The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Projects in Lari
Education Bursary
- location
-
Lari
(in Lari)
- year first funded
- 2004
- action
- Award Of Bursary To Bright Students From Poor Backgrounds
- output
- Access To Proper Schooling
- implementation status
- Ongoing
- total cost
- Ksh 13,702,963
- estimate
- Ksh 0
Gitithia Girls Secondary School
- location
-
Gitithia
(in Lari)
- year first funded
- 2004
- action
- Construction Of 4 Classrooms, 1 Admn Block,
- output
- A New Cdf Fully Funded Girls High School
- implementation status
- Classrooms, Admin Block, Toilets, Fence
- total cost
- Ksh 6,200,000
- estimate
- Ksh 7,000,000
Office Administration
- location
-
Lari
(in Lari)
- year first funded
- 2003
- action
- Administration
- output
- Efficient Constituency Administration
- implementation status
- Ongoing
- total cost
- Ksh 5,669,748
- estimate
- Ksh 0
Kambaa/Githogoiyo Water Project
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Drilling & Equiping Of A Borehole Plus Distribution
- output
- Provision Of Water To Kambaa And Githogoiyo Communities
- implementation status
- Complete And In Use
- total cost
- Ksh 5,000,000
- estimate
- Ksh 5,000,000
Kamuchege Water Project
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2004
- action
- Drilling & Equiping Of A Borehole Plus Purchase Of Distribution Pipes
- output
- Provision Of Clean Water To Kamuchege Community
- implementation status
- Complete But Not In Use
- total cost
- Ksh 3,100,000
- estimate
- Ksh 3,500,000
Lari Health Centre
- location
-
Kirenga
(in Lari)
- year first funded
- 2004
- action
- Construction Of A Mortuary, Renovation Of A Tank & Purchase Of Medical Equipments
- output
- Modern Equipments & Clean Water Supply To The H.C.
- implementation status
- Equipments Purchased, Tank Complete & In Use. Mortuary Is At Planning Stage (Pdp Ongoing)
- total cost
- Ksh 3,080,000
- estimate
- Ksh 4,500,000
Mwimutoni Chosen Water Project
- location
-
Kirenga
(in Lari)
- year first funded
- 2003
- action
- Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Escarpment Community
- implementation status
- Complete & In Use
- total cost
- Ksh 3,014,144
- estimate
- Ksh 3,500,000
Lari Secondary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Purchase Of A 60 Seater School Bus
- output
- Modern School Bus
- implementation status
- Bus Delivered. Settlement Ongoing
- total cost
- Ksh 3,000,000
- estimate
- Ksh 4,500,000
Githirioni Water Project
- location
-
Lari
(in Lari)
- year first funded
- 2004
- action
- Drilling/Equiping Borehole, Water Points & Distribution
- output
- Provision Of Clean Water To Githirioni Community
- implementation status
- Complete & In Use
- total cost
- Ksh 2,978,000
- estimate
- Ksh 3,500,000
Uplands Primary School Kanyekin
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Construction Of Classrooms
- output
- A New Cdf Fully Funded Primary School
- implementation status
- Complete & In Use
- total cost
- Ksh 2,900,000
- estimate
- Ksh 4,000,000
Kagaa Dispensary
- location
-
Kamburu
(in Lari)
- year first funded
- 2004
- action
- Renovation Of Dispensary, Purchase Of Medical Equipments & Construction Of Septic Tank & Incenerator
- output
- Face Lift For The Dispensary And Provision Of Maternity Services To The Community;
- implementation status
- Face Lift & Purchase Of Equipments Complete
- total cost
- Ksh 2,900,000
- estimate
- Ksh 2,000,000
Kamuchege Dispensary
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2003
- action
- Construction And Equiping Of A New Dispensary
- output
- New Standard Modern Cdf Fully Funded Dispensary
- implementation status
- Interior Finishing And Equiping Ongoing
- total cost
- Ksh 2,863,918
- estimate
- Ksh 2,000,000
Kagaa Water Project
- location
-
Kamburu
(in Lari)
- year first funded
- 2005
- action
- Drilling And Equiping Of A Borehole Plus Water Distribution
- output
- Provision Of Clean Water To Kagaa Health Ctr & Community
- implementation status
- Complete & In Use
- total cost
- Ksh 2,710,000
- estimate
- Ksh 3,500,000
Gitithia Borehole
- location
-
Gitithia
(in Lari)
- year first funded
- 2005
- action
- Drilling & Equiping Of A Borehole Plus Purchase Of Distribution Pipes
- output
- Provision Of Clean Water To Gitithia Community
- implementation status
- Borehole Complete & In Use: Distribution Ongoing
- total cost
- Ksh 2,510,000
- estimate
- Ksh 3,500,000
Muiri Water Project
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2004
- action
- Drilling And Equiping Of A Borehole
- output
- Provision Of Clean Water To Muiri Community
- implementation status
- Complete But Not In Use
- total cost
- Ksh 2,500,000
- estimate
- Ksh 3,000,000
Juvenalis Secondary School
- location
-
Lari
(in Lari)
- year first funded
- 2004
- action
- Construction Of Classroom/ Lab, + Equipments & Electricity
- output
- Standard Modern Science Lab And Classroom. Power Supply To The Entire School
- implementation status
- Electricity & Classroom Projects Complete And In Use, Construction Of Lab Complete, Equiping Ongoing
- total cost
- Ksh 2,500,000
- estimate
- Ksh 4,000,000
Kagwe Township Primary School
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2004
- action
- Purchase Of Land And Construction Of A 2 Storey
- output
- Modern Classrooms
- implementation status
- Purchase Of Land Complete. Construction Of
- total cost
- Ksh 2,350,000
- estimate
- Ksh 4,500,000
Emergency Reserve
- location
-
Lari
(in Lari)
- year first funded
- 2008
- action
- Emergency Reserve
- output
- Emergency Reserve
- implementation status
- not known
- total cost
- Ksh 2,332,619
- estimate
- Ksh 0
Gathaiti Secondary School
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Construction Of 4 Classrooms, 1 Admn Block,
- output
- New Cdf Funded Secondary Sch. For Over 500 Students
- implementation status
- Ongoing: Interior Finishing For The 4 Classrooms Remaining
- total cost
- Ksh 2,000,000
- estimate
- Ksh 4,000,000
Gathima Secondary School
- location
-
Kamburu
(in Lari)
- year first funded
- 2007
- action
- Rehabilitation Of 2 Classrooms, Hall, Lab & Offices
- output
- A New Cdf & Community Funded Mixed Sec Sch
- implementation status
- Complete & In Use
- total cost
- Ksh 2,000,000
- estimate
- Ksh 2,500,000
Kabunge Primary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2007
- action
- Purchase Of Land, Construction Of 2 Classrooms & 8 Toilets
- output
- A New Cdf Fully Funded Primary School
- implementation status
- Purchase Of Land Complete; Others Ongoing
- total cost
- Ksh 2,000,000
- estimate
- Ksh 3,000,000
Nduriri Water Project
- location
-
Nyanduma
(in Lari)
- year first funded
- 2003
- action
- Purchase And Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Nduriri Community
- implementation status
- Installation Of Phase 1 Pipes Complete. Phase 2 Ongoing
- total cost
- Ksh 1,984,536
- estimate
- Ksh 2,000,000
Kirenga Water Project Borehol
- location
-
Kirenga
(in Lari)
- year first funded
- 2004
- action
- Drilling And Equiping Of A Borehole And Construction Of A Tank
- output
- Provision Of Clean Water To Lari Health Ctr & Community
- implementation status
- Borehole Complete & In Use; Tank Ongoing
- total cost
- Ksh 1,950,000
- estimate
- Ksh 2,500,000
Matimbei Water Project
- location
-
Kamburu
(in Lari)
- year first funded
- 2003
- action
- Purchase And Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Matimbei Community
- implementation status
- Purchase Of Pipes Complete; Installation Ongoing
- total cost
- Ksh 1,784,536
- estimate
- Ksh 2,500,000
Gathaiti Primary School
- location
-
Lari
(in Lari)
- year first funded
- 2004
- action
- Constuction Of 4 Classrooms & Purchase Of Desks
- output
- Standard Modern Classrooms And Desks
- implementation status
- Complete & In Use
- total cost
- Ksh 1,710,000
- estimate
- Ksh 1,800,000
Kamae Dispensary
- location
-
Kamae
(in Lari)
- year first funded
- 2007
- action
- Construction And Equiping Of A New Dispensary
- output
- New Standard Modern Cdf Fully Funded Dispensary
- implementation status
- Complete But Not In Use
- total cost
- Ksh 1,700,000
- estimate
- Ksh 2,000,000
Monitoring And Evaluation
- location
-
Lari
(in Lari)
- year first funded
- 2005
- action
- Monitoring
- output
- Monitoring And Evaluation Of Projects
- implementation status
- Ongoing
- total cost
- Ksh 1,679,500
- estimate
- Ksh 0
Utugi Primary School
- location
-
Kinale
(in Lari)
- year first funded
- 2003
- action
- Constuction Of 4 Classrooms & 8 Toilets
- output
- Modern Classrooms And Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 1,647,423
- estimate
- Ksh 2,000,000
Kinale Dispensary
- location
-
Kinale
(in Lari)
- year first funded
- 2003
- action
- Construction Of A Lab And Electricity Connection
- output
- Standard Modern Hospital Lab And Supply Of Electricity To Dispensary
- implementation status
- Complete & In Use
- total cost
- Ksh 1,627,835
- estimate
- Ksh 2,500,000
Nyamweru Borehole Water Project
- location
-
Lari
(in Lari)
- year first funded
- 2008
- action
- Drilling And Equiping Of A Borehole
- output
- Provision Of Clean Water To Nyamweru Community
- implementation status
- Drilling Of Borehole Complete; Equiping Ongoing
- total cost
- Ksh 1,600,000
- estimate
- Ksh 3,000,000
Kinale Water Project
- location
-
Kinale
(in Lari)
- year first funded
- 2004
- action
- Drilling & Equiping Of A Borehole Plus Purchase Of Distribution Pipes
- output
- Provision Of Clean Water To Kinale Community
- implementation status
- Complete But Not In Use
- total cost
- Ksh 1,550,000
- estimate
- Ksh 1,750,000
Kirenga Primary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2004
- action
- Repair Of Roof After Damage By Wind
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 1,528,593
- estimate
- Ksh 1,528,593
Karia Ini Water Project
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Purchase Of Land Plus Drilling And Equiping Of A Borehole
- output
- Provision Of Clean Water To Lari Scheme Community
- implementation status
- Land Purchased; Drilling Of Borehole Complete; Equiping Ongoing
- total cost
- Ksh 1,500,000
- estimate
- Ksh 3,500,000
Nyamuthanga Bridge Project
- location
-
Kamburu
(in Lari)
- year first funded
- 2005
- action
- Re -Construction Of The Bridge
- output
- Improved Bridge
- implementation status
- Complete & In Use
- total cost
- Ksh 1,500,000
- estimate
- Ksh 1,800,000
Gitithia Dispensary Staff House
- location
-
Gitithia
(in Lari)
- year first funded
- 2007
- action
- Construction Of A Staff House
- output
- Residential Facility For The Dispensary Staff
- implementation status
- Complete But Not In Use
- total cost
- Ksh 1,500,000
- estimate
- Ksh 1,500,000
Lare Primary School
- location
-
Gitithia
(in Lari)
- year first funded
- 2004
- action
- Purchase Of Land & Construction Of An Admin Block
- output
- Land For The Sch And Offices/Boardrm For Teachers
- implementation status
- Complete & In Use
- total cost
- Ksh 1,470,000
- estimate
- Ksh 1,470,000
Soko Borehole Water Project
- location
-
Kinale
(in Lari)
- year first funded
- 2008
- action
- Purchase Of Land Plus Drilling And Equiping Of A Borehole
- output
- Provision Of Clean Water To Soko Community (Kinale)
- implementation status
- Drilling Of Borehole Complete; Equiping Ongoing
- total cost
- Ksh 1,400,000
- estimate
- Ksh 3,500,000
Gathwariga Borehole Water Project
- location
-
Kamae
(in Lari)
- year first funded
- 2008
- action
- Drilling And Equiping Of A Borehole
- output
- Provision Of Clean Water To Gathwariga Community (Kamae)
- implementation status
- Drilling Of Borehole Complete; Equiping Ongoing
- total cost
- Ksh 1,400,000
- estimate
- Ksh 3,000,000
Nyanduma Dispensary
- location
-
Nyanduma
(in Lari)
- year first funded
- 2004
- action
- Construction And Equiping Of A Community Dispensary
- output
- New Standard Modern Cdf Fully Funded Dispensary
- implementation status
- Complete But Not In Use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 2,000,000
Chiboni Kabacha Water Project
- location
-
Nyanduma
(in Lari)
- year first funded
- 2005
- action
- Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Chiboni Community
- implementation status
- Installation Of Phase 1 Pipes Complete. Phase 2 Ongoing
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,500,000
Kimende Secondary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2004
- action
- Construction And Equiping Of A Science Lab
- output
- Modern And Equiped Science Lab
- implementation status
- Ongoing; At Rental Level
- total cost
- Ksh 1,300,000
- estimate
- Ksh 2,000,000
St Patrick Secondary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2003
- action
- Construction Of A Science Laboratory
- output
- Standard Modern Laboratory
- implementation status
- Interior Finishing Ongoing
- total cost
- Ksh 1,274,227
- estimate
- Ksh 2,000,000
Gitithia Primary School
- location
-
Gitithia
(in Lari)
- year first funded
- 2003
- action
- Construction Of 3 Classrooms And 8 Toilets
- output
- Standard Modern Classrooms And Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 1,271,845
- estimate
- Ksh 1,500,000
Mugiko Primary School
- location
-
Kamae
(in Lari)
- year first funded
- 2003
- action
- Construction Of 3 Modern Classrooms & Toilets
- output
- Modern Classrooms And Toilets
- implementation status
- 2 Classrooms & Toilets Complete & In Use.
- total cost
- Ksh 1,244,845
- estimate
- Ksh 1,500,000
Kongothiria Borehole Water Project
- location
-
Kirenga
(in Lari)
- year first funded
- 2008
- action
- Drilling And Equiping Of A Borehole
- output
- Provision Of Clean Water To Kongothiria Community
- implementation status
- Drilling Of Borehole Complete; Equiping Ongoing
- total cost
- Ksh 1,200,000
- estimate
- Ksh 3,000,000
King'Atua Borehole Water Project
- location
-
Kijabe
(in Lari)
- year first funded
- 2008
- action
- Drilling And Equiping Of A Borehole
- output
- Provision Of Clean Water To King'Atua Community
- implementation status
- Drilling Of Borehole Complete; Equiping Ongoing
- total cost
- Ksh 1,200,000
- estimate
- Ksh 3,000,000
Ragia Primary School
- location
-
Kamae
(in Lari)
- year first funded
- 2004
- action
- Construction Of An Admin. Block And Toilets
- output
- Standard Modern Offices, Board Room And Toilets
- implementation status
- Toilets Complete & In Use. Interior Finishing For
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,500,000
Escarpment Secondary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Construction Of A One Storey Classrooms Block
- output
- Modern Classrooms
- implementation status
- Ongoing: At Slab
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,500,000
Mirangi Primary School
- location
-
Kinale
(in Lari)
- year first funded
- 2003
- action
- Construction Of 6 Classrooms & Purchase Of Desks
- output
- Standard Modern Classrooms And Desks
- implementation status
- Complete & In Use
- total cost
- Ksh 1,147,423
- estimate
- Ksh 1,500,000
Kimathi Road Project
- location
-
Lari
(in Lari)
- year first funded
- 2004
- action
- Grading And Putting Murram On The 3 Kms Road
- output
- Improved Road Network
- implementation status
- Complete & In Use
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,500,000
St Joseph The Worker Kereita High School
- location
-
Kirenga
(in Lari)
- year first funded
- 2004
- action
- Construction Of An Admin Block
- output
- Offices For Principal, Teachers And Other Staff
- implementation status
- Complete & In Use
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,500,000
Magina Secondary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2006
- action
- Construction Of 2 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Ongoing; Interior Finishing Remaining
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,500,000
Kagwe Community Water Project
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2008
- action
- Drilling And Equiping Of A Borehole
- output
- Provision Of Clean Water To Kagwe Girls & Surrounding Community
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 1,100,000
- estimate
- Ksh 3,000,000
Kamae Chief's & Ap Post
- location
-
Kamae
(in Lari)
- year first funded
- 2007
- action
- Construction Of Chief'S Office And Aps Post
- output
- Provision Of Provincial Admin. & Security Services To The Community
- implementation status
- Ongoing; Finishing
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,500,000
Crossroad Primary School
- location
-
Kinale
(in Lari)
- year first funded
- 2003
- action
- Construction Of An Admin Block And Staffroom
- output
- Standard Modern Offices
- implementation status
- Complete & In Use
- total cost
- Ksh 1,097,423
- estimate
- Ksh 1,200,000
Bomboi Water Project
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Purchase And Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Bathi Community
- implementation status
- Installation Of Phase 1 Pipes Complete. Phase 2 Ongoing
- total cost
- Ksh 1,080,000
- estimate
- Ksh 1,500,000
Gathima Primary School
- location
-
Kamburu
(in Lari)
- year first funded
- 2006
- action
- Purchase Of Lockers And Desks, Renovation Of 12 Classrms,
- output
- Standard Modern Classrooms, Toilets & Desks; And
- implementation status
- Complete & In Use
- total cost
- Ksh 1,050,000
- estimate
- Ksh 1,250,000
Gituamba Water Project
- location
-
Kirenga
(in Lari)
- year first funded
- 2008
- action
- Purchase Of Land & Construction Of A 40,000 Ltrs Water Tank
- output
- Additional Reservoir For Water From Gituamba & Kongothiria B/Hs
- implementation status
- Land Purchased. Tank Ongoing - At Foundation Level
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,500,000
Kanyekini Primary School
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Constuction Of 4 Classrooms, Admin Block, Toilets
- output
- A New Cdf Fully Funded Primary School
- implementation status
- Complete & In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 4,000,000
Nyamweru Secondary School
- location
-
Lari
(in Lari)
- year first funded
- 2003
- action
- Construction Of A dining Hall
- output
- Spacious Dining Hall
- implementation status
- Interior Finishing Ongoing
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,500,000
Muthaini Primary School
- location
-
Kamae
(in Lari)
- year first funded
- 2003
- action
- Constuction Of 2 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 994,845
- estimate
- Ksh 1,000,000
Sulmac Primary School
- location
-
Kamae
(in Lari)
- year first funded
- 2003
- action
- Constuction Of 2 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 944,845
- estimate
- Ksh 1,000,000
Bathi Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2003
- action
- Renovation Of A 1 Storey Classrooms Block And
- output
- Standard Modern Classrooms And Toilets
- implementation status
- Toilets Complete & In Use. Classrooms Block
- total cost
- Ksh 900,000
- estimate
- Ksh 1,500,000
Nduriri Dispensary
- location
-
Nyanduma
(in Lari)
- year first funded
- 2005
- action
- Construction Of Septic Tank, Renovation Of Staff House & Purchase Of Medical Equipments
- output
- Provision Of Maternity Services To The Community;Proper House For Hospital Staff.
- implementation status
- Complete & In Use
- total cost
- Ksh 900,000
- estimate
- Ksh 1,000,000
Kiruiru Water Project
- location
-
Nyanduma
(in Lari)
- year first funded
- 2006
- action
- Purchase And Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Kiruiru Community
- implementation status
- Phase 1 Ongoing
- total cost
- Ksh 900,000
- estimate
- Ksh 1,000,000
Kamahindu Ap Post
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2006
- action
- Construction Of A New Ap Post
- output
- Provision Of Security Services To The Community
- implementation status
- Ongoing; At Rental Level
- total cost
- Ksh 900,000
- estimate
- Ksh 1,500,000
Water Projects
- location
-
Lari
(in Lari)
- year first funded
- 2005
- action
- 2004 Boreboles Works
- output
- Provision Of Clean Water
- implementation status
- Complete & In Use
- total cost
- Ksh 872,000
- estimate
- Ksh 1,000,000
Kwaregi Primary School
- location
-
Lari
(in Lari)
- year first funded
- 2005
- action
- Renovation Of 8 Classrms & Construction Of Veranda
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 850,000
- estimate
- Ksh 1,000,000
Gitithia Secondary School
- location
-
Gitithia
(in Lari)
- year first funded
- 2005
- action
- Construction Of A Classrooms & Comp Lab
- output
- Standard Modern Classroom & Computer Lab
- implementation status
- Complete & In Use
- total cost
- Ksh 800,000
- estimate
- Ksh 800,000
Githogoiyo Primary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Construction Of 5 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 800,000
- estimate
- Ksh 1,000,000
Cdf Constituency Office
- location
-
Kirenga
(in Lari)
- year first funded
- 2007
- action
- Construction Of The Cdf & Constituency Office
- output
- Offices For Cdf And Constituency
- implementation status
- Ongoing; Finishing
- total cost
- Ksh 800,000
- estimate
- Ksh 2,000,000
Mbau Ini Secondary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2003
- action
- Interior Finishing And Equiping Of A Science Lab.
- output
- Standard Modern Laboratory
- implementation status
- Interior Finishing & Partitioning Complete; Equiping Ongoing
- total cost
- Ksh 800,000
- estimate
- Ksh 1,000,000
Takinya/Gitare/Bathi Water Project
- location
-
Kijabe
(in Lari)
- year first funded
- 2008
- action
- Purchase And Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Takinya & Bathi Communitities
- implementation status
- Installation Of Phase 1 Pipes Complete. Phase 2 Ongoing
- total cost
- Ksh 795,000
- estimate
- Ksh 1,500,000
Sports
- location
-
Lari
(in Lari)
- year first funded
- 2008
- action
- Construction Of Goal Posts, Levelling Play Grounds Etc
- output
- Standard Sports Facilities
- implementation status
- Ongoing
- total cost
- Ksh 779,500
- estimate
- Ksh 0
Gituamba Borehole
- location
-
Kirenga
(in Lari)
- year first funded
- 2005
- action
- Installation Of A New Pump And Motor
- output
- Provision Of Clean Water To Gituamba Community
- implementation status
- Complete & In Use
- total cost
- Ksh 770,000
- estimate
- Ksh 1,000,000
Mirangi Secondary School
- location
-
Kinale
(in Lari)
- year first funded
- 2004
- action
- Construction Of 3 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,000,000
Kariguini Primary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2005
- action
- Interior And Exterior Finishing Of A Storeyed
- output
- Modern Classrooms And Toilets
- implementation status
- Toilets Complete & In Use. Classrooms Interior
- total cost
- Ksh 700,000
- estimate
- Ksh 1,000,000
Gatamaiyu Primary School
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2005
- action
- Construction Of An Admin Block And Electricity Supply
- output
- Standard Modern Offices And Electricity Supply
- implementation status
- Complete & In Use
- total cost
- Ksh 700,000
- estimate
- Ksh 900,000
Muhoro Primary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2004
- action
- Construction Of An Admin Block & Septic Tank/Sewer System
- output
- Standard Modern Offices And Staff Room
- implementation status
- Complete & In Use
- total cost
- Ksh 700,000
- estimate
- Ksh 800,000
Kirasha Primary School
- location
-
Kamae
(in Lari)
- year first funded
- 2003
- action
- Constuction Of 2 Classrooms And Purchase Of Desks
- output
- Standard Modern Classrooms And Desks
- implementation status
- Complete & In Use
- total cost
- Ksh 694,845
- estimate
- Ksh 750,000
Gituamba Secondary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2003
- action
- Constuction Of 1 Classroom And Toilets
- output
- Standard Modern Classroom And Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 692,151
- estimate
- Ksh 1,000,000
St Teresa Primary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2005
- action
- Construction Of A Storeyed Classrooms Block
- output
- Modern Classrooms
- implementation status
- Ongoing; At Slab Level - 1St Flr
- total cost
- Ksh 650,000
- estimate
- Ksh 800,000
Munyaka Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2003
- action
- Constuction Of 3 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 635,629
- estimate
- Ksh 1,000,000
Kamuchege Community Ctr
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2004
- action
- Renovation Of Dispensary Block And Purchase Of Equipments
- output
- Standard Modern Fully Equiped Dispensary
- implementation status
- Complete & In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Utugi Secondary School
- location
-
Kinale
(in Lari)
- year first funded
- 2004
- action
- Construction Of A Lab & Water Tank
- output
- Standard Science Lab And Supply Of Clean Water
- implementation status
- Complete & In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 1,000,000
Kagaa Secondary School
- location
-
Kamburu
(in Lari)
- year first funded
- 2004
- action
- Wiring And Power Connection
- output
- Power Supply To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Karugo Primary School
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2004
- action
- Construction Of A Water Tank
- output
- Provision Of Clean Water To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Mugumoini Dispensary
- location
-
Nyanduma
(in Lari)
- year first funded
- 2005
- action
- Renovation Of Dispensary Block And Purchase Of Equipments
- output
- Standard Modern Fully Equiped Dispensary
- implementation status
- Complete & In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 750,000
Githioro Water Tank
- location
-
Gitithia
(in Lari)
- year first funded
- 2007
- action
- Construction Of A 70,000 Ltrs Water Tank
- output
- Reservoir For Water From Githioro Borehole
- implementation status
- Ongoing; Design Work Complete.
- total cost
- Ksh 600,000
- estimate
- Ksh 1,000,000
Nyanduma Water Project
- location
-
Nyanduma
(in Lari)
- year first funded
- 2008
- action
- Purchase And Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Nyanduma Community
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 600,000
- estimate
- Ksh 1,000,000
Githogoiyo Ap Post
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Construction Of A New Ap Post
- output
- Provision Of Security Services To The Community
- implementation status
- Ongoing; Finishing
- total cost
- Ksh 600,000
- estimate
- Ksh 800,000
Cdf Office Furniture
- location
-
Kirenga
(in Lari)
- year first funded
- 2004
- action
- Purchase
- output
- Cdf Office Administration
- implementation status
- Purchase Of First Set Complete; Phase 2 Ongoing
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Strategic Planning Project
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Planning
- output
- 5 Year Strategic Plan
- implementation status
- Ongoing
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Kaguongo Primary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2006
- action
- Construction Of A Tank
- output
- Provision Of Clean Water To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 550,000
- estimate
- Ksh 600,000
Kibagare Primary School
- location
-
Gitithia
(in Lari)
- year first funded
- 2003
- action
- Construction Of 2 Classrooms And Electricity Supply
- output
- Standard Modern Classrooms And Electricity Supply
- implementation status
- Complete & In Use
- total cost
- Ksh 533,691
- estimate
- Ksh 800,000
Upper Sheme Farmers
- location
-
Lari
(in Lari)
- year first funded
- 2003
- action
- Installation Of Electricity Mains
- output
- Connection For Over 200 Homes
- implementation status
- Ongoing
- total cost
- Ksh 511,237
- estimate
- Ksh 500,000
Publicity
- location
-
Lari
(in Lari)
- year first funded
- 2008
- action
- Publicizing Cdf Activities Through Mass Media, Sign Boards, Notice Boards Etc
- output
- Public Awareness
- implementation status
- Ongoing
- total cost
- Ksh 500,000
- estimate
- Ksh 0
Gitithia Electricity Project
- location
-
Gitithia
(in Lari)
- year first funded
- 2007
- action
- Installation Of Electricity Mains
- output
- Connection For Various Institutions
- implementation status
- Ongoing
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Chiboni Social Hall
- location
-
Nyanduma
(in Lari)
- year first funded
- 2007
- action
- n/a
- output
- -
- implementation status
- Re - Allocated
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Karatina Technical Secondary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2008
- action
- Construction Of A Classroom
- output
- Standard Modern Classroom
- implementation status
- Ongoing; At Rental Level
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Magina Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2005
- action
- Fencing And Renovation Of 4 Classrooms
- output
- Enhanced Security For The Sch And Standard Classrms
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Mbau Ini Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2007
- action
- Flooring, Plastering And General Renovation Of 3 Classrms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Escarpment Dispensary
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Construction Of A Staffhouse, Gate And Fencing
- output
- Staff Housing And Security For The Dispensary
- implementation status
- Fence & Gate Complete & In Use; S/Hse Ongoing
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Magina Dispensary
- location
-
Kijabe
(in Lari)
- year first funded
- 2008
- action
- Construction And Equiping Of A New Dispensary
- output
- New Standard Modern Cdf Fully Funded Dispensary
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 500,000
- estimate
- Ksh 2,500,000
Karatina Dispensary
- location
-
Nyanduma
(in Lari)
- year first funded
- 2008
- action
- Construction Of A New Community Dispensary
- output
- New Standard Modern Cdf Fully Funded Dispensary
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Kamburu Health Centre
- location
-
Kamburu
(in Lari)
- year first funded
- 2008
- action
- Construction Of A New Community Health Centre
- output
- New Standard Modern Health Centre
- implementation status
- Ongoing; At Floor Level
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
Githembe Water Tank
- location
-
Kirenga
(in Lari)
- year first funded
- 2008
- action
- Purchase Of Land & Construction Of A 40,000 Ltrs Water Tank
- output
- Additional Reservoir For Water From Githogoiyo Borehole
- implementation status
- Land Purchased. Tank Ongoing; Design Work Complete.
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Matathia/Korio/Mbau Ini Water Tank
- location
-
Kijabe
(in Lari)
- year first funded
- 2008
- action
- Completion Of A 100,000 Ltrs Water Tank Halfway Done
- output
- Water Reservoir
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 500,000
- estimate
- Ksh 750,000
Nyambari Borehole Water Project
- location
-
Gitithia
(in Lari)
- year first funded
- 2008
- action
- Power Re-Connection And Purchase Of New Pump & Motor
- output
- Provision Of Clean Water To Nyambari & Gitithia Communitities
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Githoito Muiri Water Project
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2008
- action
- Purchase And Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Githoito And Muiri Communities
- implementation status
- Installation Of Phase 1 Pipes Ongoing
- total cost
- Ksh 500,000
- estimate
- Ksh 2,000,000
Karangi Water Project
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2008
- action
- Purchase And Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Karangi Community
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Gatamaiyu Home For Mhc
- location
-
Nyanduma
(in Lari)
- year first funded
- 2003
- action
- Construction Of A Kitchen And Repair Of Sewage System
- output
- Standard Kitchen And Operational Drainage System
- implementation status
- Complete & In Use
- total cost
- Ksh 494,845
- estimate
- Ksh 1,000,000
Kamburu Primary School
- location
-
Kamburu
(in Lari)
- year first funded
- 2006
- action
- Construction Of Toilets
- output
- Standard Modern Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 450,000
- estimate
- Ksh 500,000
Kamuchege Non Formal L
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2004
- action
- Constuction Of 2 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 450,000
- estimate
- Ksh 600,000
Kamburu Primary School health Care
- location
-
Kamburu
(in Lari)
- year first funded
- 2004
- action
- Rehabilitation Of The Dispensary
- output
- Standard Modern Fully Equiped Dispensary
- implementation status
- Complete & In Use
- total cost
- Ksh 405,000
- estimate
- Ksh 500,000
Constituency Office Kamburu
- location
-
Kamburu
(in Lari)
- year first funded
- 2006
- action
- Construction Of A Perimeter Wall
- output
- Constituency Admin. Services
- implementation status
- Complete But Not In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 779,885
King'Atua Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2004
- action
- Constuction Of An Ecd Classrm & Renovation Of 8 Others
- output
- Standard Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 600,000
Nyanduma Primary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2005
- action
- Purchase Of A Tanks And Construction Of Water Points
- output
- Provision Of Clean Water To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 250,000
Uplands Forest Dispensary
- location
-
Lari
(in Lari)
- year first funded
- 2008
- action
- Relocation Of A Community Health Centre
- output
- New Standard Modern Dispensary
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 400,000
- estimate
- Ksh 3,000,000
Kamae Primary School
- location
-
Kamae
(in Lari)
- year first funded
- 2003
- action
- Renovation Of 8 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 500,000
Kinale Primary School
- location
-
Kinale
(in Lari)
- year first funded
- 2004
- action
- Construction Of Toilets
- output
- Standard Modern Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Lari Funds BillboaRoads Project
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Fabrication And Erection
- output
- Publicity
- implementation status
- Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 500,000
Constituency Office
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2006
- action
- Construction Of The Cdf & Constituency Office
- output
- Offices For Cdf And Constituency
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 350,000
- estimate
- Ksh 350,000
Lari Chiefs Office
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Renovation Of Chief'S Office Block And Construction Of A Toilet
- output
- Provision Of Provincial Admin. & Security Services To The Community
- implementation status
- Complete & In Use
- total cost
- Ksh 350,000
- estimate
- Ksh 400,000
Kagwe Primary School
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2005
- action
- Purchase of Desks
- output
- Enhanced Learning
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Gachoire Girls Secondary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2008
- action
- Purchase Of Dining Hall Tables
- output
- Standard Dining Hall Tables
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Mugiko Secondary School
- location
-
Kamae
(in Lari)
- year first funded
- 2005
- action
- Construction Of One Classroom
- output
- Standard Modern Classroom
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 500,000
Kimende Police Post
- location
-
Kijabe
(in Lari)
- year first funded
- 2008
- action
- Construction Of A New Police Post
- output
- Provision Of Security Services To The Community
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 300,000
- estimate
- Ksh 1,000,000
Gatamaiyu Home For Mhc
- location
-
Nyanduma
(in Lari)
- year first funded
- 2005
- action
- Construction Of A Kitchen
- output
- Standard Modern Kitchen
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kibagare Primary School
- location
-
Gitithia
(in Lari)
- year first funded
- 2004
- action
- Flooring Of 2 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kirenga Community Centre
- location
-
Kirenga
(in Lari)
- year first funded
- 2007
- action
- Purchase Of Chairs And Public Address System
- output
- Provision Of Social Services To Kirenga Community
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Environmental Activities
- location
-
Lari
(in Lari)
- year first funded
- 2008
- action
- Planting Trees, Construction Of Garbage Disposal Bins Etc
- output
- Environmental Conservation
- implementation status
- Ongoing
- total cost
- Ksh 300,000
- estimate
- Ksh 0
Kongothiria Road Kms Approx
- location
-
Kirenga
(in Lari)
- year first funded
- 2007
- action
- Murram,Hardcore And Digging Of Drainage Trenches
- output
- Improved Road Network
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Githirioni Community Health Centre
- location
-
Lari
(in Lari)
- year first funded
- 2008
- action
- Construction Of An Extension & Purchase Of Med. Equipments
- output
- New Standard Modern Dispensary
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 800,000
Escarpment Primary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Renovation Of 8 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 500,000
Juvenalis Gitau Primary School
- location
-
Lari
(in Lari)
- year first funded
- 2005
- action
- Construction Of 10 Toilets And Gate
- output
- Standard Toilets; Fence And Gate For Security
- implementation status
- Complete & In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 500,000
Kereita Primary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2005
- action
- Construction Of Toilets And Gate
- output
- Standard Modern Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 279,658
- estimate
- Ksh 300,000
Cdf Office / Nyeri Trade Fair
- location
-
Kirenga
(in Lari)
- year first funded
- 2004
- action
- Exhibition
- output
- Publicity
- implementation status
- Complete; 2 Exhibitions At Nyeri Ask Show
- total cost
- Ksh 270,000
- estimate
- Ksh 270,000
Bursary Schooleme
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Award Of Bursary To Bright Students From Poor Backgrounds
- output
- Access To Proper Schooling
- implementation status
- Complete; Bursary Awarded To Needy Students
- total cost
- Ksh 257,300
- estimate
- Ksh 0
Kirenga Boys Secondary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Provision Of Lab Gas And Water
- output
- Operational Science Lab & Clean Water Supply
- implementation status
- Complete & In Use
- total cost
- Ksh 250,000
- estimate
- Ksh 500,000
Mukeu Primary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Construction Of Latrines And Painting Of Classrooms Roof
- output
- Standard Modern Classrooms And Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 250,000
- estimate
- Ksh 400,000
Kirenga Chiefs Office
- location
-
Kirenga
(in Lari)
- year first funded
- 2007
- action
- Renovation Of Chief'S Office Block, Staff House & Installation Of Unihuts
- output
- Provision Of Provincial Admin. Services To The Community
- implementation status
- Complete & In Use
- total cost
- Ksh 250,000
- estimate
- Ksh 400,000
Uplands Non Formal Secondary School
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Purchase Of Lab Equipments And Lockers
- output
- Modern Lockers And Lab Equipments
- implementation status
- Complete & In Use
- total cost
- Ksh 250,000
- estimate
- Ksh 400,000
Gatamaiyu Ap Post
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2008
- action
- Renovation Of The A.Ps Post
- output
- Provision Of Security Services To The Community
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Kimoronditi Electricity Project
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Installation Of Electricity Mains
- output
- Connection For Over 200 Homes
- implementation status
- Ongoing
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Lari Community Centre
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Purchase Of Chairs And Public Address System
- output
- Provision Of Social Services To Lari Community
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Githirioni Community Centre
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Purchase Of Chairs And Public Address System
- output
- Provision Of Social Services To Githirioni Community
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kijabe Community Centre
- location
-
Kijabe
(in Lari)
- year first funded
- 2007
- action
- Purchase Of 2 Ccv 10,000 Ltrs Tanks
- output
- Provision Of Clean Water To Kijabe Community
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kago Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2003
- action
- Renovation Of 4 Classrooms
- output
- Standard Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nduriri Secondary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2004
- action
- Wiring And Electricity Supply To The School
- output
- Supply Of Electricity To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kamahindu Primary School
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2004
- action
- Repainting Of Classrooms Roof And Veranda
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Githirioni Community Health Centre
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Renovation Of Dispensary Block
- output
- Standard Modern Dispensary
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Kereita Health Centre
- location
-
Kirenga
(in Lari)
- year first funded
- 2007
- action
- Purchase Of A Water Tank & Renovation
- output
- Standard Modern Health Centre With Clean Water Supply
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Lari Schooleme Swamp Project
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Sinking Of A Drainage Trench
- output
- Drainage Of Water From Lari Scheme Swamp To Prevent Malaria
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Wangware Primary School
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2004
- action
- Renovation Of 8 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Kiambogo Secondary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2004
- action
- Constuction Of A Classroom
- output
- Standard Modern Classroom
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 400,000
Iriani Foot Bridge
- location
-
Kamburu
(in Lari)
- year first funded
- 2006
- action
- Rehabilitation Of The Bridge
- output
- Improved Bridge
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Nyanduma Chief's & Ap Post
- location
-
Nyanduma
(in Lari)
- year first funded
- 2008
- action
- Completion Of Chief'S Office/Ap Post Done Up To Windows Level
- output
- Provision Of Provincial Admin. & Security Services To The Community
- implementation status
- Ongoing; At Rental Level
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Kibuto Electricity Project
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Installation Of Electricity Mains
- output
- Connection For Over 200 Homes
- implementation status
- Ongoing
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Kariru Foot Bridge
- location
-
Nyanduma
(in Lari)
- year first funded
- 2004
- action
- Rehabilitation Of The Bridge
- output
- Improved Bridge
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Kagwe Dispensary
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2004
- action
- Construction Of An Extension & Purchase Of Med. Equipments
- output
- Standard Modern Fully Equiped Dispensary
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Kimende Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2006
- action
- Wiring And Electricity Supply To The School
- output
- Electricity Supply To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Iriani Nursery School
- location
-
Kamburu
(in Lari)
- year first funded
- 2006
- action
- Renovation Of 2 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Matimbei Primary School
- location
-
Kamburu
(in Lari)
- year first funded
- 2006
- action
- Renovation Of 4 Classrms And Construction Of A Veranda
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Gachoire Primary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2006
- action
- Construction Of A Gate And Fence
- output
- Security For The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Kijabe Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2004
- action
- Purchase Of Desks
- output
- Modern School Desks
- implementation status
- Complete & In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Munyaka Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2007
- action
- Construction Of An Ecd Classroom
- output
- Standard Modern Ecd Classroom
- implementation status
- Ongoing; At Rental Level
- total cost
- Ksh 150,000
- estimate
- Ksh 300,000
Kinale Primary School
- location
-
Kinale
(in Lari)
- year first funded
- 2003
- action
- Renovation Of 4 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 147,423
- estimate
- Ksh 250,000
Kanyuiro Foot Bridge
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2006
- action
- Re -Construction Of The Bridge
- output
- Improved Bridge
- implementation status
- Complete & In Use
- total cost
- Ksh 110,000
- estimate
- Ksh 200,000
Kimende Kaka Enviromental Project
- location
-
Kijabe
(in Lari)
- year first funded
- 2005
- action
- Purchase Of Wheelbarrows & Other Equipments To Clean The Environment
- output
- Environmental Conservation
- implementation status
- Complete & In Use
- total cost
- Ksh 104,888
- estimate
- Ksh 150,000
Kago Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2003
- action
- Wiring & Electricity Connection
- output
- Electricity Supply To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 101,485
- estimate
- Ksh 150,000
Kamahia Primary School
- location
-
Kamburu
(in Lari)
- year first funded
- 2007
- action
- Overhaul Of Roof, Plastering And Floor Repairs For 1 Classroom
- output
- Standard Modern Classroom
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 300,000
Kamburu Secondary School
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2006
- action
- Construction Of 4 Toilets
- output
- Standard Modern Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Bathi Secondary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2005
- action
- Renovation Of 2 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 300,000
Muthandi Primary School
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2005
- action
- Water System
- output
- Provision Of Clean Water To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Gakenge Primary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2006
- action
- Levelling Of The Playing Field
- output
- Proper Field For Soccer And Other Sports
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Karatina Primary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2006
- action
- Construction Of Toilets
- output
- Standard Modern Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 150,000
Nyamuthanga Primary School
- location
-
Kamburu
(in Lari)
- year first funded
- 2006
- action
- Renovation Of 8 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kibathithi Primary School
- location
-
Kamburu
(in Lari)
- year first funded
- 2006
- action
- Renovation Of 4 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Kamuchege Primary School
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2006
- action
- Construction Of One Classroom
- output
- Standard Modern Classroom
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 150,000
Gituamba Primary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Renovation Of 3 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 150,000
Karugo Foot Bridge
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2006
- action
- Rehabilitation Of The Bridge
- output
- Improved Bridge
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Tree Nurseries Lare
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Preparation Of Tree Nurseries And Planting Of Trees
- output
- Environmental Conservation
- implementation status
- Tree Nurseries Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Githirioni Ap Post
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Renovation Of The A.Ps Post Office Block
- output
- Provision Of Security Services To The Community
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 250,000
Magina Ap Post
- location
-
Kijabe
(in Lari)
- year first funded
- 2008
- action
- Renovation Of The A.Ps Post
- output
- Provision Of Security Services To The Community
- implementation status
- Ongoing; At Planning Stage
- total cost
- Ksh 100,000
- estimate
- Ksh 300,000
Gituamba Ap Post
- location
-
Kirenga
(in Lari)
- year first funded
- 2008
- action
- Construction Of A New Ap Post
- output
- Provision Of Security Services To The Community
- implementation status
- Fencing Complete; Construction Ongoing
- total cost
- Ksh 100,000
- estimate
- Ksh 500,000
Gituamba Electricity Project
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Power Supply To Gituamba Pri & Sec Schools
- output
- Connection For Both Schools
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kinale Roads Works
- location
-
Kinale
(in Lari)
- year first funded
- 2006
- action
- Installation Of Culverts
- output
- Improved Road Network
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 150,000
Nduriri Water Project
- location
-
Nyanduma
(in Lari)
- year first funded
- 2006
- action
- Installation Of Pipes And Pipes Fittings
- output
- Distribution Of Clean Water To Nduriri Community
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Nduriri Dispensary
- location
-
Nyanduma
(in Lari)
- year first funded
- 2006
- action
- Construction Of An Incenerator
- output
- Hospital Wastes Management
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 150,000
Kamuchege Community Centre
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2006
- action
- Renovation Of The Dispensary Block
- output
- Standard Modern Fully Equiped Dispensary
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Nyamweru Primary School
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Construction Of Toilets
- output
- Standard Modern Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Kambaa Primary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Renovation Of School'S Borehole
- output
- Provision Of Water To The School
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Gathuru Bridge
- location
-
Nyanduma
(in Lari)
- year first funded
- 2006
- action
- Renovation Of The Bridge
- output
- Improved Road Network
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Lari Division Education Office
- location
-
Kirenga
(in Lari)
- year first funded
- 2006
- action
- Wiring And Electrificity Connection
- output
- Supply Of Electricity To The Entire Office And Hall
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Gatamaiyu Diveducoffice
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2006
- action
- Repainting Of The Office And Repair Of Floor And Ceiling
- output
- Standard Offices
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Constituency Website Project
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Development Of A Website
- output
- Publicity
- implementation status
- Design Complete; Uploading Content & Registration Remaining
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Uplands Forest Dispensary
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Construction Of New Dispensary Block
- output
- Standard Modern Dispensary
- implementation status
- Planning Ongoing
- total cost
- Ksh 100,000
- estimate
- Ksh 500,000
Kariguini Primary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2007
- action
- Digging & Construction Of Toilets
- output
- Standard Modern Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Gatamaiyu D.O. Office
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2007
- action
- Repainting Of The Office And Repair Of Floor And Ceiling
- output
- Standard Offices
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Kimende Health Centre
- location
-
Kijabe
(in Lari)
- year first funded
- 2007
- action
- Purchase Of Medical Equipments
- output
- Modern Medical Equipments For The Dispensary
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kanyekini Primary School
- location
-
Gitithia
(in Lari)
- year first funded
- 2007
- action
- Purchase Of Desks
- output
- Stadard Modern Class For Junior Pupils
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Gatamaiyu Home For The Mhc
- location
-
Nyanduma
(in Lari)
- year first funded
- 2007
- action
- Construction Of Dining Hall Floor
- output
- Standard Modern Dining Hall
- implementation status
- Kitchen Complete. Hall Ongoing
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Mbau Ini Dispensary
- location
-
Kirenga
(in Lari)
- year first funded
- 2007
- action
- Painting Of The Dispensary, Repair Of Floor & Purchase Of Furniture
- output
- Standard Modern Dispensary
- implementation status
- Complete But Not In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 500,000
King'Atua Secondary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2007
- action
- Plastering, Flooring And General Repairs For 2 Classrooms
- output
- Standard Modern Classrooms
- implementation status
- Complete And In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Nyanduma Polytechnic
- location
-
Nyanduma
(in Lari)
- year first funded
- 2007
- action
- Wiring And Electrificity Connection
- output
- Supply Of Electricity To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 300,000
Kirenga Primary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2007
- action
- Fencing And Renovation Of Toilets
- output
- Enhanced Security And Standard Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 300,000
Sulmac Secondary School
- location
-
Kamae
(in Lari)
- year first funded
- 2007
- action
- Purchase Of Desks
- output
- Standard Modern Desks
- implementation status
- Complete And In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Constituency Food Program
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Purchase Of Maize Flour And Other Foodstuffs
- output
- Aleviation Of Hunger And Starvation
- implementation status
- Complete; Maize Flour Distributed
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Constituency Education Day
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Prize Giving
- output
- Improved Academic Performance
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Lari Division Education Office
- location
-
Kijabe
(in Lari)
- year first funded
- 2007
- action
- Repainting, Roof, Doors And Window Repairs
- output
- Standard Offices
- implementation status
- Complete And In Use
- total cost
- Ksh 82,619
- estimate
- Ksh 82,619
Gituamba Secondary School
- location
-
Kirenga
(in Lari)
- year first funded
- 2005
- action
- Wiring And Electricity Supply To The School
- output
- Supply Of Electricity To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 80,000
- estimate
- Ksh 80,000
Kamburu Chiefs Office
- location
-
Kamburu
(in Lari)
- year first funded
- 2006
- action
- Construction Of A Gate And Fence
- output
- Security For The Chief'S Office & A.P Post
- implementation status
- Complete & In Use
- total cost
- Ksh 80,000
- estimate
- Ksh 80,000
Bathi Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2006
- action
- Construction Of A Classroom
- output
- Standard Modern Classroom
- implementation status
- Complete & In Use
- total cost
- Ksh 61,000
- estimate
- Ksh 500,000
Kirenga Community Nursery
- location
-
Kirenga
(in Lari)
- year first funded
- 2005
- action
- General Repairs For 2 Classrooms - Plastering, Flooring, Roof Repairs Etc
- output
- Standard Modern Classrooms
- implementation status
- Phase 1 Complete & In Use
- total cost
- Ksh 60,000
- estimate
- Ksh 60,000
King'Atua Primary School
- location
-
Kijabe
(in Lari)
- year first funded
- 2003
- action
- Construction Of Toilets
- output
- Standard Modern Toilets
- implementation status
- Complete & In Use
- total cost
- Ksh 51,000
- estimate
- Ksh 51,000
Kamahindu Primary School
- location
-
Gatamaiyu
(in Lari)
- year first funded
- 2007
- action
- Wiring And Electrificity Connection
- output
- Supply Of Electricity To The Entire School
- implementation status
- Complete & In Use
- total cost
- Ksh 50,000
- estimate
- Ksh 300,000
Nyamweru Primary School
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Construction Of Toilets
- output
- Standard Modern Toilets
- implementation status
- Complete And In Use
- total cost
- Ksh 50,000
- estimate
- Ksh 200,000
Kambaa Cattle Dip
- location
-
Kirenga
(in Lari)
- year first funded
- 2007
- action
- Renovation Of The Dip
- output
- Standard Cattle Dip
- implementation status
- Ongoing
- total cost
- Ksh 50,000
- estimate
- Ksh 100,000
Gakenge Primary School
- location
-
Nyanduma
(in Lari)
- year first funded
- 2007
- action
- Construction Of A Gate
- output
- Enhanced Security For The School
- implementation status
- Complete & In Use
- total cost
- Ksh 50,000
- estimate
- Ksh 80,000
District Education Day
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Prize Giving
- output
- Improved Academic Performance
- implementation status
- Complete; Prize Giving Held At District Hqs
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Kbu West Nyeri Trade Fair
- location
-
Lari
(in Lari)
- year first funded
- 2007
- action
- Exhibition
- output
- Publicity
- implementation status
- Complete; Exhibition Held At Nyeri Ask Show
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Githirioni Primary School
- location
-
Lari
(in Lari)
- year first funded
- 2006
- action
- Construction Of A Gate
- output
- Improved Security For The School
- implementation status
- Complete & In Use
- total cost
- Ksh 50,000
- estimate
- Ksh 100,000
Bursary Schooleme
- location
-
Lari
(in Lari)
- year first funded
- 2003
- action
- Award Of Bursary To Bright Students From Poor Backgrounds
- output
- Access To Proper Schooling
- implementation status
- Complete; Bursary Awarded To Needy Students
- total cost
- Ksh 49,000
- estimate
- Ksh 0
Bursary Schooleme
- location
-
Lari
(in Lari)
- year first funded
- 2004
- action
- Award Of Bursary To Bright Students From Poor Backgrounds
- output
- Access To Proper Schooling
- implementation status
- Complete; Bursary Awarded To Needy Students
- total cost
- Ksh 33,333
- estimate
- Ksh 0