Block
- output
- CompletE Dispensary Block
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 0
Mutenkuarr Olengoloto Road
- location
-
Olomismis
(in Kilgoris)
- year first funded
- 2006
- action
- Open Access Road
- output
- Complete Spring
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 500,000
Oltanki Water Project
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2006
- action
- Spring Protection
- output
- Complete Dispensary Block
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Osinoni Dispensary
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of Disp Block
- output
- Complete Dispensary Block
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
Osupuko Dispensary
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of Disp Block
- output
- Complete Renov
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
Chebara Primary School
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 350,000
Kurankuriki Primary School
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 2 classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
Changina primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 2 classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
Chilani primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 2 classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
St. Joseph's primary School
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2005
- action
- Renovate 8 Classrooms
- output
- Complete Renov
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Simotwet Secondary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 1 Class
- output
- Complete and in use
- implementation status
- More Funds
- total cost
- Ksh 400,000
- estimate
- Ksh 0
Osonkoroi primary School
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 2 Classes
- output
- Complete 4 classes
- implementation status
- 2nd allocation
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
Kilgoris D.E.B School
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2005
- action
- Construction 1 Class
- output
- Complete Renov
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Kiribwet Community Dispensary
- location
-
Emarti
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of dispensaryBlock
- output
- Complete Disp Block
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 600,000
Mokondo Primary School
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 2 classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
Olokwaya Tumpelian Rd
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2006
- action
- Open Access Road
- output
- complete AcRd
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 0
Kimintet Health centre
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2007
- action
- Construction dispensary Block
- output
- Cheq Stalled Re All
- implementation status
- On Going
- total cost
- Ksh 400,000
- estimate
- Ksh 0
Chemamit Dispensary
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2006
- action
- Disp Bl Partly Spon
- output
- Complete Disp Block
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 0
Esoit Tumpelian RD
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2005
- action
- Open Access Road
- output
- complete Access RD
- implementation status
- not known
- total cost
- Ksh 400,000
- estimate
- Ksh 0
Karda Primary School
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 class
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 350,000
Ntuka Primary School
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 2 classes
- output
- Complete 2 Classes
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
Nentekeny Primary School
- location
-
Nkararo
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 2 classes
- output
- Complete 2 Classes
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
Oldanyati Dispensary
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of dispensary Block
- output
- Complete Disp Block
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 600,000
Osagam Lenkop W/P
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2004
- action
- Spring Protection
- output
- complete spring protection
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 500,000
Mumeita Water Project
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2007
- action
- Spring Protection
- output
- Complete Spring protection
- implementation status
- not known
- total cost
- Ksh 400,000
- estimate
- Ksh 0
Meguarra primary School
- location
-
Kapune
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 2 Classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
Kuresiet Dispensary
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of Disp Block
- output
- Complete Dispensary Block
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 600,000
Njipiship Dispensary
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of Disp Block
- output
- Ongoing & 3 RM Com
- implementation status
- On going
- total cost
- Ksh 363,000
- estimate
- Ksh 0
Enkoiperiai primary School
- location
-
Angata
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 1 Class
- output
- Complete 1 class
- implementation status
- 2nd allocation
- total cost
- Ksh 350,000
- estimate
- Ksh 350,000
Emarti Dispensary
- location
-
Emarti
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of dispensaryBlock
- output
- Complete Disp Block
- implementation status
- Complete
- total cost
- Ksh 350,000
- estimate
- Ksh 0
Takitech Primary School
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 Class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Chelemei Primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Chepkisa Primary School
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Esoit Naibor primary School
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2006
- action
- Construct1 Class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Lelegoin primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Kapolecho Primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2004
- action
- Re-Construction of 2 classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 700,000
Ntulele Dispensary
- location
-
Emarti
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of dispensaryBlock
- output
- Complete Disp Block
- implementation status
- Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Mogor secondary School
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2007
- action
- Contsrution of 1 class
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Olpopong Secondary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of 1 class
- output
- Complet 1 class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Ilmeoshi Pre. School
- location
-
Emarti
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Ainamoi Primary School
- location
-
Emarti
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Sikawa Primary School
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 2 classes
- output
- Complete 2 Classes
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 700,000
Kiikat Primary School
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 2 classes
- output
- Complete 2 Classes
- implementation status
- Completed and in use
- total cost
- Ksh 300,000
- estimate
- Ksh 700,000
Masurura primary School
- location
-
Masurura
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 class
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 700,000
Olereko Dispensary
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of dispensary Block
- output
- Complete Disp Block
- implementation status
- Deviated
- total cost
- Ksh 300,000
- estimate
- Ksh 600,000
Ole Moroon W/P
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of health center
- output
- complete H/C
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Empurkel Comm. Rd
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2006
- action
- Open Acess Road
- output
- complete access road
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 600,000
Ogwedhi Kiikat Rd
- location
-
Masurura
(in Kilgoris)
- year first funded
- 2006
- action
- Open Acess Road
- output
- complete access road
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Osagam Naarolong Road
- location
-
Masurura
(in Kilgoris)
- year first funded
- 2007
- action
- Open Acess Road
- output
- complete ac Rd
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Oldanyati Primary
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of Classes
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Olasenua Primary School
- location
-
Sikawa
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of Classes
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Entargeeti Disp
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of dispensary Block
- output
- Complete Disp Block
- implementation status
- not known
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Kapune primary Schooloool
- location
-
Kapune
(in Kilgoris)
- year first funded
- 2004
- action
- Costruct 1 Class
- output
- complete 1 Class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Kaperekeiywo Road
- location
-
Kapune
(in Kilgoris)
- year first funded
- 2006
- action
- Open Access Road
- output
- Complete Access Road
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 400,000
Oronkai -Tororek Road
- location
-
Shartuka
(in Kilgoris)
- year first funded
- 2006
- action
- Open Access Road
- output
- Complete Ac Rd
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 700,000
Chesoen Cattle Dip
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of Cattle Dip
- output
- Complete Cattle Dip
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Ololchani primary School
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 2 Classes
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 700,000
Nyasita Enarau WP
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2007
- action
- Spring Protection
- output
- Complete Spring
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Sirua Enkiteng WP
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2006
- action
- Spring Protection
- output
- Complete Spring
- implementation status
- not known
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Olchoro Oirowua WP
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2006
- action
- Spring Protection
- output
- Complete Ac RD
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Ngendalel primary School
- location
-
Angata
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 4 Classes
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 1,400,000
Olmotonyi Dispensary
- location
-
Moyoi
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of Disp Block
- output
- Complete Dispensary Block
- implementation status
- 2nd allocation
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Ilkarian primary School
- location
-
Moyoi
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 2 Classes
- output
- Complete 4 classes
- implementation status
- 2nd allocation
- total cost
- Ksh 300,000
- estimate
- Ksh 700,000
Emurtoto Primary School
- location
-
Oloirien
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 1 Class
- output
- Complete 3 classes
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Ilopilukuny Pre. School
- location
-
Moyoi
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 1 Classes
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Olaitong primary School
- location
-
Angata
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 Class
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 350,000
Chebitok primary school
- location
-
E/ Dikirr
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 2 started classes
- output
- To complete the 2 class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Kipupu primary school
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2009
- action
- Constructing a new class
- output
- To complete 1 class
- implementation status
- On going
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Lelechonic Community Library
- location
-
E/Dkirr
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of Lib Block
- output
- Complete Lib Block
- implementation status
- On going
- total cost
- Ksh 291,449
- estimate
- Ksh 0
Mosocho Nentekeny R
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2006
- action
- Open Access Road
- output
- Complete Ac RD
- implementation status
- not known
- total cost
- Ksh 272,679
- estimate
- Ksh 0
Ololmong'i Pre School
- location
-
Oloirien
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 1 Class
- output
- Complete 2 classes
- implementation status
- On going
- total cost
- Ksh 250,000
- estimate
- Ksh 350,000
Ilmeshuki primary school
- location
-
Olalui
(in Kilgoris)
- year first funded
- 2009
- action
- Construction to completion of 1 class
- output
- To complete the 1 class
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 400,000
Murkan primary School
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2007
- action
- Construction 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Kibisorwet primary School
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2007
- action
- Construction 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Murkan junction Mogor Rd
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2007
- action
- Open Access Road
- output
- complete Access RD
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Operai Foot Bridge
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of foot brdge
- output
- Complete Foot bridge
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Chebitoik Primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 Class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Soymingin Primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Chepkoiyet Water Project
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2006
- action
- Spring Protection
- output
- Complete Spring
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Chebulu Primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of Classes
- output
- Complete Classes
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Ereko Primary School
- location
-
Nkararo
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 1 class
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 350,000
Enkiwancha Primary School
- location
-
Masurura
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 3 classes
- output
- Complete 3 Classes
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 1,050,000
Isampin Primary School
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 1 class
- output
- Complete 1 class
- implementation status
- Complete and in use
- total cost
- Ksh 200,000
- estimate
- Ksh 350,000
Enooretet Road
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2007
- action
- Open Acess Road
- output
- complete ac Rd
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Angaset primary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 1 class
- output
- complete 1 Class
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 350,000
Kelonget primary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 1 class
- output
- complete 1 Class
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 350,000
Abossi primary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 2 Classes
- output
- Complete 2 classes
- implementation status
- Alocate more funds
- total cost
- Ksh 200,000
- estimate
- Ksh 700,000
Ololmasani Water project
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2005
- action
- Spring Protecction
- output
- Complete Spring
- implementation status
- 2nd Allocation
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Selembu Cattle Dip
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2006
- action
- Costruct Cattle Dip
- output
- Complete Cattle Dip
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Cheplakwet Road
- location
-
Kapune
(in Kilgoris)
- year first funded
- 2007
- action
- Open Access Road
- output
- Complete Ac. R
- implementation status
- not known
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Olesentu Dispensary
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of Disp Block
- output
- Complete Dispensary Block
- implementation status
- 2nd allocation
- total cost
- Ksh 200,000
- estimate
- Ksh 700,000
Nyasita - Olalui Bridge
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2004
- action
- Open Access Road
- output
- Complete Ac RD
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Endoinyo Onkopit C.D.C
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of Office Block
- output
- Comp Off Blo
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Naronyo Primary School
- location
-
Olomismis
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of 1 Class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Olepoipoi Dispensary
- location
-
Moyoi
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of Disp Block
- output
- Complete Dispensary Block
- implementation status
- 2nd allocation
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Soimet Disp
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of Disp Block
- output
- Complete Dispensary Block
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Olgos Sopia Primary School
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 1 Class
- output
- Complete Classes
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Kigonor Primary School
- location
-
kImintet
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of classrooms
- output
- Complete Classes
- implementation status
- not known
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Chemamit Primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 1 class
- output
- Not Complete & in use
- implementation status
- On going
- total cost
- Ksh 200,000
- estimate
- Ksh 350,000
Sitoka Dispensary
- location
-
Kimintet
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of dispensaryBlock
- output
- Complete Disp Block
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Ilkeek oado Spring
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2005
- action
- Spring Protection
- output
- Complete spring protection
- implementation status
- On going
- total cost
- Ksh 194,559
- estimate
- Ksh 400,000
Empurkel Bridge
- location
-
Enoosaen
(in Kilgoris)
- year first funded
- 2005
- action
- Construction of Foot Bridge
- output
- Complete Foot Bridge
- implementation status
- complete
- total cost
- Ksh 155,364
- estimate
- Ksh 160,000
E/Dkirr Dispensary
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of dispensaryBlock
- output
- Complete Disp Block
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 0
Olalui Ilkutot Water project
- location
-
Osinoni
(in Kilgoris)
- year first funded
- 2006
- action
- Spring Protection
- output
- Complete Spring
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Ololtele Water Project
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2007
- action
- Spring Protection
- output
- Complete Ac RD
- implementation status
- On going
- total cost
- Ksh 150,000
- estimate
- Ksh 0
Olereko secondary School
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of 4 classes
- output
- Complete 4 classes
- implementation status
- On going
- total cost
- Ksh 130,000
- estimate
- Ksh 1,200,000
Chilani Cattle Dip
- location
-
E/Dkirr
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of Cattle Dip
- output
- Complete c. Dip
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 0
Kuresiet primary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2004
- action
- Construct1 class
- output
- complete 1 Class
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 350,000
Olmelil primary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 1 class
- output
- complete 1 Class
- implementation status
- Alocate more funds
- total cost
- Ksh 100,000
- estimate
- Ksh 350,000
Kapkosros primary School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 1 class
- output
- complete 1 Class
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 350,000
St. Thomas Aquinas School
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2003
- action
- Construction of 1 class
- output
- complete 1 Class
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 350,000
Kamaget Dispensary
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2004
- action
- Costruct Disp Block
- output
- Complete Dispensary Block
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Kimugul Cattle Dip
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2007
- action
- Construction of Cattle Dip
- output
- Complete Cattle Dip
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 0
Abossi - Chesoen Road
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2007
- action
- Open Access Road
- output
- Complete Ac Rd
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 0
Poroko Water Project
- location
-
Poroko
(in Kilgoris)
- year first funded
- 2004
- action
- Spring Protection
- output
- Complete Dispensary Block
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Olosayiet Water Project
- location
-
Olomismis
(in Kilgoris)
- year first funded
- 2006
- action
- Spring Protection
- output
- Complete H/ Centre
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 400,000
Ileleshwani WP
- location
-
Olomismis
(in Kilgoris)
- year first funded
- 2007
- action
- Spring Protection
- output
- -
- implementation status
- Ongoing
- total cost
- Ksh 100,000
- estimate
- Ksh 0
Kerinkani Disp
- location
-
oloirien
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of Disp Block
- output
- Complete 1 class
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 600,000
Simotwet primary school
- location
-
Ololmasani
(in Kilgoris)
- year first funded
- 2009
- action
- Construction of 1 classroom
- output
- To complete 1 class
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 0
Mogor primary Schooloo
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2003
- action
- Renovate 4 Classrooms
- output
- Complete 4 classes
- implementation status
- Allo. funds
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Lelechonik primary School
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of 1 class
- output
- Complete 1 Class
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 350,000
Mogor Dispensary
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2004
- action
- Construction of dispensary Block
- output
- Complete Disp Block
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 600,000
Chebungei Cattle Dip
- location
-
Murkan
(in Kilgoris)
- year first funded
- 2007
- action
- Construction ca Dip
- output
- Complete 1 cattle Dip
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 0
Tumda Cattle Dip
- location
-
E/Dikirr
(in Kilgoris)
- year first funded
- 2006
- action
- Construction of Dip
- output
- Complete Disp Block
- implementation status
- On going
- total cost
- Ksh 100,000
- estimate
- Ksh 0
St. Mathew E/Nkopit W/p
- location
-
Shankoe
(in Kilgoris)
- year first funded
- 2004
- action
- Spring Protection
- output
- Complete Spring
- implementation status
- No Work Done
- total cost
- Ksh 70,000
- estimate
- Ksh 100,000
Shololo Water Project
- location
-
Poroko
(in Kilgoris)
- action
- Spring Protection
- output
- Complete Spring
- implementation status
- On going
- total cost
- Ksh 0
- estimate
- Ksh 250,000