The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Sololo Water Project
- location
-
Sololo
(in Moyale)
- year first funded
- 2007
- action
- Supply Of Water From Walda To Sololo
- output
- Creating Access Of Water To Sololo Community
- implementation status
- Not Completed
- total cost
- Ksh 11,300,000
- estimate
- Ksh 5,000,000
Obbu Girls Secondary School
- location
-
Sololo
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Administra-Tion Block And Two Dormito-Ries And Three Classroomsand Laboratory.
- output
- To Establish A Girl Sec.
- implementation status
- Laboratory Completed Not In Use - Construction Of Classroom Funded In Fy09/10 Incomplete
- total cost
- Ksh 8,400,000
- estimate
- Ksh 7,900,000
Ele Borr Borehole
- location
-
Walda
(in Moyale)
- year first funded
- 2007
- action
- Drilling Bore Hole Classroom
- output
- Creating Access Of Water To Ele Borr Community
- implementation status
- Not Completed
- total cost
- Ksh 4,000,000
- estimate
- Ksh 4,000,000
Anona Borehole
- location
-
Sololo
(in Moyale)
- year first funded
- 2007
- action
- Sinking Bore Hole
- output
- Creating Access To Anona
- implementation status
- Not Completed
- total cost
- Ksh 4,000,000
- estimate
- Ksh 4,000,000
Manyatta Primary School
- location
-
Manyatta
(in Moyale)
- year first funded
- 2003
- action
- Eight Classrooms And Adm Block Built
- output
- To Meet Educational Need
- implementation status
- Complete And In Use
- total cost
- Ksh 3,300,000
- estimate
- Ksh 3,300,000
Godoma Didiqo Primary School
- location
-
Godoma
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Two Classroom And Two Latrine
- output
- Meet Education Need
- implementation status
- Complete And In Use
- total cost
- Ksh 2,900,000
- estimate
- Ksh 2,900,000
Baliti Secondary Walda
- location
-
Walda
(in Moyale)
- year first funded
- 2006
- action
- Construction Of Admin. Block And Classroom And Dormitory
- output
- Promote Education
- implementation status
- Complete And In Use
- total cost
- Ksh 2,800,000
- estimate
- Ksh 2,800,000
Holale Primary School
- location
-
Butiye
(in Moyale)
- year first funded
- 2004
- action
- Three Classroom Adm Block Kitchen And Toilet Built
- output
- To Create Conducive Learning Environment
- implementation status
- Complete And In Use
- total cost
- Ksh 2,700,000
- estimate
- Ksh 2,700,000
Golole Dam
- location
-
Golole
(in Moyale)
- year first funded
- 2008
- action
- Construction Of Dam
- output
- Access To Water
- implementation status
- Incomplete
- total cost
- Ksh 2,500,000
- estimate
- Ksh 0
Uran Godha Primary School
- location
-
Uran
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Classroom
- output
- To Meet On Going Education Demand
- implementation status
- Two Classroom Notcomplete And In Use Doors And Windows Not Fixedfurnishing Not Done
- total cost
- Ksh 2,500,000
- estimate
- Ksh 2,000,000
Sololo Dispensary
- location
-
Sololo
(in Moyale)
- year first funded
- 2008
- action
- Construction Of Health Centre
- output
- Access To Health
- implementation status
- Incomplete
- total cost
- Ksh 2,500,000
- estimate
- Ksh 0
Qate Primary School
- location
-
Qate
(in Moyale)
- year first funded
- 2003
- action
- Construction Ofclasses Adm.Block And Pitlatrine And One Classroom
- output
- Primary Education At The Location
- implementation status
- One Classroom Not Compelted - Doors And Windows Not Fixed And Furnihsing Not Done
- total cost
- Ksh 2,400,000
- estimate
- Ksh 2,400,000
Karbururi Primary School
- location
-
Uran
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Three Standard Class
- output
- To Meet Educational Demand
- implementation status
- Construction Of Classroom Funded In Fy09/10 Incomplete
- total cost
- Ksh 2,350,000
- estimate
- Ksh 1,850,000
Nana Primary School
- location
-
Nana
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Two Classrooms
- output
- To Meet Raising Education Demand
- implementation status
- Constraction Of Classroom Funded In Fy 09/10 Incomplete
- total cost
- Ksh 2,208,032
- estimate
- Ksh 1,600,000
Rawana Primary School
- location
-
Rawana
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Pry School(Lower Classes)
- output
- To Enhance Education Demand
- implementation status
- Complete And In Use
- total cost
- Ksh 2,200,000
- estimate
- Ksh 2,200,000
Sessi Primary School
- location
-
Central
(in Moyale)
- year first funded
- 2003
- action
- Three Administration Block Built
- output
- To Meet Educational Need
- implementation status
- Complete And In Use
- total cost
- Ksh 2,200,000
- estimate
- Ksh 2,200,000
Grading Of Roads To Sololo Hospital
- location
-
Sololo
(in Moyale)
- year first funded
- 2007
- action
- Grading Of Roads
- output
- Enhance Infrastructure
- implementation status
- Phase Ii Funded In Fy09/10 Incomplete
- total cost
- Ksh 2,200,000
- estimate
- Ksh 1,000,000
Funan Qumbi Primary School
- location
-
Rawana
(in Moyale)
- year first funded
- 2003
- action
- Five Thousand Pieces Of Blocks Made - Construction Of One Classroom
- output
- To Meet Educational Need
- implementation status
- Project Halted Due To Insecurity - Classroom Project Compelte
- total cost
- Ksh 2,100,000
- estimate
- Ksh 2,100,000
Uran Lataka Primary School
- location
-
Uran
(in Moyale)
- year first funded
- 2008
- action
- Construction Of Three Classes
- output
- Access To Education
- implementation status
- Incomplete
- total cost
- Ksh 2,100,000
- estimate
- Ksh 0
Uran Lataka Maternity
- location
-
Uran
(in Moyale)
- year first funded
- 2004
- action
- Construction Of Standard
- output
- Promote Health
- implementation status
- Complete And In Use
- total cost
- Ksh 2,100,000
- estimate
- Ksh 2,100,000
Somare Primary School
- location
-
Somare
(in Moyale)
- year first funded
- 2003
- action
- Two Classroom Built
- output
- To Enhance Education
- implementation status
- Construction Of One Classroom Not Done (09/10)
- total cost
- Ksh 1,847,169
- estimate
- Ksh 1,697,169
Godoma Maternity
- location
-
Godoma
(in Moyale)
- year first funded
- 2004
- action
- Construction Of Standard Maternity
- output
- To Enhance Health
- implementation status
- Complete And In Use
- total cost
- Ksh 1,800,000
- estimate
- Ksh 1,800,000
Moyale Girls Secondary School
- location
-
Central
(in Moyale)
- year first funded
- 2004
- action
- Construction Of Administration Block
- output
- Promote Education
- implementation status
- Complete And In Use
- total cost
- Ksh 1,613,114
- estimate
- Ksh 1,613,114
Walda Maternity
- location
-
Walda
(in Moyale)
- year first funded
- 2004
- action
- Construction Of Standard Maternity
- output
- Promote Health
- implementation status
- Complete And In Use
- total cost
- Ksh 1,600,000
- estimate
- Ksh 1,600,000
Sololo Makutano Dispensary
- location
-
Sololo
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Dispensary
- output
- To Bring Improve Health Service For Community
- implementation status
- Complete And In Use
- total cost
- Ksh 1,520,000
- estimate
- Ksh 1,520,000
Bori River
- location
-
Bori
(in Moyale)
- year first funded
- 2008
- action
- Rehabilitation Of River
- output
- Access To Water
- implementation status
- Incomplete
- total cost
- Ksh 1,500,000
- estimate
- Ksh 0
Manyatta Primary School
- location
-
Manyatta
(in Moyale)
- year first funded
- 2008
- action
- Construction Of Administration Block
- output
- Access To Education
- implementation status
- Incomplete
- total cost
- Ksh 1,500,000
- estimate
- Ksh 0
Heilu Primary School
- location
-
Heilu
(in Moyale)
- year first funded
- 2006
- action
- Construction Of Two Classrooms
- output
- Promote Education
- implementation status
- Not Complete
- total cost
- Ksh 1,400,000
- estimate
- Ksh 700,000
Df Maternity
- location
-
Dambala Fachana
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Standard Maternity
- output
- To Bring Improved Health Services Closer To Community
- implementation status
- Complete And In Use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,300,000
Madho Adhi Dispensary
- location
-
Uran
(in Moyale)
- year first funded
- 2004
- action
- Construction Of Dispensary And The Equipment
- output
- To Improve Health Facility
- implementation status
- Complete And In Use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,300,000
Golole Maternity
- location
-
Uran
(in Moyale)
- year first funded
- 2004
- action
- Construction Of Standard Maternity
- output
- To Bring Health Facility Within Community Reach
- implementation status
- Complete And In Use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,300,000
Dabel Dispensary
- location
-
Dabel
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Dispensary
- output
- To Bring Health Facility To The Community
- implementation status
- Complete
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,300,000
Anona Dispensary
- location
-
Anona
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Standard Dispensary
- output
- Promote Health
- implementation status
- Complete And In Use
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,200,000
Satellite Provision For Banale, Funan Qumbi And Bododa Communities
- location
-
Walda, Funan, Qumbi, Bododa And Banale
(in Moyale)
- year first funded
- 2006
- action
- Provision Of Satellite Phones
- output
- Creating Provision Of Communication Tools
- implementation status
- Complete And In Use
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,200,000
Karbururi Water Tank
- location
-
Sololo
(in Moyale)
- year first funded
- 2005
- action
- Tank Built
- output
- Access Water
- implementation status
- Completed And Not In Use
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,200,000
Butiye Dispensary
- location
-
Butiye
(in Moyale)
- year first funded
- 2003
- action
- Varnishing And Equipping
- output
- To Bring Health Services Nearer
- implementation status
- Complete And In Use
- total cost
- Ksh 1,150,000
- estimate
- Ksh 1,150,000
Waye Godha Irrigation
- location
-
Uran
(in Moyale)
- year first funded
- 2004
- action
- Plots For 2 Groups Constructed Fenced And A Tank Built
- output
- To Boost Horticultural Gardening
- implementation status
- Complete And In Use
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,100,000
Bori Maternity
- location
-
Bori
(in Moyale)
- year first funded
- 2003
- action
- n/a
- output
- Creation Of Improved Health
- implementation status
- Complete Not Furnished And Not In Use
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,100,000
Walda Community Dispensary
- location
-
Walda
(in Moyale)
- year first funded
- 2004
- action
- Bringing Health Facilities Towards Walda Resident
- output
- To Access Health Facility
- implementation status
- Complete And In Use
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,100,000
Uran Health Centre
- location
-
Uran
(in Moyale)
- year first funded
- 2008
- action
- Construction Of Health Centre
- output
- Access To Health
- implementation status
- Incomplete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 0
Karbururi Dispensary
- location
-
Uran
(in Moyale)
- year first funded
- 2007
- action
- Construction Of Dispensary
- output
- Creating Access Of Health Facility To
- implementation status
- Complete And In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Funan Qumbi Admpolice
- location
-
Walda
(in Moyale)
- year first funded
- 2007
- action
- Construction Of Ap Staff House
- output
- Creating Access To Securityfor Funan Qumbi Community
- implementation status
- Complete And In Use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Moyale Boys Secondary School
- location
-
Butiye
(in Moyale)
- year first funded
- 2004
- action
- Construction Of Classroom
- output
- Promote Education Facility
- implementation status
- Complete And In Use
- total cost
- Ksh 900,000
- estimate
- Ksh 900,000
Waye Primary School
- location
-
Uran
(in Moyale)
- year first funded
- 2006
- action
- Construction Of One Classroom
- output
- Promote Education
- implementation status
- Complete And In Use
- total cost
- Ksh 900,000
- estimate
- Ksh 900,000
Muslim Primary School
- location
-
Central
(in Moyale)
- year first funded
- 2005
- action
- Admiistration Block Built
- output
- To Have Good And Efficient Teaching Facilities
- implementation status
- Completed And In Use
- total cost
- Ksh 900,000
- estimate
- Ksh 900,000
Sololo Primary School
- location
-
Sololo
(in Moyale)
- year first funded
- 2007
- action
- Construction Of Classroom
- output
- Promote Education
- implementation status
- Completed
- total cost
- Ksh 800,000
- estimate
- Ksh 800,000
Odda Maternity
- location
-
Odda
(in Moyale)
- year first funded
- 2005
- action
- Construction Of Maternity
- output
- To Bring Health Facility Closer To The Community
- implementation status
- Funded
- total cost
- Ksh 800,000
- estimate
- Ksh 800,000
Manyatta Social Hall
- location
-
Manyatta
(in Moyale)
- year first funded
- 2007
- action
- Construction Of Social Hall
- output
- Provision Of Education
- implementation status
- Incomplete
- total cost
- Ksh 800,000
- estimate
- Ksh 800,000
Butiye Store
- location
-
Butiye
(in Moyale)
- year first funded
- 2007
- action
- Provison Of Storage Facility
- output
- Enhance Storage Hall
- implementation status
- Complete And In Use
- total cost
- Ksh 800,000
- estimate
- Ksh 800,000
Qilta Primary School
- location
-
Qilta
(in Moyale)
- year first funded
- 2008
- action
- Construction Of One Class
- output
- Access To Education
- implementation status
- Incomplete
- total cost
- Ksh 750,000
- estimate
- Ksh 0
Df Social Hall
- location
-
Dambala Fachana
(in Moyale)
- year first funded
- 2006
- action
- Building Social Hall
- output
- Provision Of Education
- implementation status
- Complete And In Use
- total cost
- Ksh 700,000
- estimate
- Ksh 700,000
Yaballo Primary School
- location
-
Yaballo
(in Moyale)
- year first funded
- 2005
- action
- Construction Of Two Classrooms
- output
- To Bring Education Closer To Community
- implementation status
- Complete Classroom In Use Dispensary Not In Use
- total cost
- Ksh 700,000
- estimate
- Ksh 700,000
Walda Primary School
- location
-
Walda
(in Moyale)
- year first funded
- 2006
- action
- Construction Of Two Classrooms
- output
- Promote Education
- implementation status
- Not Complete
- total cost
- Ksh 700,000
- estimate
- Ksh 700,000
Sololo Water Supply
- location
-
Sololo
(in Moyale)
- year first funded
- 2004
- action
- Building Of Water Kiosk
- output
- Access Of Water
- implementation status
- Complete And In Use
- total cost
- Ksh 700,000
- estimate
- Ksh 700,000
Sololo Boys Secondary School
- location
-
Sololo
(in Moyale)
- year first funded
- 2007
- action
- Reconstruction Of One Burnt Dormitory
- output
- Promote Education Facility
- implementation status
- Complete And In Use
- total cost
- Ksh 700,000
- estimate
- Ksh 700,000
Golole Social Hall
- location
-
Uran
(in Moyale)
- year first funded
- 2006
- action
- Construction Of Social Hall
- output
- Provision Of Social Amenities
- implementation status
- Complete And In Use
- total cost
- Ksh 700,000
- estimate
- Ksh 700,000
Kinisa Primary School
- location
-
Kinisa
(in Moyale)
- year first funded
- 2004
- action
- Construction Of Two Manonry Tanks Built And In Use 500,000Ltrs
- output
- To Provide Water For Primary School
- implementation status
- Purchase Of Desks Not Done (09/10)
- total cost
- Ksh 650,000
- estimate
- Ksh 500,000
Sololo Township
- location
-
Sololo
(in Moyale)
- year first funded
- 2006
- action
- 50 Desk Tables
- output
- Helping Sitting Facilities
- implementation status
- Complete And In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Godoma Primary School
- location
-
Godoma
(in Moyale)
- year first funded
- 2007
- action
- Construction Of One Classroom
- output
- Promote Education
- implementation status
- Complete And In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Bori Primary School
- location
-
Bori
(in Moyale)
- year first funded
- 2007
- action
- Reconstruction Of One Classroom And Fencing
- output
- Promote Education
- implementation status
- Complete
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Uran Godha Primary School
- location
-
Uran
(in Moyale)
- year first funded
- 2008
- action
- Construction Of One Class
- output
- Access To Education
- implementation status
- Incomplete
- total cost
- Ksh 500,000
- estimate
- Ksh 0
Somare Primary School
- location
-
Somare
(in Moyale)
- year first funded
- 2007
- action
- Construction Of One Classroom
- output
- Promote Education
- implementation status
- Complete And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Construction Of Ap Post
- location
-
Rawana
(in Moyale)
- year first funded
- 2005
- action
- Construction Of Ap Post
- output
- Enhance Security
- implementation status
- Complete And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Banale Primary School
- location
-
Walda
(in Moyale)
- year first funded
- 2007
- action
- Construction Of One Classroom
- output
- Promote Education For Nomadic
- implementation status
- Complete And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Anona Primary School
- location
-
Walda
(in Moyale)
- year first funded
- 2007
- action
- Construction Of One Classroom
- output
- Promote Education
- implementation status
- Complete And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Ambalo Primary School
- location
-
Ambalo
(in Moyale)
- year first funded
- 2007
- action
- Construction Of Classes
- output
- Promote Education
- implementation status
- Completed
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Ramole Primary School
- location
-
Sololo
(in Moyale)
- year first funded
- 2007
- action
- Construction Of Classroom
- output
- Promote Education Facilities
- implementation status
- Complete And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Much Gura Primary School
- location
-
Golole
(in Moyale)
- year first funded
- 2007
- action
- Construction Of One Classroom
- output
- Promote Education
- implementation status
- Complete And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Heilu Maternity
- location
-
Heilu
(in Moyale)
- year first funded
- 2003
- action
- Maternity Block Built 80% Complete
- output
- To Bring Health Services Nearer
- implementation status
- Complete And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Golole Primary School
- location
-
Golole
(in Moyale)
- year first funded
- 2008
- action
- Construction Of One Class
- output
- Access To Education
- implementation status
- Incomplete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Godoma Didiko Borehole
- location
-
Godoma
(in Moyale)
- year first funded
- 2008
- action
- Cdf Contribution To The Community
- output
- Access To Water
- implementation status
- Incomplete
- total cost
- Ksh 500,000
- estimate
- Ksh 0
Galma Primary School
- location
-
Uran
(in Moyale)
- year first funded
- 2007
- action
- Construction Of One Classroom
- output
- Promote Education
- implementation status
- Complete And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Dabel Secondary School
- location
-
Dabel
(in Moyale)
- year first funded
- 2008
- action
- Community Distribution By Cdf
- output
- Access To Education
- implementation status
- Incomplete
- total cost
- Ksh 500,000
- estimate
- Ksh 0
Peace And Reconciliation
- location
-
Sololo
(in Moyale)
- year first funded
- 2004
- action
- Facilitating Peace Process
- output
- Minimize Interclan Rivalry
- implementation status
- Facilitated
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Dadach Elele Dam
- location
-
Uran
(in Moyale)
- year first funded
- 2006
- action
- Construction Of Dam
- output
- Access Water Point
- implementation status
- Not Done
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Ramole Earth Pan
- location
-
Sololo
(in Moyale)
- year first funded
- 2006
- action
- Earth Pan Manually Constructed
- output
- To Give Water Point
- implementation status
- Completed And In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Odda Water Supply
- location
-
Odda
(in Moyale)
- year first funded
- 2003
- action
- Construction Of Water Kiosk
- output
- Access Of Water To The Resident Of Odda
- implementation status
- Complete
- total cost
- Ksh 220,000
- estimate
- Ksh 220,000
Moyale District Deeda Council
- location
-
Sololo
(in Moyale)
- year first funded
- 2006
- action
- Awareness Creation On Environmental Conservation
- output
- To Conserve Environment
- implementation status
- Facilitated
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Madho Furniture
- location
-
Uran
(in Moyale)
- year first funded
- 2006
- action
- 50 (Furniture) Desk
- output
- Helping Sitting Facilities
- implementation status
- Complete And In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Mado Adhi
- location
-
Sololo
(in Moyale)
- year first funded
- 2007
- action
- Construction Of Classrooms
- output
- Promote Education
- implementation status
- Completed
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Purchase Of Unihuts - Rawana
- location
-
Rawana
(in Moyale)
- year first funded
- 2006
- action
- Purchase Of Unihuts
- output
- To Develop Security
- implementation status
- Complete And In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000