The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Magare Secondary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom & Lab Office Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 4,560,000
- estimate
- Ksh 3,350,000
Nyangoma Secondary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2003
- action
- Lab & Lib Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 4,410,000
- estimate
- Ksh 3,800,000
Mariwa Secondary School
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 4,200,000
- estimate
- Ksh 3,600,000
Menara Secondary School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2004
- action
- Lab&Dom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 4,200,000
- estimate
- Ksh 3,700,000
Oduwo Secondary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2004
- action
- Class/Adm/Lab Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 4,100,000
- estimate
- Ksh 3,600,000
Koru Clinic
- location
-
Koru
(in Muhoroni)
- year first funded
- 2003
- action
- Clinic & Staff House Bldg Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 3,295,000
- estimate
- Ksh 3,035,000
Ogen Secondary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 3,100,000
- estimate
- Ksh 2,500,000
Olik Oliero Secondary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,750,000
- estimate
- Ksh 1,300,000
Oginga Odinga Secondary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom & Admin Block Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,750,000
- estimate
- Ksh 2,000,000
Soghor Secondary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,700,000
- estimate
- Ksh 2,400,000
Ngeny' Secondary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,695,000
- estimate
- Ksh 2,000,000
God Abuoro Secondary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom & Admin Block Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,600,000
- estimate
- Ksh 2,000,000
Ombeyi Secondary School
- location
-
Ombeyi North
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,580,000
- estimate
- Ksh 2,180,000
Nyangore Footbridge
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2004
- action
- Bridge Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 2,565,000
- estimate
- Ksh 2,565,000
Kibigori Secondary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,550,000
- estimate
- Ksh 1,950,000
Muhoroni Secondary School
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2004
- action
- Multipurpose Hall Cons
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,480,000
- estimate
- Ksh 2,180,000
Ngere Kagoro Secondary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2004
- action
- Admin. Block Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,475,000
- estimate
- Ksh 2,080,000
Fort Tenan Health Clinic
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2003
- action
- Maternity Ward & Placenta Pit Const
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,450,000
- estimate
- Ksh 2,150,000
Miwani Secondary School
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2004
- action
- Multipurp Hall Cons
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,380,000
- estimate
- Ksh 2,080,000
Koru Secondary School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2004
- action
- Dom Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 2,380,000
- estimate
- Ksh 2,080,000
Nyakoko Secondary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2003
- action
- Library Constuction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,380,000
- estimate
- Ksh 2,080,000
Township Primary School
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,366,000
- estimate
- Ksh 1,966,000
St. Augustine Kandege Secondary School
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2004
- action
- Staff House, Dom, Class, Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,280,000
- estimate
- Ksh 1,980,000
Achego Secondary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,280,000
- estimate
- Ksh 1,980,000
Our Queen Of Peace Secondary School
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 2,050,000
- estimate
- Ksh 1,300,000
Ruke Primary School
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,991,000
- estimate
- Ksh 1,691,000
Cappuchin Franciscan Masogo Girls Secondary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Lockers/Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,700,000
- estimate
- Ksh 1,700,000
Miwani West Water Project
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2003
- action
- Purchase And Instalation Of Water Pump
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,550,000
- estimate
- Ksh 1,550,000
Mutuala Primary School
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,541,000
- estimate
- Ksh 1,241,000
Kipturi Primary School
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,350,000
- estimate
- Ksh 1,100,000
Tamu Health Centre
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2003
- action
- Staff House/ Water/Electric
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,275,000
- estimate
- Ksh 700,000
Jaber Primary School
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,250,000
- estimate
- Ksh 1,050,000
Tonde Primary School
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,250,000
- estimate
- Ksh 1,050,000
Nyangoma Water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2008
- action
- Borehole Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,150,000
- estimate
- Ksh 700,000
Nyando Primary School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,025,000
- estimate
- Ksh 735,000
Muhoroni District Headquarter
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Gul Primary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,000,000
- estimate
- Ksh 850,000
Muhoroni Factory Primary School
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,000,000
- estimate
- Ksh 800,000
Chiefs Office
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2005
- action
- Office Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,000,000
- estimate
- Ksh 950,000
Archbishop Okoth College Of Technology
- location
-
Koru
(in Muhoroni)
- year first funded
- 2008
- action
- Renovation /Extention/ Equipment
- output
- -
- implementation status
- On Going
- total cost
- Ksh 1,000,000
- estimate
- Ksh 500,000
Soghor Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 971,430
- estimate
- Ksh 721,430
Saoset Water Project
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2004
- action
- Borehole Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 930,000
- estimate
- Ksh 700,000
Miwani Section Iii Primary School
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 925,000
- estimate
- Ksh 675,000
Oroba Primary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 890,000
- estimate
- Ksh 700,000
Kisure Primary School
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 800,000
- estimate
- Ksh 600,000
Koru Township Primary School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 790,000
- estimate
- Ksh 790,000
Karunga Primary School
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 750,000
- estimate
- Ksh 650,000
Nyakoko Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 737,000
- estimate
- Ksh 562,000
Kibigori Railways Primary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 725,000
- estimate
- Ksh 625,000
School Desks
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2004
- action
- Supply Of Desks
- output
- -
- implementation status
- Complete
- total cost
- Ksh 720,000
- estimate
- Ksh 720,000
Kibigori Primary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 705,000
- estimate
- Ksh 605,000
Ogwedhi Primary School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2006
- action
- Land Purchase,Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 700,000
- estimate
- Ksh 600,000
Makindu Dispensary
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2003
- action
- Marternity Construction &Beds
- output
- -
- implementation status
- On Going
- total cost
- Ksh 700,000
- estimate
- Ksh 400,000
Nyarenda Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 700,000
- estimate
- Ksh 400,000
Cheptuiyet Primary School
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 690,000
- estimate
- Ksh 490,000
Kipchoria Primary School
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 690,000
- estimate
- Ksh 490,000
Miwani Estate Health Clinic
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2003
- action
- Dispensary Constr, Furniture & Water Sink
- output
- -
- implementation status
- On Going
- total cost
- Ksh 675,000
- estimate
- Ksh 675,000
Ngere Kagoro Police Post
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2005
- action
- Office Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 650,000
- estimate
- Ksh 500,000
Nyatao Secondary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- Construction/Lab Equipments
- output
- -
- implementation status
- On Going
- total cost
- Ksh 650,000
- estimate
- Ksh 650,000
God Nyithindo Primary School Electrification
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2004
- action
- Electrification
- output
- -
- implementation status
- On Going
- total cost
- Ksh 650,000
- estimate
- Ksh 550,000
Osembe Primary School
- location
-
Ombeyi South
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 640,000
- estimate
- Ksh 540,000
Homalimekipsamwe Primary School
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 640,000
- estimate
- Ksh 540,000
Mikiria Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 635,000
- estimate
- Ksh 360,000
Kware Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 621,430
- estimate
- Ksh 421,430
Obago Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 616,663
- estimate
- Ksh 426,363
Masara Primary School
- location
-
Ombeyi South
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 610,000
- estimate
- Ksh 410,000
Chiefs Office Construction
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2007
- action
- Office Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 600,000
- estimate
- Ksh 300,000
Magare Community Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Pipes &Tank Installation
- output
- -
- implementation status
- Complete
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Nyakungru Dispensary
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Dispensary Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 600,000
- estimate
- Ksh 450,000
Nyangore Primary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 600,000
- estimate
- Ksh 450,000
Nyalenya Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 600,000
- estimate
- Ksh 425,000
Kandege Primary School
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 590,000
- estimate
- Ksh 390,000
Tamu Central Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 575,000
- estimate
- Ksh 450,000
Orenge Primary School
- location
-
Ombeyi North
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 570,000
- estimate
- Ksh 370,000
Mitando Primary School
- location
-
Ombeyi South
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 560,000
- estimate
- Ksh 410,000
Nyangoto Primary School
- location
-
Ombeyi South
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 560,000
- estimate
- Ksh 410,000
Kigoche Primary School
- location
-
Ombeyi South
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 560,000
- estimate
- Ksh 410,000
Oduwo Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2003
- action
- Toilet/Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 555,000
- estimate
- Ksh 380,000
Ogen Dispensary
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2004
- action
- Staff House Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 550,000
- estimate
- Ksh 400,000
Cheptuiyet Dispensary
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2007
- action
- Dispensary Construct.
- output
- -
- implementation status
- On Going
- total cost
- Ksh 550,000
- estimate
- Ksh 350,000
Muhoroni Hospital Water
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2004
- action
- Supply Of Water
- output
- -
- implementation status
- Complete
- total cost
- Ksh 550,000
- estimate
- Ksh 300,000
Muhoroni Water Association
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2004
- action
- Water Supply
- output
- -
- implementation status
- Complete
- total cost
- Ksh 550,000
- estimate
- Ksh 550,000
Nyangoma Health Centre
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Construction Of Maternity Wing
- output
- -
- implementation status
- On Going
- total cost
- Ksh 550,000
- estimate
- Ksh 400,000
Chemelil Market Dispensary
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Construction Of Maternity Wing
- output
- -
- implementation status
- On Going
- total cost
- Ksh 550,000
- estimate
- Ksh 400,000
Saoset Primary School
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 540,000
- estimate
- Ksh 540,000
Nyatao Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 539,000
- estimate
- Ksh 389,000
Kiliti Primary School
- location
-
Ombeyi North
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 520,000
- estimate
- Ksh 370,000
Ombeyi Primary School
- location
-
Ombeyi North
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 520,000
- estimate
- Ksh 370,000
Obiayo Primary School
- location
-
Ombeyi South
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 510,000
- estimate
- Ksh 510,000
Wagai Primary School
- location
-
Ombeyi South
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 510,000
- estimate
- Ksh 510,000
Bacho Primary School
- location
-
Ombeyi South
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 510,000
- estimate
- Ksh 510,000
Kibos Prison Primary School
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Miwani Division Resource Centre
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 500,000
- estimate
- Ksh 0
Round About Water Project
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2004
- action
- Pipe Costruction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Nyangoma Village Polytechnic
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Renovation And Equipment
- output
- -
- implementation status
- On Going
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Nyangoma Water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Pipe Laying
- output
- -
- implementation status
- On Going
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Miwani Estate Primary School
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 500,000
- estimate
- Ksh 400,000
Masogo/Waware Youth Polytechnic
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Class/Adm Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Ngula Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Minyange Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 490,000
- estimate
- Ksh 390,000
Ramula Primary School
- location
-
Ombeyi North
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 470,000
- estimate
- Ksh 370,000
Thurbie Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 465,000
- estimate
- Ksh 315,000
Ogilo Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 459,419
- estimate
- Ksh 346,363
Kibigori Police Post
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2005
- action
- Ap Line Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 450,000
- estimate
- Ksh 450,000
Jagir Singh Primary School
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 450,000
- estimate
- Ksh 350,000
Ngere Kagoro Water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Pipes Installation
- output
- -
- implementation status
- On Going
- total cost
- Ksh 450,000
- estimate
- Ksh 100,000
Education Improvement
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 450,000
- estimate
- Ksh 450,000
Ogwodo Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 447,363
- estimate
- Ksh 364,363
Yago Dispensary
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2007
- action
- Dispensary Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 446,430
- estimate
- Ksh 321,430
Orago Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 445,000
- estimate
- Ksh 295,000
Kolang' Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 440,000
- estimate
- Ksh 290,000
Oneno Nam Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 435,000
- estimate
- Ksh 300,000
Sanda Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 431,563
- estimate
- Ksh 336,363
Pawteng Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 429,000
- estimate
- Ksh 279,000
Sangayo Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 426,663
- estimate
- Ksh 336,363
Ngeny' Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 425,000
- estimate
- Ksh 425,000
Soghor Dispensary
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2007
- action
- Dispensary Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 421,430
- estimate
- Ksh 221,430
Lwala Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2003
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 421,430
- estimate
- Ksh 421,430
Mashambani Dispensary
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2007
- action
- Dispensary Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 421,420
- estimate
- Ksh 221,420
Okwach Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 420,000
- estimate
- Ksh 320,000
Magare Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 416,363
- estimate
- Ksh 286,363
Wambi Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 409,419
- estimate
- Ksh 296,363
Ngiti Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 409,419
- estimate
- Ksh 296,363
Chiefs Office Extension
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Extension Of Chief'S Office
- output
- -
- implementation status
- On Going
- total cost
- Ksh 402,000
- estimate
- Ksh 202,000
Cheptuiyet Nursery Schoolwater Project
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2008
- action
- Well Construction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 400,000
- estimate
- Ksh 200,000
God Nyithindo Primary School
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2005
- action
- Fencing
- output
- -
- implementation status
- On Going
- total cost
- Ksh 400,000
- estimate
- Ksh 200,000
Kibos School For The Blind
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 400,000
- estimate
- Ksh 300,000
Kibigori Dispensary
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2004
- action
- Clinic Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
God Ruke Primary School Water Project
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2008
- action
- Borehole Construction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 400,000
- estimate
- Ksh 200,000
Tamu Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 396,430
- estimate
- Ksh 221,430
Omanyi Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 390,000
- estimate
- Ksh 200,000
Nyakungru Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 382,363
- estimate
- Ksh 299,363
Olik Oliero Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 375,000
- estimate
- Ksh 300,000
Osiri Migere Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 374,000
- estimate
- Ksh 374,000
Milenye Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 370,000
- estimate
- Ksh 370,000
Rangombe Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 370,000
- estimate
- Ksh 300,000
Educational Improvement
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2006
- action
- Lab& Comp Equip
- output
- -
- implementation status
- Complete
- total cost
- Ksh 360,000
- estimate
- Ksh 360,000
Oyani Primary School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 360,000
- estimate
- Ksh 360,000
Kowawa Police Post
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2008
- action
- Office Construction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 350,000
- estimate
- Ksh 200,000
Mashambani Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 350,000
- estimate
- Ksh 250,000
Tonde Water Project
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2004
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 350,000
- estimate
- Ksh 350,000
Kopere Police Post
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2008
- action
- Police Post Construction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 350,000
- estimate
- Ksh 200,000
Chemelil B Primary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 350,000
- estimate
- Ksh 350,000
Assistant Chiefs' Office
- location
-
Koru
(in Muhoroni)
- year first funded
- 2007
- action
- Office Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 350,000
- estimate
- Ksh 200,000
Purchase Of Land Ongalo Primary School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2007
- action
- Land Purchase
- output
- -
- implementation status
- To Be Reallocated
- total cost
- Ksh 350,000
- estimate
- Ksh 350,000
Nyakoko Stream Drainage
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Desiltation
- output
- -
- implementation status
- Complete
- total cost
- Ksh 330,000
- estimate
- Ksh 130,000
Osengteti Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 300,000
- estimate
- Ksh 200,000
Ngeny Special School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- D. Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Mariwa Secondary School Water Project
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2008
- action
- Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Yago Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 300,000
- estimate
- Ksh 200,000
Makindu Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 300,000
- estimate
- Ksh 200,000
God Abuoro Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 300,000
- estimate
- Ksh 200,000
Educational Improvement
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2007
- action
- Lab Equip
- output
- -
- implementation status
- Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Nyakoko Oroba Drainage
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Flood Control
- output
- -
- implementation status
- Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kabonyo Village Miwani West
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2009
- action
- Transformer
- output
- -
- implementation status
- On Going
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kabar West Catlle Dip Land Purchase
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Rehabilitation
- output
- -
- implementation status
- Complete
- total cost
- Ksh 296,000
- estimate
- Ksh 296,000
Wuok Nursery /Primary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 295,000
- estimate
- Ksh 145,000
Ang'Ogo Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 295,000
- estimate
- Ksh 295,000
Amilo Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 290,000
- estimate
- Ksh 220,000
Kodhiambo Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 286,000
- estimate
- Ksh 236,000
Gatundu Village Nursery/Pri
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 270,000
- estimate
- Ksh 70,000
St. Johns' Primary School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2006
- action
- Desks/Toilet Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 270,000
- estimate
- Ksh 70,000
Ogwedhi Primary School foot Bridge
- location
-
Koru
(in Muhoroni)
- year first funded
- 2007
- action
- Footbridge Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 250,000
- estimate
- Ksh 100,000
Achego Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 250,000
- estimate
- Ksh 250,000
Muhoroni Primary School
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2005
- action
- Fencing
- output
- -
- implementation status
- Complete
- total cost
- Ksh 250,000
- estimate
- Ksh 250,000
Educational Improvement
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Laboratory Equipping
- output
- -
- implementation status
- Complete
- total cost
- Ksh 250,000
- estimate
- Ksh 250,000
Mdemp - Kibigori Settlement
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2009
- action
- Silt/Veg Removal
- output
- -
- implementation status
- To Start
- total cost
- Ksh 250,000
- estimate
- Ksh 250,000
Kibigori Muslim Community School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2008
- action
- Classroom Construction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 250,000
- estimate
- Ksh 250,000
Ogen Primary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 250,000
- estimate
- Ksh 200,000
Ngere Kagoro Cattle Dip
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Renovation
- output
- -
- implementation status
- On Going
- total cost
- Ksh 250,000
- estimate
- Ksh 50,000
Sanitary Facilities In Primary School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2003
- action
- Pit Latrine Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 245,000
- estimate
- Ksh 245,000
Kasongo Health Centre
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Toilet Facility/Disp Bldg
- output
- -
- implementation status
- On Going
- total cost
- Ksh 235,000
- estimate
- Ksh 235,000
Rapogi Community Water Project
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2007
- action
- Well Contruction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 225,000
- estimate
- Ksh 125,000
Sidho Owee Comwater Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 225,000
- estimate
- Ksh 225,000
Nyangore Nursery School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 220,000
- estimate
- Ksh 70,000
Makiindu Primary School Water Project
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2008
- action
- Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Simbi Luora Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2004
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Holo Community Water Project
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2009
- action
- Well Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 200,000
- estimate
- Ksh 20,000
Chief's Office Construction/Elect
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Office Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 150,000
St. Claudio Kowiti Primary School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2008
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Achego Primary School water Project
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Chiefs Office Construction
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2006
- action
- Office Consteruction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kagai Water Project
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2007
- action
- Pipes Installation
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Koru Hospital Generator
- location
-
Koru
(in Muhoroni)
- year first funded
- 2007
- action
- Purchase Of Generator
- output
- -
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Pombo Water Project
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2008
- action
- Well Construction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Mdemp-Oroba/Miwani Estate
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2009
- action
- Drainage/Veg Removal
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kibos Nubian Nursery
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Mdemp-Nyakoko/Ogandi
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Drainage Work
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Mdemp-Sangayo/Obago
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Drainage Work
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Mdemp-Siala/Abwao
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Drainage Work
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 0
Sanda Community Irrigation Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Irrigation
- output
- -
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Masogo Health Centre
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2004
- action
- Repair Works
- output
- -
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Wuok Primary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2008
- action
- Classroom Construction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kibigori Cattle Dip
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2008
- action
- Dip Construction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Profayiecho Kibigori Nursery School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2008
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 100,000
Apidi Nursery
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 75,000
Katuk Community Water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- Well Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Geno Community Water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- Well Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Masaka Community Water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- Well Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Mdemp-Kamagaga/Owee Village
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- Silt/Veg Removal
- output
- -
- implementation status
- To Start
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Chemelil Market Police Post
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- construction Of Police Post Bldn
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ngere Kagoro Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 200,000
- estimate
- Ksh 100,000
Ogen Nursery School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 185,000
- estimate
- Ksh 75,000
Desks/Students Lockers
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2007
- action
- Purchase Of Lockers/Chairs
- output
- -
- implementation status
- On Going
- total cost
- Ksh 185,000
- estimate
- Ksh 185,000
Nyalelbuch Water Project
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2004
- action
- Shalowest Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 175,000
- estimate
- Ksh 100,000
Sanda Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2005
- action
- Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 170,000
- estimate
- Ksh 170,000
Osiri Migere Primary School Water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2005
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 170,000
- estimate
- Ksh 170,000
Minyange Primary School water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 170,000
- estimate
- Ksh 170,000
Sugarbelt Nursery School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom & Toilet Rehabilitation
- output
- -
- implementation status
- Complete
- total cost
- Ksh 165,000
- estimate
- Ksh 165,000
Ramanda Nursery School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 160,370
- estimate
- Ksh 60,370
Oyani Nursery School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 160,000
- estimate
- Ksh 160,000
Bondo Community Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Ogen Dispensary Water Project
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2006
- action
- Well Contruction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Menara Primary School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Education Improvement[Menara]
- location
-
Koru
(in Muhoroni)
- year first funded
- 2006
- action
- Lab Equipment
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
St. Augustine Kandege Secondary School Water Project
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2006
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Electric Power Kandege
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2006
- action
- Purchase Of Generator
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Jua Kali Compound Fence
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2007
- action
- Fencing
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Mariwa Primary School
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Education Improvement
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2006
- action
- Lab Equipment
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Simbi Luora Primary School Water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2006
- action
- Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
St. Joseph Ngula Primary School Water Proj
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Makindu Dispensary Water Proj
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Okwach Primary School water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Mibasi Community Water
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2008
- action
- Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Nyadundo Primary School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Mikiria Community Water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- Well Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Lockers And Chairs
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Purchasechairs/Lockers
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Siala Community Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Well & Pump construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Ogilo Primary School water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Well & Pump construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Ngiti Primary School water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Well & Pump Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Waware Primary School water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Well & Pump Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Kaktai Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Well & Pump Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Ramanda Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Well & Pump Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Ogwodo Primary School water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Well & Pump Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Wagunga Obago Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Well & Pump Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Sanitary Facility
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2004
- action
- Public Toilet Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 50,000
Abwao Community Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Okiro Community Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
North Kamrika Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Kunya Community Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Mumbo Community Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Siboga Nyamawa Community Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Jagir Singh Primary School water Project
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2006
- action
- Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Nyangeta Police Post Water Project
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2008
- action
- Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 150,000
- estimate
- Ksh 150,000
Jacob Ombara Nursery School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 145,000
- estimate
- Ksh 70,000
Kambaria Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 140,000
- estimate
- Ksh 140,000
Masogo Cattle Dip
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Dip Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 136,667
- estimate
- Ksh 80,000
Livestock{Catle Dip}
- location
-
Koru
(in Muhoroni)
- year first funded
- 2006
- action
- Construction Of Cattle Dip
- output
- -
- implementation status
- Complete
- total cost
- Ksh 130,000
- estimate
- Ksh 130,000
Tree Planting
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2004
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 112,695
- estimate
- Ksh 112,695
Tree Planting
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2004
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 112,695
- estimate
- Ksh 112,695
Amilo Cattle Dip
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Dip Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 110,000
- estimate
- Ksh 60,000
Tree Planting
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2004
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 100,130
- estimate
- Ksh 90,130
Jaramogi Oginga Odinga Secondary School Electrification
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2008
- action
- School Electrification
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kamarawa Water Project
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2005
- action
- Laying Of Pipes
- output
- -
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Ngere Kamarawa Nursery
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- Classroom Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 100,000
- estimate
- Ksh 0
Ng'Eny Secondary School Footbridge
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2008
- action
- Footbridge Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
God Nyithindo Primary School Foot Bridge
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2008
- action
- Footbridge Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Owee Apida Nursery School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Rapogi Nursery
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2005
- action
- Classroom Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Chiefs Office Construction
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2006
- action
- Office Rehabilitation
- output
- -
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kibigori Secondary School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2008
- action
- Purchase Of Laboratory Equipment
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kibigori Secondary School Electrification
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2008
- action
- School Electrification
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Mwai Abiero Secondary School Electrification
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2008
- action
- School Electrification
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Bicycyle Taxi Waiting Shed Point -C/ Round Abount
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2009
- action
- 2 Sheds Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
D's House
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2004
- action
- House Constrution
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Ogwodo Primary School foot Bridge
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Foot Bridge Constrution
- output
- -
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Rangombe Primary School Drainage Ditch
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Ditch Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kunya Nursery School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Abwao Foot Bridge
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Foot Bridge
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Mumbo Nursery School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Siala Nursery School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Abwao Nursery School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Bondo Nursery School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kamrika Nursery School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Komieri Water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Joy Nursery School
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
School Desks At Kibos P Pr
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2006
- action
- Purchase Of Desks
- output
- -
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kibos School Blind
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2007
- action
- Purchase Of Brail Equip
- output
- -
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Muhoroni Youth
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2006
- action
- Field Rehabilitation
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 50,000
Agriculture
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2007
- action
- Purchase Of Equipment
- output
- -
- implementation status
- Yet To Be Funded
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Cattle Dip Karos
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2007
- action
- Rehabilitation
- output
- -
- implementation status
- Yet To Be Funded
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Cheptuiyet Nursery School
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2008
- action
- Classconsrtuction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Menara Secondary School Electrification
- location
-
Koru
(in Muhoroni)
- year first funded
- 2008
- action
- School Electrification
- output
- -
- implementation status
- Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Okwach Primary School Footbridge
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2008
- action
- Footbridge Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Tamu Water Association
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2009
- action
- Electrification
- output
- -
- implementation status
- To Start
- total cost
- Ksh 100,000
- estimate
- Ksh 0
Makindu Primary School footbridge
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2007
- action
- Footbridge Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Oduwo Primary School water Project
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Mashambani Primary School Water Project
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Lwala Primary School water Project
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Well Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Achego Girls Electrification
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2008
- action
- School Electrification
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Songor Secondary School Electrification
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2008
- action
- School Electrification
- output
- -
- implementation status
- On Going
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Holo Nursery School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 90,000
- estimate
- Ksh 90,000
Nyang Nursery School
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 90,000
- estimate
- Ksh 90,000
Saoset BNursery School
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 90,000
- estimate
- Ksh 90,000
Olasi Nursery School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 80,000
- estimate
- Ksh 80,000
Nyakoko Primary School Culvert
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Culvet Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 80,000
- estimate
- Ksh 80,000
Nyakoko Primary School water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Tank Instalation
- output
- -
- implementation status
- Complete
- total cost
- Ksh 80,000
- estimate
- Ksh 80,000
Chiefs Office Construction
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Office Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 80,000
- estimate
- Ksh 80,000
Kibuon Nursery School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 80,000
- estimate
- Ksh 80,000
Kipchorian Water Project
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2009
- action
- Well Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 75,000
- estimate
- Ksh 75,000
Medicinal Drugs
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2003
- action
- Supply Of Drugs
- output
- -
- implementation status
- Complete
- total cost
- Ksh 70,000
- estimate
- Ksh 70,000
Yago Nursery School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 70,000
- estimate
- Ksh 70,000
Lailai Water Project
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2008
- action
- Borehole Construction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 70,000
- estimate
- Ksh 70,000
Wambi Primary School water Project
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2006
- action
- Well Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 70,000
- estimate
- Ksh 70,000
Tree Planting
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2004
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 64,275
- estimate
- Ksh 64,275
Wagunga Obago Nursery
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 60,000
- estimate
- Ksh 60,000
Odiyo Wange Nursery School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 60,000
- estimate
- Ksh 60,000
Sibuor Ochoria Nursery School
- location
-
Koru
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 60,000
- estimate
- Ksh 60,000
Mibasi Nursery School
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 60,000
- estimate
- Ksh 60,000
Tree Planting
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2004
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 53,420
- estimate
- Ksh 53,420
Bicycle Taxi Waiting Shed
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Waiting Shed Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Koru Muungano Market Enrp
- location
-
Koru
(in Muhoroni)
- year first funded
- 2007
- action
- Market Rehabilitation
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Oyani Primary School foot Bridge
- location
-
Koru
(in Muhoroni)
- year first funded
- 2007
- action
- Footbridge Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Kagai Nursery School
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Kipchorian Nursery
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Kambi Awendo Nursery
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2007
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Desks
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2007
- action
- Purchase Of Desks
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Kipchui Nursery
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Saoset Nuersry
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Muhoroni Police Post Electrification
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2009
- action
- Electrification
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Bicycle/Matatu Waiting Shed Point At Mhr Stage
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2009
- action
- Shed Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Bicycle Taxi Waiting/Picking Sheds At Orego
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2008
- action
- Waiting Shed Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Agroforestry- Orego Tn
- location
-
God Nyithindo
(in Muhoroni)
- year first funded
- 2007
- action
- Tree Nursery Management
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Lwala Primary School footbridge
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2007
- action
- Footbridge Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Oduwo Nursery School
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2006
- action
- Classroom Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Bicycle Taxi Waiting Shed Point At Achego
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2009
- action
- Shed Construction
- output
- -
- implementation status
- To Start
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Student Lockers
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2007
- action
- Purchasechairs/Lockers
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Bicycle Taxi Waiting Shed Point
- location
-
Koru
(in Muhoroni)
- year first funded
- 2009
- action
- Shed Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Bicycle Taxi Waiting Sheds At Kibigori Mrk Centre
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2008
- action
- Waiting Shed Construction
- output
- -
- implementation status
- To Be Funded
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Kibigori Railways Primary School Footbridge
- location
-
Chemelil
(in Muhoroni)
- year first funded
- 2007
- action
- Footbridge Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
St. Benedict Nyangoma Secondary School Electrification
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2008
- action
- School Electrification
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Ngere Kagoro Secondary School Electrification
- location
-
Nyangoma
(in Muhoroni)
- year first funded
- 2008
- action
- School Electrification
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Wambi Primary School footbridge
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2007
- action
- Construction of Wooden Bridge
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Bicycle Taxi Shed At Masogo
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Repair Works
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Bicycle Taxi Shed At Kasongo
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Shed Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Olik Oliero Primary School Culvert
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Culvet Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Bicycle Taxi Waiting Shed In Miwani Estate
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2008
- action
- Shed Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
MtNursery School Miwani
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2009
- action
- Desks
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Milimani Nursery School
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2009
- action
- Desks
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Miwani Staff Quarters Nursery School
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2009
- action
- Desks
- output
- -
- implementation status
- On Going
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000
Tree Planting
- location
-
Miwani
(in Muhoroni)
- year first funded
- 2004
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 47,993
- estimate
- Ksh 47,993
Tree Planting Schools
- location
-
Koru
(in Muhoroni)
- year first funded
- 2004
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 47,992
- estimate
- Ksh 47,992
Achego Ap Line Electrification
- location
-
Tamu
(in Muhoroni)
- year first funded
- 2009
- action
- Electrification
- output
- -
- implementation status
- To Start
- total cost
- Ksh 40,000
- estimate
- Ksh 40,000
Nyakoko Primary School Toilet
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Toilet Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 30,000
- estimate
- Ksh 30,000
Kunya Nursery School Toilet
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Toilet Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 30,000
- estimate
- Ksh 30,000
Amilo Primary School Footbridge
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Foot Bridge Constrution
- output
- -
- implementation status
- Complete
- total cost
- Ksh 30,000
- estimate
- Ksh 30,000
Omanyi Primary School Foot Bridge
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Foot Bridge construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 30,000
- estimate
- Ksh 30,000
Tree Planting
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2004
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 27,138
- estimate
- Ksh 27,138
Chief's Office Furniture
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2008
- action
- Purchase Of Furniture
- output
- -
- implementation status
- Complete
- total cost
- Ksh 25,000
- estimate
- Ksh 10,000
Sanitary Facility At Chief's Office
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2003
- action
- Pit Latrine Construction
- output
- -
- implementation status
- Complete
- total cost
- Ksh 25,000
- estimate
- Ksh 25,000
Tree Planting
- location
-
Muhoroni
(in Muhoroni)
- year first funded
- 2004
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 21,283
- estimate
- Ksh 21,283
Omanyi Nursery School
- location
-
North Eastkano
(in Muhoroni)
- year first funded
- 2009
- action
- Construction
- output
- -
- implementation status
- On Going
- total cost
- Ksh 20,000
- estimate
- Ksh 20,000
St. Augustine Kandege Secondary School Tree Planting
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2008
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 5,000
- estimate
- Ksh 5,000
Homa Lime Primary School Tree Planting
- location
-
Fort Ternan
(in Muhoroni)
- year first funded
- 2008
- action
- Planting Of Trees
- output
- -
- implementation status
- Complete
- total cost
- Ksh 5,000
- estimate