The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.

It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

Projects in Matungu

Bursary

location
Matungu (in Matungu)
year first funded
2004
action
Assist needy students
output
College &School Edu.
implementation status
ongoing
total cost
Ksh 23,136,756
estimate
Ksh 0

Matungu-Kholera -Bungoma Db Road,Ejinja-Watoya Road

location
Koyonzo and Matungu (in Matungu)
year first funded
2005
action
Construction Of Road
output
Road
implementation status
Ongoing
total cost
Ksh 10,682,885
estimate
Ksh 0

Administration

location
Matungu (in Matungu)
year first funded
2003
action
Management &Supervision
output
Project Completion
implementation status
Ongoing
total cost
Ksh 7,538,147
estimate
Ksh 0

Nanyeni-Drift-Lung'Anyiro-Nanyeni Road

location
Koyonzo and Matungu (in Matungu)
year first funded
2005
action
Construction Of Road
output
Road
implementation status
Completed
total cost
Ksh 6,795,772
estimate
Ksh 0

Matungu Distict Hospital

location
Matungu (in Matungu)
year first funded
2003
action
Construction Of Hospital
output
Hospital
implementation status
Ongoing
total cost
Ksh 6,250,000
estimate
Ksh 0

Provision Of Laboratory Equipment

location
Matungu (in Matungu)
year first funded
2005
action
Providing Lab. Equipment To Different Schools
output
Laboratory Equipment
implementation status
Ongoing
total cost
Ksh 6,209,941
estimate
Ksh 0

School Bus- Kholera Sec

location
Koyonzo (in Matungu)
year first funded
2009
action
Purchase Of School Bus
output
Bus
implementation status
Complete And In Use
total cost
Ksh 5,000,000
estimate
Ksh 0

Lubanga Secondary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Construction Of 1 Classroom & Twin Lab,
output
Classroom & Twin Lab.
implementation status
Ongoing
total cost
Ksh 4,530,000
estimate
Ksh 0

School Bus- Koyonzo Sec

location
Koyonzo (in Matungu)
year first funded
2007
action
Purchase Of School Bus
output
Bus
implementation status
Complete And In Use
total cost
Ksh 4,509,000
estimate
Ksh 0

Rural Access Road

location
Koyonzo and Matungu (in Matungu)
year first funded
2006
action
Construction Ofrural Access Road
output
Roads
implementation status
Ongoing
total cost
Ksh 4,409,142
estimate
Ksh 0

Munami Secondary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Construction Of Multi Purpose Hall
output
Hall
implementation status
Ongoing
total cost
Ksh 4,300,000
estimate
Ksh 0

Lung'Anyiro Dispensary

location
Koyonzo (in Matungu)
year first funded
2003
action
Construction Of Dispensary - Wards
output
Dispensary
implementation status
Ongoing
total cost
Ksh 3,750,000
estimate
Ksh 0

St. Teresa Itete Secondary School

location
Koyonzo (in Matungu)
year first funded
2004
action
C0Nstruction Of 3 Classrooms & Lab,Purchase Of Land
output
Classrooms,Lab &Land
implementation status
Ongoing
total cost
Ksh 3,530,000
estimate
Ksh 0

M&E

location
Matungu (in Matungu)
year first funded
2006
action
Project Supervision
output
Projects
implementation status
Ongoing
total cost
Ksh 3,425,984
estimate
Ksh 0

St Maurice Mwira Secondary School

location
Matungu (in Matungu)
year first funded
2004
action
Construction Of D/H & Kitchen
output
D/H & Kitchen
implementation status
Ongoing
total cost
Ksh 3,300,000
estimate
Ksh 0

Indangalasa Secondary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Lab Construction
output
Laboratory
implementation status
Ongoing
total cost
Ksh 3,180,000
estimate
Ksh 0

Namamba Secondary School

location
Matungu (in Matungu)
year first funded
2004
action
Construction Of D/H
output
D/H
implementation status
Ongoing
total cost
Ksh 3,130,000
estimate
Ksh 0

St. Charles Khalaba Secondary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Lab Construction
output
Laboratory
implementation status
Ongoing
total cost
Ksh 2,880,000
estimate
Ksh 0

St. Gabriel Mirere Secondary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Constructon Of Tw.In Lab
output
Twin Lab.
implementation status
Ongoing
total cost
Ksh 2,750,000
estimate
Ksh 0

Makunda MSecondary School

location
Matungu (in Matungu)
year first funded
2004
action
Lab Construction
output
Laboratory
implementation status
Completed
total cost
Ksh 2,630,000
estimate
Ksh 0

Mirere Health Centre

location
Koyonzo (in Matungu)
year first funded
2006
action
Ward Construction
output
Wards
implementation status
Ongoing
total cost
Ksh 2,550,000
estimate
Ksh 0

Lunganyiro Reservoir And Pump Station

location
Koyonzo (in Matungu)
year first funded
2009
action
Yet To Start
output
-
implementation status
not known
total cost
Ksh 2,500,000
estimate
Ksh 0

Mungore Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 2,460,000
estimate
Ksh 0

Mukunyuku Primary School

location
Koyonzo (in Matungu)
year first funded
2003
action
Construction Of 5 Classrooms
output
Classrooms
implementation status
3 Complete 2 Plastering And Painting
total cost
Ksh 2,400,000
estimate
Ksh 0

Emarinda Primary School

location
Matungu (in Matungu)
year first funded
2003
action
Construction Of 6 Classrooms
output
Classrooms
implementation status
5 Complete 1 Ongoing
total cost
Ksh 2,350,000
estimate
Ksh 0

Lutasio Primary School

location
Matungu (in Matungu)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 2,300,000
estimate
Ksh 0

Shibanze Komoro Dispensary

location
Matungu (in Matungu)
year first funded
2004
action
Construction Of Dispensary
output
Dispensary
implementation status
Ongoing
total cost
Ksh 2,250,000
estimate
Ksh 0

Busombi Secondary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Construction Of Admin. Block
output
Admin. Block
implementation status
Completed
total cost
Ksh 2,225,000
estimate
Ksh 0

Provision Of Desks

location
Matungu (in Matungu)
year first funded
2003
action
Providing Desks To Different Schools
output
Desks
implementation status
Complete
total cost
Ksh 2,200,000
estimate
Ksh 0

St. James Bulimbo Gecondary School

location
Matungu (in Matungu)
year first funded
2004
action
Construction Of Kitchen
output
Kitchen
implementation status
Completed
total cost
Ksh 2,180,000
estimate
Ksh 0

Kholera Secondary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Construction Of Dorm &Purchase Of Lab Equi.
output
Dorm. & Lab Equi.
implementation status
Ongoing
total cost
Ksh 2,100,000
estimate
Ksh 0

Khalaba Health Centre

location
Matungu (in Matungu)
year first funded
2003
action
Construction Of Healthy Centre
output
Health Centre
implementation status
Funds Not yet released
total cost
Ksh 2,000,000
estimate
Ksh 0

Ejinja-Watoya Road

location
Koyonzo (in Matungu)
year first funded
2006
action
Construction Of Road
output
Road
implementation status
Completed
total cost
Ksh 2,000,000
estimate
Ksh 0

Koyonzo Secondary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Construction Of Multi Purpose Hall
output
Hall
implementation status
Ongoing
total cost
Ksh 1,950,000
estimate
Ksh 0

Koyonzo-Namalasire

location
Koyonzo (in Matungu)
year first funded
2007
action
n/a
output
-
implementation status
-
total cost
Ksh 1,920,000
estimate
Ksh 0

Sayangwe Primary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Completed
total cost
Ksh 1,900,000
estimate
Ksh 0

Ejinja Mixed Secondary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Construction Of 1 Classroom & Twin Lab,
output
Classroom & Lab.
implementation status
0Ngoing
total cost
Ksh 1,880,000
estimate
Ksh 0

Nanyeni-Shikhondi

location
Koyonzo (in Matungu)
year first funded
2007
action
n/a
output
-
implementation status
-
total cost
Ksh 1,880,000
estimate
Ksh 0

Springs Protection, Sinking And Rehablitation Of Boreholes

location
Matungu (in Matungu)
year first funded
2003
action
Spring Protection
output
Water
implementation status
Completed
total cost
Ksh 1,859,000
estimate
Ksh 0

Mukunyuku-Mirere-Sio River

location
Koyonzo (in Matungu)
year first funded
2007
action
n/a
output
-
implementation status
not known
total cost
Ksh 1,850,000
estimate
Ksh 0

Khabukoshe Secondary School

location
Matungu (in Matungu)
year first funded
2008
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 1,800,000
estimate
Ksh 0

Lubanba-Lunganyiro Road

location
Koyonzo (in Matungu)
year first funded
2007
action
n/a
output
-
implementation status
not known
total cost
Ksh 1,750,000
estimate
Ksh 0

Lunganyiro Polytechic

location
Koyonzo (in Matungu)
year first funded
2004
action
Rehabilitatation
output
Polytechic
implementation status
Complete
total cost
Ksh 1,660,000
estimate
Ksh 0

Disasters

location
Matungu (in Matungu)
year first funded
2006
action
For Cash Emergency Situations
output
Disaster Addressed
implementation status
Ongoing
total cost
Ksh 1,637,878
estimate
Ksh 0

Kadima Primary School

location
Koyonzo (in Matungu)
year first funded
2007
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Plastering Painting And Fittings To Be Done
total cost
Ksh 1,600,000
estimate
Ksh 0

Mirere Primary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
2 Completed 2 Ongoing
total cost
Ksh 1,550,000
estimate
Ksh 0

Namalasire Primary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
2 Completed 2 Ongoing
total cost
Ksh 1,550,000
estimate
Ksh 0

Ebusombi Primary School

location
Matungu (in Matungu)
year first funded
2005
action
Construction Of 2 Classrooms+Twin Lab
output
Classrooms And Twin Lab
implementation status
Clasroms Completed And In Use,Twin Lab At Rindal Level
total cost
Ksh 1,550,000
estimate
Ksh 0

Afforestation

location
Matungu (in Matungu)
year first funded
2007
action
n/a
output
-
implementation status
not known
total cost
Ksh 1,500,000
estimate
Ksh 0

Lunganyiro Secondary School

location
Koyonzo (in Matungu)
year first funded
2008
action
Lab Construction
output
Laboratory
implementation status
Ongoing
total cost
Ksh 1,500,000
estimate
Ksh 0

Namulungu MPrimary School

location
Matungu (in Matungu)
year first funded
2004
action
Construction Of 3 Classrooms
output
Classrooms
implementation status
2 Complete 1 Ongoing
total cost
Ksh 1,460,000
estimate
Ksh 0

Mung'Ung'U Dispensary

location
Koyonzo (in Matungu)
year first funded
2003
action
Construction Of Dispensary &Borehole
output
Dispensary & Borehole
implementation status
Ongoing
total cost
Ksh 1,420,000
estimate
Ksh 0

Lung'Anyiro Road

location
Matungu (in Matungu)
year first funded
2005
action
Construction Of Road
output
Road
implementation status
Completed
total cost
Ksh 1,352,000
estimate
Ksh 0

Energy Saving Jikos

location
Matungu (in Matungu)
year first funded
2008
action
Provision Of Jikos To All Schools
output
Jikos
implementation status
Yet Ton Reach All The Scools
total cost
Ksh 1,325,000
estimate
Ksh 0

Namamba Primary School

location
Matungu (in Matungu)
year first funded
2004
action
Construction Of 5 Classrooms
output
Classrooms
implementation status
3 Completed 2 Ongoing
total cost
Ksh 1,310,000
estimate
Ksh 0

Namasanda Primary School

location
Matungu (in Matungu)
year first funded
2003
action
Construction Of 4 Classrooms & Land Purchase
output
Land And Classrooms
implementation status
Land Purchased & 2Classrooms Complete 2 Ongoing
total cost
Ksh 1,275,000
estimate
Ksh 0

Busambe Primary School

location
Matungu (in Matungu)
year first funded
2004
action
Construction Of 5 Classrooms
output
Classroom
implementation status
3 Completed 2 Ongoing
total cost
Ksh 1,260,000
estimate
Ksh 0

Lubanga Health Centre

location
Koyonzo (in Matungu)
year first funded
2009
action
Yet To Start
output
-
implementation status
Funds Not yet released
total cost
Ksh 1,250,000
estimate
Ksh 0

Classiffied Roads

location
Koyonzo and Matungu (in Matungu)
year first funded
2006
action
Construction Of Road
output
Road
implementation status
Completed
total cost
Ksh 1,215,000
estimate
Ksh 0

Munanga Primary School

location
Matungu (in Matungu)
year first funded
2004
action
Construction Of 3 Classrooms
output
Classrooms
implementation status
Completed
total cost
Ksh 1,160,000
estimate
Ksh 0

Strategic Plan/Website

location
Matungu (in Matungu)
year first funded
2008
action
Produce A Strategic Plan And Develop Website
output
Strategic Plan And Website
implementation status
Strategic Plan And No Website
total cost
Ksh 1,100,000
estimate
Ksh 0

Emakokhwe Primary School

location
Matungu (in Matungu)
year first funded
2005
action
Construction Of 3 Classrooms
output
Classrooms
implementation status
2 Complete 1 Ongoing
total cost
Ksh 1,100,000
estimate
Ksh 0

Youth Empowerment Centre

location
Matungu (in Matungu)
year first funded
2008
action
n/a
output
-
implementation status
400,000 Re-Allocated To Cdf Office-700,000 Not Disbursed
total cost
Ksh 1,100,000
estimate
Ksh 0

Lubanga Primary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Construction Of 1 Classroom
output
Classroom
implementation status
Completed
total cost
Ksh 1,100,000
estimate
Ksh 0

Emurabe Primary School

location
Matungu (in Matungu)
year first funded
2004
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Completed And In Use
total cost
Ksh 1,050,000
estimate
Ksh 0

Makunda Primary School

location
Matungu (in Matungu)
year first funded
2008
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 1,000,000
estimate
Ksh 0

Provision Of Water To Sublocationsz

location
Matungu (in Matungu)
year first funded
2008
action
Re-Allocated To Cdf Office
output
-
implementation status
Land on Road Reserve
total cost
Ksh 1,000,000
estimate
Ksh 0

Mukhweya Secondary School

location
Matungu (in Matungu)
year first funded
2008
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 1,000,000
estimate
Ksh 0

Ebutaliko Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Purchase Of Land And Constructions Of 2 New Classrooms
output
Land And Classrooms
implementation status
Completed And In Use Classrooms Yet To Start
total cost
Ksh 1,000,000
estimate
Ksh 0

Namayiakalo Primary School

location
Koyonzo (in Matungu)
year first funded
2003
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 975,000
estimate
Ksh 0

Nyapora Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Construction Of 3 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 910,000
estimate
Ksh 0

Shiyabo Primary School

location
Matungu (in Matungu)
year first funded
2007
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 900,000
estimate
Ksh 0

Namalasire Secondary School

location
Koyonzo (in Matungu)
year first funded
2009
action
New Secondary Yet To Start
output
-
implementation status
not known
total cost
Ksh 800,000
estimate
Ksh 0

Mungakha Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Construction Of 2 Classrooms
output
Classroom
implementation status
Completed
total cost
Ksh 760,000
estimate
Ksh 0

Nyapwaka Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Construction Of 3 Classrooms
output
Classrooms
implementation status
Completed
total cost
Ksh 760,000
estimate
Ksh 0

Koyonzo Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Construction Of 2 Classrooms
output
Classroom
implementation status
Completed
total cost
Ksh 760,000
estimate
Ksh 0

Eshirumbwe Primary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 750,000
estimate
Ksh 0

Ejinja Primary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Completed
total cost
Ksh 670,000
estimate
Ksh 0

Nanyeni Primary School

location
Koyonzo (in Matungu)
year first funded
2003
action
2 Classrooms
output
Classrooms
implementation status
Completed
total cost
Ksh 625,000
estimate
Ksh 0

Eshibanze Primary School

location
Matungu (in Matungu)
year first funded
2005
action
Constuction Of 2 Class Rooms & Toilet
output
Classrooms& Toilet
implementation status
Toilet Complete Classrooms Ongoing
total cost
Ksh 600,000
estimate
Ksh 0

Ngairwe Primary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Construction Of Hall & Classroom
output
Classroom And Hall
implementation status
Completed
total cost
Ksh 600,000
estimate
Ksh 0

Mukhweya Primary School

location
Matungu (in Matungu)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 600,000
estimate
Ksh 0

Bulimbo Primary School

location
Matungu (in Matungu)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 600,000
estimate
Ksh 0

District Officers Office

location
Matungu (in Matungu)
year first funded
2006
action
Construction Of Customer Care & Fencing
output
Customer Care Office & Fencing
implementation status
Completed
total cost
Ksh 550,000
estimate
Ksh 0

Lung'Anyiro -Namayaikalo Road

location
Matungu (in Matungu)
year first funded
2007
action
Construction Of Road
output
Road
implementation status
Completed
total cost
Ksh 527,104
estimate
Ksh 0

Matungu-Hospital Road

location
Matungu (in Matungu)
year first funded
2007
action
Construction Of Road
output
Road
implementation status
Completed
total cost
Ksh 502,000
estimate
Ksh 0

St. Pauls Ejinja Primary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Completed
total cost
Ksh 500,000
estimate
Ksh 0

Kholera Primary School

location
Matungu (in Matungu)
year first funded
2005
action
Construction Of Classroom & Office
output
Classroom & Office
implementation status
Completed
total cost
Ksh 500,000
estimate
Ksh 0

St. Tephen Namulungu Sec

location
Matungu (in Matungu)
year first funded
2007
action
Constrructing Water Tank &Piping The Whole School From The Bore Hole
output
Water To Flow To Every Part Of The School
implementation status
Completed
total cost
Ksh 500,000
estimate
Ksh 0

Munami Primary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Construction Of 2 Classrooms
output
Classroom
implementation status
Completed
total cost
Ksh 500,000
estimate
Ksh 0

Indangalasia Primary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Completed
total cost
Ksh 500,000
estimate
Ksh 0

Eshikondi Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 500,000
estimate
Ksh 0

Khalaba Primary School

location
Matungu (in Matungu)
year first funded
2005
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Completed
total cost
Ksh 500,000
estimate
Ksh 0

Namalenge Primary School

location
Matungu (in Matungu)
year first funded
2005
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Completed
total cost
Ksh 500,000
estimate
Ksh 0

Namulungu Ack Primary School

location
Matungu (in Matungu)
year first funded
2005
action
Construction Of 2 Classrooms
output
Classrooms
implementation status
Completed
total cost
Ksh 500,000
estimate
Ksh 0

Ebubambula Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Classroom Construction And Repair
output
Classroom
implementation status
Completed
total cost
Ksh 450,000
estimate
Ksh 0

Khabukoshe Primary School

location
Matungu (in Matungu)
year first funded
2006
action
Construction Of 1 Classroom
output
Classroom
implementation status
Ongoing
total cost
Ksh 400,000
estimate
Ksh 0

Bulonga Primary School

location
Matungu (in Matungu)
year first funded
2003
action
Construction Of 1 Classroom
output
Classroom
implementation status
Completed
total cost
Ksh 375,000
estimate
Ksh 0

Ststephen Namulungu Secondary School

location
Matungu (in Matungu)
year first funded
2006
action
Sinking Borehole
output
Borehole
implementation status
Ongoing
total cost
Ksh 350,000
estimate
Ksh 0

Ststephen Namulungu Secondary School

location
Matungu (in Matungu)
year first funded
2006
action
Sinking Borehole
output
Borehole
implementation status
Completed
total cost
Ksh 350,000
estimate
Ksh 0

Makokwe Primary School

location
Koyonzo (in Matungu)
year first funded
2007
action
Classroom Construction And Repair
output
Classroom
implementation status
Completed
total cost
Ksh 300,000
estimate
Ksh 0

Koyonzo Primary School

location
Koyonzo (in Matungu)
year first funded
2007
action
Repair Of Blown Roof
output
Roof
implementation status
Completed
total cost
Ksh 300,000
estimate
Ksh 0

Lunganyiro Primary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Construction Of 1 Classroom
output
Classroom
implementation status
Completed
total cost
Ksh 300,000
estimate
Ksh 0

Emanani Primary School

location
Matungu (in Matungu)
year first funded
2006
action
1 Classroom Construction
output
Classroom
implementation status
Completed
total cost
Ksh 300,000
estimate
Ksh 0

Emakale Primary School

location
Matungu (in Matungu)
year first funded
2006
action
1 Classroom Construction
output
Classroom
implementation status
Completed
total cost
Ksh 300,000
estimate
Ksh 0

Koyonzo Secondary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Construction Of Multipurpose Hall
output
Multipurpose Hall
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 0

Itete Secondary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Renovation Of Classroom
output
Classroom
implementation status
Completed
total cost
Ksh 300,000
estimate
Ksh 0

Emurabe Primary School

location
Matungu (in Matungu)
year first funded
2006
action
Classroom Completion
output
Classroom
implementation status
Completed
total cost
Ksh 300,000
estimate
Ksh 0

Namayaikalo Primary School

location
Koyonzo (in Matungu)
year first funded
2007
action
Classroom Construction And Repair
output
Classroom
implementation status
Completed
total cost
Ksh 300,000
estimate
Ksh 0

Mungungu Dispensary

location
Koyonzo (in Matungu)
year first funded
2004
action
Purchase Of Land & Labour Charges In Construction
output
Land
implementation status
Ongoing
total cost
Ksh 270,000
estimate
Ksh 0

Busombi Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Classroom Construction
output
Classroom
implementation status
Completed
total cost
Ksh 269,006
estimate
Ksh 0

Nanyeni

location
Koyonzo (in Matungu)
year first funded
2005
action
Purchase Of Land & Classroom Renovation
output
Land & Classroom
implementation status
Completed
total cost
Ksh 260,000
estimate
Ksh 0

Namulungu Dispensary

location
Matungu (in Matungu)
year first funded
2008
action
Renovation
output
Dispensary
implementation status
Completed And In Use
total cost
Ksh 250,000
estimate
Ksh 0

Namberekeya Primary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Construuction Of Classroom & Renovation
output
Classroom &Reno.
implementation status
Completed
total cost
Ksh 250,000
estimate
Ksh 0

Matungu Divisional Mock

location
Matungu (in Matungu)
year first funded
2006
action
Mocks To Be Done
output
Mocks
implementation status
Completed
total cost
Ksh 200,000
estimate
Ksh 0

Namberekeya Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Renovation Of Classroom
output
Classroom
implementation status
Completed
total cost
Ksh 188,750
estimate
Ksh 0

Matungu Community Social Goup

location
Matungu (in Matungu)
year first funded
2005
action
n/a
output
-
implementation status
Completed
total cost
Ksh 165,280
estimate
Ksh 0

Eshibanze Primary School

location
Matungu (in Matungu)
year first funded
2006
action
Construction Of Toilet
output
Toilet
implementation status
Completed
total cost
Ksh 150,000
estimate
Ksh 0

Namalasire Primary School

location
Koyonzo (in Matungu)
year first funded
2004
action
Repair Of Blown Roof
output
Roof
implementation status
Completed
total cost
Ksh 150,000
estimate
Ksh 0

Eshikhondi Primary School

location
Koyonzo (in Matungu)
year first funded
2007
action
Classroom Completion
output
Classroom
implementation status
Completed
total cost
Ksh 125,650
estimate
Ksh 0

Sayangwe Primary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Classroom Completion
output
Classroom
implementation status
Completed
total cost
Ksh 120,000
estimate
Ksh 0

Indangalasia Primary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Classroom Completion
output
Classroom
implementation status
Completed
total cost
Ksh 120,000
estimate
Ksh 0

Stejinja Primary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Classroom Completion
output
Classroom
implementation status
Completed
total cost
Ksh 120,000
estimate
Ksh 0

Munami Primary School

location
Koyonzo (in Matungu)
year first funded
2006
action
Classroom Completion
output
Classroom
implementation status
Completed
total cost
Ksh 120,000
estimate
Ksh 0

Ngairwe Primary School

location
Koyonzo (in Matungu)
year first funded
2005
action
Classroom Completion
output
Classroom
implementation status
Completed
total cost
Ksh 113,724
estimate
Ksh 0

Khalaba Primary School

location
Matungu (in Matungu)
year first funded
2007
action
Classroom Completion
output
Classroom
implementation status
Completed
total cost
Ksh 89,000
estimate
Ksh 0

Namulungu Primary School

location
Matungu (in Matungu)
year first funded
2006
action
Classroom Completion
output
Classroom
implementation status
Completed
total cost
Ksh 70,386
estimate
Ksh 0

Namalenge Primary School

location
Matungu (in Matungu)
year first funded
2006
action
Classroom Completion
output
Classroom
implementation status
Completed
total cost
Ksh 54,500
estimate
Ksh 0

Ejinja Primary School

location
Koyonzo (in Matungu)
year first funded
2007
action
Classroom Completion
output
Classroom
implementation status
Ongoing
total cost
Ksh 26,000
estimate
Ksh 0

Namasanda Primary School

location
Matungu (in Matungu)
action
Land Purchase
output
Land
implementation status
Completed
total cost
Ksh 0
estimate
Ksh 0