The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
    It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
    It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
    
    
        
            
            Magare Secondary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom & Lab Office Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 4,560,000
 
                - estimate
 
                    - Ksh 3,350,000
 
            
         
    
        
            
            Nyangoma Secondary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Lab & Lib Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 4,410,000
 
                - estimate
 
                    - Ksh 3,800,000
 
            
         
    
        
            
            Mariwa Secondary School
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 4,200,000
 
                - estimate
 
                    - Ksh 3,600,000
 
            
         
    
        
            
            Menara Secondary School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Lab&Dom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 4,200,000
 
                - estimate
 
                    - Ksh 3,700,000
 
            
         
    
        
            
            Oduwo Secondary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Class/Adm/Lab Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 4,100,000
 
                - estimate
 
                    - Ksh 3,600,000
 
            
         
    
        
            
            Koru Clinic
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Clinic & Staff House Bldg Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 3,295,000
 
                - estimate
 
                    - Ksh 3,035,000
 
            
         
    
        
            
            Ogen Secondary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 3,100,000
 
                - estimate
 
                    - Ksh 2,500,000
 
            
         
    
        
            
            Olik Oliero Secondary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,750,000
 
                - estimate
 
                    - Ksh 1,300,000
 
            
         
    
        
            
            Oginga Odinga Secondary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom & Admin Block Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,750,000
 
                - estimate
 
                    - Ksh 2,000,000
 
            
         
    
        
            
            Soghor Secondary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,700,000
 
                - estimate
 
                    - Ksh 2,400,000
 
            
         
    
        
            
            Ngeny' Secondary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,695,000
 
                - estimate
 
                    - Ksh 2,000,000
 
            
         
    
        
            
            God Abuoro Secondary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom & Admin Block Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,600,000
 
                - estimate
 
                    - Ksh 2,000,000
 
            
         
    
        
            
            Ombeyi Secondary School
            
            
                - location
 
                    - 
                        Ombeyi North
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,580,000
 
                - estimate
 
                    - Ksh 2,180,000
 
            
         
    
        
            
            Nyangore Footbridge
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Bridge Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 2,565,000
 
                - estimate
 
                    - Ksh 2,565,000
 
            
         
    
        
            
            Kibigori Secondary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,550,000
 
                - estimate
 
                    - Ksh 1,950,000
 
            
         
    
        
            
            Muhoroni Secondary School
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Multipurpose Hall Cons
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,480,000
 
                - estimate
 
                    - Ksh 2,180,000
 
            
         
    
        
            
            Ngere Kagoro Secondary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Admin. Block Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,475,000
 
                - estimate
 
                    - Ksh 2,080,000
 
            
         
    
        
            
            Fort Tenan Health Clinic
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Maternity Ward & Placenta Pit Const
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,450,000
 
                - estimate
 
                    - Ksh 2,150,000
 
            
         
    
        
            
            Miwani Secondary School
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Multipurp Hall Cons
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,380,000
 
                - estimate
 
                    - Ksh 2,080,000
 
            
         
    
        
            
            Koru Secondary School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Dom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 2,380,000
 
                - estimate
 
                    - Ksh 2,080,000
 
            
         
    
        
            
            Nyakoko Secondary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Library Constuction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,380,000
 
                - estimate
 
                    - Ksh 2,080,000
 
            
         
    
        
            
            Township Primary School
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,366,000
 
                - estimate
 
                    - Ksh 1,966,000
 
            
         
    
        
            
            St. Augustine Kandege Secondary School
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Staff House, Dom, Class, Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,280,000
 
                - estimate
 
                    - Ksh 1,980,000
 
            
         
    
        
            
            Achego Secondary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,280,000
 
                - estimate
 
                    - Ksh 1,980,000
 
            
         
    
        
            
            Our Queen Of Peace Secondary School
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 2,050,000
 
                - estimate
 
                    - Ksh 1,300,000
 
            
         
    
        
            
            Ruke Primary School
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,991,000
 
                - estimate
 
                    - Ksh 1,691,000
 
            
         
    
        
            
            Cappuchin Franciscan Masogo Girls Secondary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Lockers/Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,700,000
 
                - estimate
 
                    - Ksh 1,700,000
 
            
         
    
        
            
            Miwani West Water Project
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Purchase And Instalation Of Water Pump
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,550,000
 
                - estimate
 
                    - Ksh 1,550,000
 
            
         
    
        
            
            Mutuala Primary School
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,541,000
 
                - estimate
 
                    - Ksh 1,241,000
 
            
         
    
        
            
            Kipturi Primary School
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,350,000
 
                - estimate
 
                    - Ksh 1,100,000
 
            
         
    
        
            
            Tamu Health Centre
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Staff House/ Water/Electric
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,275,000
 
                - estimate
 
                    - Ksh 700,000
 
            
         
    
        
            
            Jaber Primary School
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,250,000
 
                - estimate
 
                    - Ksh 1,050,000
 
            
         
    
        
            
            Tonde Primary School
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,250,000
 
                - estimate
 
                    - Ksh 1,050,000
 
            
         
    
        
            
            Nyangoma Water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Borehole Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,150,000
 
                - estimate
 
                    - Ksh 700,000
 
            
         
    
        
            
            Nyando Primary School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,025,000
 
                - estimate
 
                    - Ksh 735,000
 
            
         
    
        
            
            Muhoroni District Headquarter
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 1,000,000
 
                - estimate
 
                    - Ksh 1,000,000
 
            
         
    
        
            
            Gul Primary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,000,000
 
                - estimate
 
                    - Ksh 850,000
 
            
         
    
        
            
            Muhoroni Factory Primary School
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,000,000
 
                - estimate
 
                    - Ksh 800,000
 
            
         
    
        
            
            Chiefs Office
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Office Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,000,000
 
                - estimate
 
                    - Ksh 950,000
 
            
         
    
        
            
            Archbishop Okoth College Of Technology
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Renovation /Extention/ Equipment
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 1,000,000
 
                - estimate
 
                    - Ksh 500,000
 
            
         
    
        
            
            Soghor Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 971,430
 
                - estimate
 
                    - Ksh 721,430
 
            
         
    
        
            
            Saoset Water Project
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Borehole Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 930,000
 
                - estimate
 
                    - Ksh 700,000
 
            
         
    
        
            
            Miwani Section Iii Primary School
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 925,000
 
                - estimate
 
                    - Ksh 675,000
 
            
         
    
        
            
            Oroba Primary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 890,000
 
                - estimate
 
                    - Ksh 700,000
 
            
         
    
        
            
            Kisure Primary School
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 800,000
 
                - estimate
 
                    - Ksh 600,000
 
            
         
    
        
            
            Koru Township Primary School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 790,000
 
                - estimate
 
                    - Ksh 790,000
 
            
         
    
        
            
            Karunga Primary School
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 750,000
 
                - estimate
 
                    - Ksh 650,000
 
            
         
    
        
            
            Nyakoko Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 737,000
 
                - estimate
 
                    - Ksh 562,000
 
            
         
    
        
            
            Kibigori Railways Primary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 725,000
 
                - estimate
 
                    - Ksh 625,000
 
            
         
    
        
            
            School Desks
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Supply Of Desks
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 720,000
 
                - estimate
 
                    - Ksh 720,000
 
            
         
    
        
            
            Kibigori Primary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 705,000
 
                - estimate
 
                    - Ksh 605,000
 
            
         
    
        
            
            Ogwedhi Primary School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Land Purchase,Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 700,000
 
                - estimate
 
                    - Ksh 600,000
 
            
         
    
        
            
            Makindu Dispensary
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Marternity Construction &Beds
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 700,000
 
                - estimate
 
                    - Ksh 400,000
 
            
         
    
        
            
            Nyarenda Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 700,000
 
                - estimate
 
                    - Ksh 400,000
 
            
         
    
        
            
            Cheptuiyet Primary School
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 690,000
 
                - estimate
 
                    - Ksh 490,000
 
            
         
    
        
            
            Kipchoria Primary School
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 690,000
 
                - estimate
 
                    - Ksh 490,000
 
            
         
    
        
            
            Miwani Estate Health Clinic
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Dispensary Constr, Furniture & Water Sink
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 675,000
 
                - estimate
 
                    - Ksh 675,000
 
            
         
    
        
            
            Ngere Kagoro Police Post
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Office Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 650,000
 
                - estimate
 
                    - Ksh 500,000
 
            
         
    
        
            
            Nyatao Secondary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction/Lab Equipments
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 650,000
 
                - estimate
 
                    - Ksh 650,000
 
            
         
    
        
            
            God Nyithindo Primary School Electrification
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 650,000
 
                - estimate
 
                    - Ksh 550,000
 
            
         
    
        
            
            Osembe Primary School
            
            
                - location
 
                    - 
                        Ombeyi South
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 640,000
 
                - estimate
 
                    - Ksh 540,000
 
            
         
    
        
            
            Homalimekipsamwe Primary School
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 640,000
 
                - estimate
 
                    - Ksh 540,000
 
            
         
    
        
            
            Mikiria Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 635,000
 
                - estimate
 
                    - Ksh 360,000
 
            
         
    
        
            
            Kware Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 621,430
 
                - estimate
 
                    - Ksh 421,430
 
            
         
    
        
            
            Obago Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 616,663
 
                - estimate
 
                    - Ksh 426,363
 
            
         
    
        
            
            Masara Primary School
            
            
                - location
 
                    - 
                        Ombeyi South
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 610,000
 
                - estimate
 
                    - Ksh 410,000
 
            
         
    
        
            
            Chiefs Office Construction
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Office Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 600,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Magare Community Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Pipes &Tank Installation
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 600,000
 
                - estimate
 
                    - Ksh 600,000
 
            
         
    
        
            
            Nyakungru Dispensary
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Dispensary Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 600,000
 
                - estimate
 
                    - Ksh 450,000
 
            
         
    
        
            
            Nyangore Primary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 600,000
 
                - estimate
 
                    - Ksh 450,000
 
            
         
    
        
            
            Nyalenya Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 600,000
 
                - estimate
 
                    - Ksh 425,000
 
            
         
    
        
            
            Kandege Primary School
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 590,000
 
                - estimate
 
                    - Ksh 390,000
 
            
         
    
        
            
            Tamu Central Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 575,000
 
                - estimate
 
                    - Ksh 450,000
 
            
         
    
        
            
            Orenge Primary School
            
            
                - location
 
                    - 
                        Ombeyi North
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 570,000
 
                - estimate
 
                    - Ksh 370,000
 
            
         
    
        
            
            Mitando Primary School
            
            
                - location
 
                    - 
                        Ombeyi South
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 560,000
 
                - estimate
 
                    - Ksh 410,000
 
            
         
    
        
            
            Nyangoto Primary School
            
            
                - location
 
                    - 
                        Ombeyi South
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 560,000
 
                - estimate
 
                    - Ksh 410,000
 
            
         
    
        
            
            Kigoche Primary School
            
            
                - location
 
                    - 
                        Ombeyi South
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 560,000
 
                - estimate
 
                    - Ksh 410,000
 
            
         
    
        
            
            Oduwo Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Toilet/Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 555,000
 
                - estimate
 
                    - Ksh 380,000
 
            
         
    
        
            
            Ogen Dispensary
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Staff House Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 550,000
 
                - estimate
 
                    - Ksh 400,000
 
            
         
    
        
            
            Cheptuiyet Dispensary
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Dispensary Construct.
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 550,000
 
                - estimate
 
                    - Ksh 350,000
 
            
         
    
        
            
            Muhoroni Hospital Water
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Supply Of Water
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 550,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Muhoroni Water Association
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Water Supply
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 550,000
 
                - estimate
 
                    - Ksh 550,000
 
            
         
    
        
            
            Nyangoma Health Centre
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Construction Of Maternity Wing
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 550,000
 
                - estimate
 
                    - Ksh 400,000
 
            
         
    
        
            
            Chemelil Market Dispensary
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Construction Of Maternity Wing
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 550,000
 
                - estimate
 
                    - Ksh 400,000
 
            
         
    
        
            
            Saoset Primary School
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 540,000
 
                - estimate
 
                    - Ksh 540,000
 
            
         
    
        
            
            Nyatao Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 539,000
 
                - estimate
 
                    - Ksh 389,000
 
            
         
    
        
            
            Kiliti Primary School
            
            
                - location
 
                    - 
                        Ombeyi North
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 520,000
 
                - estimate
 
                    - Ksh 370,000
 
            
         
    
        
            
            Ombeyi Primary School
            
            
                - location
 
                    - 
                        Ombeyi North
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 520,000
 
                - estimate
 
                    - Ksh 370,000
 
            
         
    
        
            
            Obiayo Primary School
            
            
                - location
 
                    - 
                        Ombeyi South
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 510,000
 
                - estimate
 
                    - Ksh 510,000
 
            
         
    
        
            
            Wagai Primary School
            
            
                - location
 
                    - 
                        Ombeyi South
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 510,000
 
                - estimate
 
                    - Ksh 510,000
 
            
         
    
        
            
            Bacho Primary School
            
            
                - location
 
                    - 
                        Ombeyi South
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 510,000
 
                - estimate
 
                    - Ksh 510,000
 
            
         
    
        
            
            Kibos Prison Primary School
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 500,000
 
                - estimate
 
                    - Ksh 500,000
 
            
         
    
        
            
            Miwani Division Resource Centre
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 500,000
 
                - estimate
 
                    - Ksh 0
 
            
         
    
        
            
            Round About Water Project
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Pipe Costruction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 500,000
 
                - estimate
 
                    - Ksh 500,000
 
            
         
    
        
            
            Nyangoma Village Polytechnic
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Renovation And Equipment
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 500,000
 
                - estimate
 
                    - Ksh 500,000
 
            
         
    
        
            
            Nyangoma Water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Pipe Laying
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 500,000
 
                - estimate
 
                    - Ksh 500,000
 
            
         
    
        
            
            Miwani Estate Primary School
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 500,000
 
                - estimate
 
                    - Ksh 400,000
 
            
         
    
        
            
            Masogo/Waware Youth Polytechnic
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Class/Adm Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 500,000
 
                - estimate
 
                    - Ksh 500,000
 
            
         
    
        
            
            Ngula Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 500,000
 
                - estimate
 
                    - Ksh 500,000
 
            
         
    
        
            
            Minyange Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 490,000
 
                - estimate
 
                    - Ksh 390,000
 
            
         
    
        
            
            Ramula Primary School
            
            
                - location
 
                    - 
                        Ombeyi North
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 470,000
 
                - estimate
 
                    - Ksh 370,000
 
            
         
    
        
            
            Thurbie Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 465,000
 
                - estimate
 
                    - Ksh 315,000
 
            
         
    
        
            
            Ogilo Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 459,419
 
                - estimate
 
                    - Ksh 346,363
 
            
         
    
        
            
            Kibigori Police Post
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Ap Line Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 450,000
 
                - estimate
 
                    - Ksh 450,000
 
            
         
    
        
            
            Jagir Singh Primary School
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 450,000
 
                - estimate
 
                    - Ksh 350,000
 
            
         
    
        
            
            Ngere Kagoro Water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Pipes Installation
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 450,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Education Improvement
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 450,000
 
                - estimate
 
                    - Ksh 450,000
 
            
         
    
        
            
            Ogwodo Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 447,363
 
                - estimate
 
                    - Ksh 364,363
 
            
         
    
        
            
            Yago Dispensary
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Dispensary Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 446,430
 
                - estimate
 
                    - Ksh 321,430
 
            
         
    
        
            
            Orago Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 445,000
 
                - estimate
 
                    - Ksh 295,000
 
            
         
    
        
            
            Kolang' Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 440,000
 
                - estimate
 
                    - Ksh 290,000
 
            
         
    
        
            
            Oneno Nam Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 435,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Sanda Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 431,563
 
                - estimate
 
                    - Ksh 336,363
 
            
         
    
        
            
            Pawteng Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 429,000
 
                - estimate
 
                    - Ksh 279,000
 
            
         
    
        
            
            Sangayo Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 426,663
 
                - estimate
 
                    - Ksh 336,363
 
            
         
    
        
            
            Ngeny' Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 425,000
 
                - estimate
 
                    - Ksh 425,000
 
            
         
    
        
            
            Soghor Dispensary
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Dispensary Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 421,430
 
                - estimate
 
                    - Ksh 221,430
 
            
         
    
        
            
            Lwala Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 421,430
 
                - estimate
 
                    - Ksh 421,430
 
            
         
    
        
            
            Mashambani Dispensary
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Dispensary Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 421,420
 
                - estimate
 
                    - Ksh 221,420
 
            
         
    
        
            
            Okwach Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 420,000
 
                - estimate
 
                    - Ksh 320,000
 
            
         
    
        
            
            Magare Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 416,363
 
                - estimate
 
                    - Ksh 286,363
 
            
         
    
        
            
            Wambi Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 409,419
 
                - estimate
 
                    - Ksh 296,363
 
            
         
    
        
            
            Ngiti Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 409,419
 
                - estimate
 
                    - Ksh 296,363
 
            
         
    
        
            
            Chiefs Office Extension
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Extension Of Chief'S Office
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 402,000
 
                - estimate
 
                    - Ksh 202,000
 
            
         
    
        
            
            Cheptuiyet Nursery Schoolwater Project
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 400,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            God Nyithindo Primary School
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Fencing
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 400,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Kibos School For The Blind
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 400,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Kibigori Dispensary
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Clinic Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 400,000
 
                - estimate
 
                    - Ksh 400,000
 
            
         
    
        
            
            God Ruke Primary School Water Project
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Borehole Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 400,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Tamu Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 396,430
 
                - estimate
 
                    - Ksh 221,430
 
            
         
    
        
            
            Omanyi Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 390,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Nyakungru Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 382,363
 
                - estimate
 
                    - Ksh 299,363
 
            
         
    
        
            
            Olik Oliero Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 375,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Osiri Migere Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 374,000
 
                - estimate
 
                    - Ksh 374,000
 
            
         
    
        
            
            Milenye Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 370,000
 
                - estimate
 
                    - Ksh 370,000
 
            
         
    
        
            
            Rangombe Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 370,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Educational Improvement
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Lab& Comp Equip
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 360,000
 
                - estimate
 
                    - Ksh 360,000
 
            
         
    
        
            
            Oyani Primary School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 360,000
 
                - estimate
 
                    - Ksh 360,000
 
            
         
    
        
            
            Kowawa Police Post
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Office Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 350,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Mashambani Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 350,000
 
                - estimate
 
                    - Ksh 250,000
 
            
         
    
        
            
            Tonde Water Project
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 350,000
 
                - estimate
 
                    - Ksh 350,000
 
            
         
    
        
            
            Kopere Police Post
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Police Post Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 350,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Chemelil B Primary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 350,000
 
                - estimate
 
                    - Ksh 350,000
 
            
         
    
        
            
            Assistant Chiefs' Office
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Office Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 350,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Purchase Of Land Ongalo Primary School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Land Purchase
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Reallocated
 
                - total cost
 
                    - Ksh 350,000
 
                - estimate
 
                    - Ksh 350,000
 
            
         
    
        
            
            Nyakoko Stream Drainage
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Desiltation
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 330,000
 
                - estimate
 
                    - Ksh 130,000
 
            
         
    
        
            
            Osengteti Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 300,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Ngeny Special School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - D. Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 300,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Mariwa Secondary School Water Project
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 300,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Yago Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 300,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Makindu Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 300,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            God Abuoro Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 300,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Educational Improvement
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Lab Equip
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 300,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Nyakoko Oroba Drainage
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Flood Control
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 300,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Kabonyo Village Miwani West
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Transformer
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 300,000
 
                - estimate
 
                    - Ksh 300,000
 
            
         
    
        
            
            Kabar West Catlle Dip Land Purchase
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Rehabilitation
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 296,000
 
                - estimate
 
                    - Ksh 296,000
 
            
         
    
        
            
            Wuok Nursery /Primary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 295,000
 
                - estimate
 
                    - Ksh 145,000
 
            
         
    
        
            
            Ang'Ogo Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 295,000
 
                - estimate
 
                    - Ksh 295,000
 
            
         
    
        
            
            Amilo Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 290,000
 
                - estimate
 
                    - Ksh 220,000
 
            
         
    
        
            
            Kodhiambo Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 286,000
 
                - estimate
 
                    - Ksh 236,000
 
            
         
    
        
            
            Gatundu Village Nursery/Pri
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 270,000
 
                - estimate
 
                    - Ksh 70,000
 
            
         
    
        
            
            St. Johns' Primary School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Desks/Toilet Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 270,000
 
                - estimate
 
                    - Ksh 70,000
 
            
         
    
        
            
            Ogwedhi Primary School foot Bridge
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Footbridge Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 250,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Achego Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 250,000
 
                - estimate
 
                    - Ksh 250,000
 
            
         
    
        
            
            Muhoroni Primary School
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Fencing
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 250,000
 
                - estimate
 
                    - Ksh 250,000
 
            
         
    
        
            
            Educational Improvement
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Laboratory Equipping
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 250,000
 
                - estimate
 
                    - Ksh 250,000
 
            
         
    
        
            
            Mdemp - Kibigori Settlement
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Silt/Veg Removal
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 250,000
 
                - estimate
 
                    - Ksh 250,000
 
            
         
    
        
            
            Kibigori Muslim Community School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 250,000
 
                - estimate
 
                    - Ksh 250,000
 
            
         
    
        
            
            Ogen Primary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 250,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Ngere Kagoro Cattle Dip
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Renovation
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 250,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Sanitary Facilities In Primary School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Pit Latrine Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 245,000
 
                - estimate
 
                    - Ksh 245,000
 
            
         
    
        
            
            Kasongo Health Centre
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Toilet Facility/Disp Bldg
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 235,000
 
                - estimate
 
                    - Ksh 235,000
 
            
         
    
        
            
            Rapogi Community Water Project
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well Contruction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 225,000
 
                - estimate
 
                    - Ksh 125,000
 
            
         
    
        
            
            Sidho Owee Comwater Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 225,000
 
                - estimate
 
                    - Ksh 225,000
 
            
         
    
        
            
            Nyangore Nursery School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 220,000
 
                - estimate
 
                    - Ksh 70,000
 
            
         
    
        
            
            Makiindu Primary School Water Project
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Simbi Luora Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Holo Community Water Project
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 20,000
 
            
         
    
        
            
            Chief's Office Construction/Elect
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Office Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            St. Claudio Kowiti Primary School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Achego Primary School water Project
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Chiefs Office Construction
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Office Consteruction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Kagai Water Project
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Pipes Installation
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Koru Hospital Generator
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Purchase Of Generator
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Pombo Water Project
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Mdemp-Oroba/Miwani Estate
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Drainage/Veg Removal
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Kibos Nubian Nursery
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Mdemp-Nyakoko/Ogandi
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Drainage Work
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 0
 
            
         
    
        
            
            Mdemp-Sangayo/Obago
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Drainage Work
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 0
 
            
         
    
        
            
            Mdemp-Siala/Abwao
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Drainage Work
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 0
 
            
         
    
        
            
            Sanda Community Irrigation Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Irrigation
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Masogo Health Centre
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Repair Works
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Wuok Primary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Kibigori Cattle Dip
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Dip Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Profayiecho Kibigori Nursery School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Apidi Nursery
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 75,000
 
            
         
    
        
            
            Katuk Community Water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Geno Community Water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Masaka Community Water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Mdemp-Kamagaga/Owee Village
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Silt/Veg Removal
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Chemelil Market Police Post
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - construction Of Police Post Bldn
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 200,000
 
            
         
    
        
            
            Ngere Kagoro Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 200,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Ogen Nursery School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 185,000
 
                - estimate
 
                    - Ksh 75,000
 
            
         
    
        
            
            Desks/Students Lockers
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Purchase Of Lockers/Chairs
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 185,000
 
                - estimate
 
                    - Ksh 185,000
 
            
         
    
        
            
            Nyalelbuch Water Project
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Shalowest Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 175,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Sanda Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 170,000
 
                - estimate
 
                    - Ksh 170,000
 
            
         
    
        
            
            Osiri Migere Primary School Water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 170,000
 
                - estimate
 
                    - Ksh 170,000
 
            
         
    
        
            
            Minyange Primary School water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 170,000
 
                - estimate
 
                    - Ksh 170,000
 
            
         
    
        
            
            Sugarbelt Nursery School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom & Toilet Rehabilitation
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 165,000
 
                - estimate
 
                    - Ksh 165,000
 
            
         
    
        
            
            Ramanda Nursery School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 160,370
 
                - estimate
 
                    - Ksh 60,370
 
            
         
    
        
            
            Oyani Nursery School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 160,000
 
                - estimate
 
                    - Ksh 160,000
 
            
         
    
        
            
            Bondo Community Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Ogen Dispensary Water Project
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Contruction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Menara Primary School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Education Improvement[Menara]
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Lab Equipment
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            St. Augustine Kandege Secondary School Water Project
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Electric Power Kandege
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Purchase Of Generator
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Jua Kali Compound Fence
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Fencing
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Mariwa Primary School
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Education Improvement
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Lab Equipment
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Simbi Luora Primary School Water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            St. Joseph Ngula Primary School Water Proj
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Makindu Dispensary Water Proj
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Okwach Primary School water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Mibasi Community Water
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Nyadundo Primary School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Mikiria Community Water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Lockers And Chairs
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Purchasechairs/Lockers
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Siala Community Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well & Pump construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Ogilo Primary School water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well & Pump construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Ngiti Primary School water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well & Pump Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Waware Primary School water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well & Pump Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Kaktai Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well & Pump Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Ramanda Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well & Pump Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Ogwodo Primary School water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well & Pump Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Wagunga Obago Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Well & Pump Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Sanitary Facility
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Public Toilet Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Abwao Community Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Okiro Community Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            North Kamrika Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Kunya Community Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Mumbo Community Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Siboga Nyamawa Community Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Jagir Singh Primary School water Project
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Nyangeta Police Post Water Project
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 150,000
 
                - estimate
 
                    - Ksh 150,000
 
            
         
    
        
            
            Jacob Ombara Nursery School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 145,000
 
                - estimate
 
                    - Ksh 70,000
 
            
         
    
        
            
            Kambaria Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 140,000
 
                - estimate
 
                    - Ksh 140,000
 
            
         
    
        
            
            Masogo Cattle Dip
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Dip Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 136,667
 
                - estimate
 
                    - Ksh 80,000
 
            
         
    
        
            
            Livestock{Catle Dip}
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Construction Of Cattle Dip
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 130,000
 
                - estimate
 
                    - Ksh 130,000
 
            
         
    
        
            
            Tree Planting
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 112,695
 
                - estimate
 
                    - Ksh 112,695
 
            
         
    
        
            
            Tree Planting
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 112,695
 
                - estimate
 
                    - Ksh 112,695
 
            
         
    
        
            
            Amilo Cattle Dip
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Dip Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 110,000
 
                - estimate
 
                    - Ksh 60,000
 
            
         
    
        
            
            Tree Planting
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 100,130
 
                - estimate
 
                    - Ksh 90,130
 
            
         
    
        
            
            Jaramogi Oginga Odinga Secondary School Electrification
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - School Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Kamarawa Water Project
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Laying Of Pipes
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Ngere Kamarawa Nursery
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 0
 
            
         
    
        
            
            Ng'Eny Secondary School Footbridge
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Footbridge Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            God Nyithindo Primary School Foot Bridge
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Footbridge Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Owee Apida Nursery School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Rapogi Nursery
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2005
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Chiefs Office Construction
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Office Rehabilitation
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Kibigori Secondary School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Purchase Of Laboratory Equipment
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Kibigori Secondary School Electrification
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - School Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Mwai Abiero Secondary School Electrification
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - School Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Bicycyle Taxi Waiting Shed Point -C/ Round Abount
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - 2 Sheds Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            D's House
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - House Constrution
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Ogwodo Primary School foot Bridge
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Foot Bridge Constrution
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Rangombe Primary School Drainage Ditch
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Ditch Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Kunya Nursery School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Abwao Foot Bridge
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Foot Bridge
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Mumbo Nursery School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Siala Nursery School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Abwao Nursery School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Bondo Nursery School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Kamrika Nursery School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Komieri Water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Joy Nursery School
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            School Desks At Kibos P Pr
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Purchase Of Desks
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Kibos School Blind
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Purchase Of Brail Equip
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Muhoroni Youth
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Field Rehabilitation
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Agriculture
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Purchase Of Equipment
 
                - output
 
                    - -
 
                - implementation status
 
                    - Yet To Be Funded
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Cattle Dip Karos
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Rehabilitation
 
                - output
 
                    - -
 
                - implementation status
 
                    - Yet To Be Funded
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Cheptuiyet Nursery School
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Classconsrtuction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Menara Secondary School Electrification
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - School Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Okwach Primary School Footbridge
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Footbridge Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Tamu Water Association
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 0
 
            
         
    
        
            
            Makindu Primary School footbridge
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Footbridge Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Oduwo Primary School water Project
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Mashambani Primary School Water Project
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Lwala Primary School water Project
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Achego Girls Electrification
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - School Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Songor Secondary School Electrification
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - School Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 100,000
 
                - estimate
 
                    - Ksh 100,000
 
            
         
    
        
            
            Holo Nursery School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 90,000
 
                - estimate
 
                    - Ksh 90,000
 
            
         
    
        
            
            Nyang Nursery School
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 90,000
 
                - estimate
 
                    - Ksh 90,000
 
            
         
    
        
            
            Saoset BNursery School
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 90,000
 
                - estimate
 
                    - Ksh 90,000
 
            
         
    
        
            
            Olasi Nursery School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 80,000
 
                - estimate
 
                    - Ksh 80,000
 
            
         
    
        
            
            Nyakoko Primary School Culvert
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Culvet Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 80,000
 
                - estimate
 
                    - Ksh 80,000
 
            
         
    
        
            
            Nyakoko Primary School water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Tank Instalation
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 80,000
 
                - estimate
 
                    - Ksh 80,000
 
            
         
    
        
            
            Chiefs Office Construction
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Office Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 80,000
 
                - estimate
 
                    - Ksh 80,000
 
            
         
    
        
            
            Kibuon Nursery School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 80,000
 
                - estimate
 
                    - Ksh 80,000
 
            
         
    
        
            
            Kipchorian Water Project
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 75,000
 
                - estimate
 
                    - Ksh 75,000
 
            
         
    
        
            
            Medicinal Drugs
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Supply Of Drugs
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 70,000
 
                - estimate
 
                    - Ksh 70,000
 
            
         
    
        
            
            Yago Nursery School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 70,000
 
                - estimate
 
                    - Ksh 70,000
 
            
         
    
        
            
            Lailai Water Project
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Borehole Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 70,000
 
                - estimate
 
                    - Ksh 70,000
 
            
         
    
        
            
            Wambi Primary School water Project
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Well Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 70,000
 
                - estimate
 
                    - Ksh 70,000
 
            
         
    
        
            
            Tree Planting
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 64,275
 
                - estimate
 
                    - Ksh 64,275
 
            
         
    
        
            
            Wagunga Obago Nursery
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 60,000
 
                - estimate
 
                    - Ksh 60,000
 
            
         
    
        
            
            Odiyo Wange Nursery School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 60,000
 
                - estimate
 
                    - Ksh 60,000
 
            
         
    
        
            
            Sibuor Ochoria Nursery School
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 60,000
 
                - estimate
 
                    - Ksh 60,000
 
            
         
    
        
            
            Mibasi Nursery School
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 60,000
 
                - estimate
 
                    - Ksh 60,000
 
            
         
    
        
            
            Tree Planting
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 53,420
 
                - estimate
 
                    - Ksh 53,420
 
            
         
    
        
            
            Bicycle Taxi Waiting Shed
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Waiting Shed Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Koru Muungano Market Enrp
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Market Rehabilitation
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Oyani Primary School foot Bridge
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Footbridge Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Kagai Nursery School
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Kipchorian Nursery
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Kambi Awendo Nursery
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Desks
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Purchase Of Desks
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Kipchui Nursery
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Saoset Nuersry
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Muhoroni Police Post Electrification
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Bicycle/Matatu Waiting Shed Point At Mhr Stage
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Shed Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Bicycle Taxi Waiting/Picking Sheds At Orego
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Waiting Shed Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Agroforestry- Orego Tn
            
            
                - location
 
                    - 
                        God Nyithindo
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Tree Nursery Management
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Lwala Primary School footbridge
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Footbridge Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Oduwo Nursery School
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2006
 
                
                - action
 
                    - Classroom Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Bicycle Taxi Waiting Shed Point At Achego
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Shed Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Student Lockers
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Purchasechairs/Lockers
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Bicycle Taxi Waiting Shed Point
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Shed Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Bicycle Taxi Waiting Sheds At Kibigori Mrk Centre
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Waiting Shed Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Be Funded
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Kibigori Railways Primary School Footbridge
            
            
                - location
 
                    - 
                        Chemelil
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Footbridge Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            St. Benedict Nyangoma Secondary School Electrification
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - School Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Ngere Kagoro Secondary School Electrification
            
            
                - location
 
                    - 
                        Nyangoma
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - School Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Wambi Primary School footbridge
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2007
 
                
                - action
 
                    - Construction of Wooden Bridge
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Bicycle Taxi Shed At Masogo
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Repair Works
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Bicycle Taxi Shed At Kasongo
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Shed Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Olik Oliero Primary School Culvert
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Culvet Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Bicycle Taxi Waiting Shed In Miwani Estate
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Shed Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            MtNursery School Miwani
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Desks
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Milimani Nursery School
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Desks
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Miwani Staff Quarters Nursery School
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Desks
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 50,000
 
                - estimate
 
                    - Ksh 50,000
 
            
         
    
        
            
            Tree Planting
            
            
                - location
 
                    - 
                        Miwani
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 47,993
 
                - estimate
 
                    - Ksh 47,993
 
            
         
    
        
            
            Tree Planting Schools
            
            
                - location
 
                    - 
                        Koru
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 47,992
 
                - estimate
 
                    - Ksh 47,992
 
            
         
    
        
            
            Achego Ap Line Electrification
            
            
                - location
 
                    - 
                        Tamu
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Electrification
 
                - output
 
                    - -
 
                - implementation status
 
                    - To Start
 
                - total cost
 
                    - Ksh 40,000
 
                - estimate
 
                    - Ksh 40,000
 
            
         
    
        
            
            Nyakoko Primary School Toilet
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Toilet Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 30,000
 
                - estimate
 
                    - Ksh 30,000
 
            
         
    
        
            
            Kunya Nursery School Toilet
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Toilet Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 30,000
 
                - estimate
 
                    - Ksh 30,000
 
            
         
    
        
            
            Amilo Primary School Footbridge
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Foot Bridge Constrution
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 30,000
 
                - estimate
 
                    - Ksh 30,000
 
            
         
    
        
            
            Omanyi Primary School Foot Bridge
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Foot Bridge construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 30,000
 
                - estimate
 
                    - Ksh 30,000
 
            
         
    
        
            
            Tree Planting
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 27,138
 
                - estimate
 
                    - Ksh 27,138
 
            
         
    
        
            
            Chief's Office Furniture
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Purchase Of Furniture
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 25,000
 
                - estimate
 
                    - Ksh 10,000
 
            
         
    
        
            
            Sanitary Facility At Chief's Office
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2003
 
                
                - action
 
                    - Pit Latrine Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 25,000
 
                - estimate
 
                    - Ksh 25,000
 
            
         
    
        
            
            Tree Planting
            
            
                - location
 
                    - 
                        Muhoroni
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2004
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 21,283
 
                - estimate
 
                    - Ksh 21,283
 
            
         
    
        
            
            Omanyi Nursery School
            
            
                - location
 
                    - 
                        North Eastkano
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2009
 
                
                - action
 
                    - Construction
 
                - output
 
                    - -
 
                - implementation status
 
                    - On Going
 
                - total cost
 
                    - Ksh 20,000
 
                - estimate
 
                    - Ksh 20,000
 
            
         
    
        
            
            St. Augustine Kandege Secondary School Tree Planting
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 5,000
 
                - estimate
 
                    - Ksh 5,000
 
            
         
    
        
            
            Homa Lime Primary School Tree Planting
            
            
                - location
 
                    - 
                        Fort Ternan
                        (in Muhoroni)
                    
 
                
                - year first funded
 
                    - 2008
 
                
                - action
 
                    - Planting Of Trees
 
                - output
 
                    - -
 
                - implementation status
 
                    - Complete
 
                - total cost
 
                    - Ksh 5,000
 
                - estimate
 
                    - Ksh 5,000