The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.

It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

Projects in North Mugirango Borabu

Kijauri Dispensary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2004
action
Construction of faciltity
output
Provide health services
implementation status
walling
total cost
Ksh 7,600,000
estimate
Ksh 13,074,565

Rionyari- Nyabikomu- Egentubi- Gucha Rd

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2008
action
Road Construction
output
Road
implementation status
Stump removal, bush clearing and levelising done. Laying culverts
total cost
Ksh 2,667,237
estimate
Ksh 3,667,237

Ensakia primary School

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2004
action
Construction of Classrooms electr/installalation
output
Reduction of learning congestion
implementation status
Finishing with plastering and flooring
total cost
Ksh 2,600,000
estimate
Ksh 606,000

Chebilate Water Project

location
Mekenene (in North Mugirango Borabu)
year first funded
2003
action
Construction of piped water
output
Proximity to water
implementation status
Reservoiur tank to construct
total cost
Ksh 2,576,000
estimate
Ksh 2,739,000

AIC Nyabikomu Health Centre

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2003
action
Construction of faciltity
output
Provide health services
implementation status
Completed
total cost
Ksh 2,414,000
estimate
Ksh 3,180,671

St. Joseph Biego secondary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2003
action
Construction of Admin Block and Classrooms(phase 1).
output
improve learning conditions
implementation status
Ground floor on finishing level. Windows, doors,flooring.
total cost
Ksh 2,347,000
estimate
Ksh 3,159,304

Nyamusi Health Center

location
Bokeira (in North Mugirango Borabu)
year first funded
2004
action
Construction of faciltity
output
Provide health services
implementation status
Ceiling, paiting,wiring the remaining part
total cost
Ksh 2,300,000
estimate
Ksh 1,341,120

Riechieri Dispensary

location
Obwari (in North Mugirango Borabu)
year first funded
2003
action
Construction of facility
output
Provide health services
implementation status
completed facility.
total cost
Ksh 2,189,000
estimate
Ksh 2,089,000

Nyakenimo secondary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2004
action
Classrooms, Offices & Teachers' house
output
Reduction of learning congestion
implementation status
Finishing of teacher"s house
total cost
Ksh 2,050,000
estimate
Ksh 1,750,000

Eronge SDA secondary School

location
Esise (in North Mugirango Borabu)
year first funded
2005
action
Construction of lab
output
Improve science subjects
implementation status
Roofing to do
total cost
Ksh 1,917,000
estimate
Ksh 1,842,924

Manga Girls Water Project

location
Esise (in North Mugirango Borabu)
year first funded
2005
action
Construction of water supply system
output
water supply to school
implementation status
drilling of borehole
total cost
Ksh 1,750,000
estimate
Ksh 1,080,000

Nyangoge secondary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2004
action
Lab & Library Construction
output
improve learning conditions
implementation status
walling a storey structure
total cost
Ksh 1,700,000
estimate
Ksh 4,585,343

Endiba secondary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2005
action
Lab and wiring 2 Classrooms
output
Reduction of learning congestion
implementation status
Fittings and Equipment procurement. Classrooms completed and wiring done
total cost
Ksh 1,650,000
estimate
Ksh 1,203,470

Mecheo secondary School

location
Esise (in North Mugirango Borabu)
year first funded
2005
action
dining Hall Construction
output
dining Hall
implementation status
Skeleton done and roofing done.
total cost
Ksh 1,600,000
estimate
Ksh 2,375,000

Ikonge Dispesary

location
Obwari (in North Mugirango Borabu)
year first funded
2004
action
Construction of facility
output
Provide health services
implementation status
Facility completed and in use
total cost
Ksh 1,600,000
estimate
Ksh 1,113,160

Chaina Dispensary

location
Itibo (in North Mugirango Borabu)
year first funded
2004
action
Construction of faciltity
output
Provide health services
implementation status
Finishing with painting and fittings
total cost
Ksh 1,600,000
estimate
Ksh 1,634,080

Isoge/Kineni Water Project

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2006
action
Construction of piped water
output
Proximity to water
implementation status
Piping on
total cost
Ksh 1,512,371
estimate
Ksh 5,456,570

Entono Health Centre

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2003
action
Construction of faciltity
output
Provide health services
implementation status
facility completed. Wiring to do.
total cost
Ksh 1,500,000
estimate
Ksh 1,520,300

Kenyoro Dispensary

location
Itibo (in North Mugirango Borabu)
year first funded
2004
action
Construction of faciltity
output
Provide health services
implementation status
Finishing with palstring, floors,painting and wiring
total cost
Ksh 1,500,000
estimate
Ksh 1,316,820

Riagechiko Bridge

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of bridge
output
Improve communication
implementation status
Finishing
total cost
Ksh 1,500,000
estimate
Ksh 1,138,000

Nyamiranga secondary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2008
action
Twin lab construction
output
Improve science subjects
implementation status
At walling
total cost
Ksh 1,500,000
estimate
Ksh 0

Nyankono Dispensary

location
Kiang'eni (in North Mugirango Borabu)
year first funded
2003
action
Construction of faciltity
output
Provide health services
implementation status
completed facility. Doctor's house need plastering and flooring and ceiling
total cost
Ksh 1,500,000
estimate
Ksh 3,740,500

Mecheo Dispensary

location
Esise (in North Mugirango Borabu)
year first funded
2003
action
Construction of faciltity
output
Health Services
implementation status
Completed and in use
total cost
Ksh 1,414,000
estimate
Ksh 1,931,590

Ntana secondary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2005
action
Textbooks,Tank & electricty
output
provision of enough books,water and lighting
implementation status
Books bought,tak made & Electrical wiring to do
total cost
Ksh 1,400,000
estimate
Ksh 2,767,650

Kineni- Saigangiya Rd

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Road Construction
output
Road
implementation status
Bush clearing, culverting stump removal
total cost
Ksh 1,400,000
estimate
Ksh 5,118,750

Chepngombe Health Centre

location
Esise (in North Mugirango Borabu)
year first funded
2003
action
Construction of Martanity
output
Martanity services
implementation status
Completed and in use
total cost
Ksh 1,394,000
estimate
Ksh 2,980,000

Eronge DEB secondary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2005
action
Lab Construction
output
Improve science subjects
implementation status
Finishing with plastering and flooring and fittings & wiring
total cost
Ksh 1,352,940
estimate
Ksh 5,484,524

Isoge Health Centre

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2004
action
Construction of faciltity
output
Provide health services
implementation status
At slab level
total cost
Ksh 1,300,000
estimate
Ksh 8,692,639

Eronge Board. primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Renovation of burnt dorm
output
To provide accommodation to learners
implementation status
Ongoing
total cost
Ksh 1,300,000
estimate
Ksh 0

Gisage Dispensary

location
Borangi (in North Mugirango Borabu)
year first funded
2003
action
Construction of faciltity
output
Provide health services
implementation status
Completed and in use
total cost
Ksh 1,300,000
estimate
Ksh 1,366,480

Kineni Dispensary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2003
action
Construction of faciltity maternity ward
output
Provide health services
implementation status
complete
total cost
Ksh 1,285,000
estimate
Ksh 1,738,901

Endiba Dispensary

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2005
action
Construction of faciltity
output
Provide health services
implementation status
Completed
total cost
Ksh 1,250,000
estimate
Ksh 1,950,000

St. Mattias Mulumba secondary

location
Mekenene (in North Mugirango Borabu)
year first funded
2007
action
Classroooms construction
output
Reduction of learning congestion
implementation status
Roofing
total cost
Ksh 1,210,588
estimate
Ksh 10,000,000

Mokomoni Dispensary

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2004
action
Construction of faciltity
output
Provide health services
implementation status
complete
total cost
Ksh 1,200,000
estimate
Ksh 1,546,702

Egentubi secondary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2003
action
Construction of twin Lab
output
improve learning conditions
implementation status
Wing one completed
total cost
Ksh 1,197,000
estimate
Ksh 1,039,393

Kahawa Dispensary

location
Esise (in North Mugirango Borabu)
year first funded
2003
action
Construction of faciltity
output
Health Services
implementation status
Finishing of structure
total cost
Ksh 1,145,000
estimate
Ksh 1,976,827

Mwongori Dispensary

location
Mekenene (in North Mugirango Borabu)
year first funded
2004
action
Construction of faciltity and electricity
output
Provide health services
implementation status
Project completed
total cost
Ksh 1,100,000
estimate
Ksh 800,000

Nyansiongo secondary School

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2005
action
Completion of PTA dormitory
output
Enough accomodation
implementation status
complete and in use
total cost
Ksh 1,100,000
estimate
Ksh 200,000

Saiga Ngiya Bridge

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2005
action
Construction of bridge
output
Improve communication
implementation status
Completed
total cost
Ksh 1,100,000
estimate
Ksh 1,160,000

Nyandoche II secondary

location
Mekenene (in North Mugirango Borabu)
year first funded
2004
action
Equipment and Lab
output
Improve science subjects
implementation status
Equipment bought. Building at foundation
total cost
Ksh 1,100,000
estimate
Ksh 2,611,678

Ribaita primary School

location
Mekenene (in North Mugirango Borabu)
year first funded
2006
action
Construction of Classrooms
output
Reduction of learning congestion
implementation status
Demolished during post election skirmishes
total cost
Ksh 1,100,000
estimate
Ksh 1,872,327

Amatierio Dispensary

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2003
action
Construction of faciltity
output
Provide health services
implementation status
Completed
total cost
Ksh 1,097,000
estimate
Ksh 3,430,600

Riensune primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of Classrooms
output
Reduction of learning congestion
implementation status
Renovation of classrooms
total cost
Ksh 1,050,000
estimate
Ksh 2,718,382

Itibo primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2004
action
Construction of Classrooms
output
Reduction of learning congestion
implementation status
Finishing with plastering and flooring
total cost
Ksh 1,000,800
estimate
Ksh 700,000

mwongori riamoseti

location
Mekenene (in North Mugirango Borabu)
year first funded
2009
action
Construction of road
output
now passable
implementation status
almost complete
total cost
Ksh 1,000,000
estimate
Ksh 4,320,030

Nyakwerema secondary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2004
action
Lab Construction and equiping
output
Improve science subjects
implementation status
At walling
total cost
Ksh 1,000,000
estimate
Ksh 1,847,782

Nsicha Dispensary

location
Kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of faciltity
output
Health Services
implementation status
Roofing is on
total cost
Ksh 1,000,000
estimate
Ksh 4,393,207

Nyanchoka Bridge

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2005
action
Construction of bridge
output
Improve communication
implementation status
Construction is on
total cost
Ksh 1,000,000
estimate
Ksh 1,044,500

Kemunchugu Dispensary

location
Bokeira (in North Mugirango Borabu)
year first funded
2006
action
Construction of faciltity
output
Health Services
implementation status
Plastering,doors,windows, flooring and painting of wing 1
total cost
Ksh 1,000,000
estimate
Ksh 3,141,919

Kitaru Dispensary

location
kiang'eni (in North Mugirango Borabu)
year first funded
2005
action
Construction of faciltity
output
Health Services
implementation status
Roofing
total cost
Ksh 1,000,000
estimate
Ksh 1,994,562

Mwongori secondary School

location
Mekenene (in North Mugirango Borabu)
year first funded
2005
action
Classrooms Construction & wiring
output
Electricity and Classrooms
implementation status
complete
total cost
Ksh 1,000,000
estimate
Ksh 1,596,039

Mogusii secondary School

location
Mekenene (in North Mugirango Borabu)
year first funded
2005
action
Construction of lab
output
Improve science subjects
implementation status
Completed
total cost
Ksh 1,000,000
estimate
Ksh 2,600,000

Kerumbe Dispensary

location
kiang'eni (in North Mugirango Borabu)
year first funded
2005
action
Construction of faciltity
output
Health Services
implementation status
Completed
total cost
Ksh 1,000,000
estimate
Ksh 3,650,000

Bomwagamo W. Springs

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2003
action
8 springs protected
output
Water
implementation status
One gravity project is underway
total cost
Ksh 982,784
estimate
Ksh 580,000

Esianyi Dispensary

location
Borangi (in North Mugirango Borabu)
year first funded
2003
action
Construction of faciltity
output
Provide health services
implementation status
completed facility. Start doctor's house
total cost
Ksh 970,000
estimate
Ksh 1,239,000

Orwaki Dispesary

location
Bokeira (in North Mugirango Borabu)
year first funded
2004
action
Construction of faciltity
output
Provide health services
implementation status
facility completed
total cost
Ksh 900,000
estimate
Ksh 927,200

Itumbe secondary School

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2005
action
Lab Construction
output
Improve science subjects
implementation status
Completed
total cost
Ksh 900,000
estimate
Ksh 1,400,000

St. Stephen Youth Polytechnic

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Facility Construction
output
Provide technical training
implementation status
Lecture rooms now at plastering
total cost
Ksh 900,000
estimate
Ksh 1,198,496

Ibara Boarding primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2004
action
Construction of Dormitory
output
To provide enough boarding facilities
implementation status
Finishing with plastering and flooring and painting
total cost
Ksh 900,000
estimate
Ksh 1,030,886

Kenyoro SDA primary School

location
Esise (in North Mugirango Borabu)
year first funded
2004
action
Construction of Classrooms
output
Reduce congestion
implementation status
Finishing of structure
total cost
Ksh 900,000
estimate
Ksh 7,765,600

Nyambiri secondary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2005
action
Construction of 3 Classrooms
output
Reduction of learning congestion
implementation status
Finishing with plastering and flooring
total cost
Ksh 900,000
estimate
Ksh 1,114,600

Nyamori primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2006
action
Construction of 3 Classrooms
output
Reduction of learning congestion
implementation status
Painting and flooring
total cost
Ksh 860,000
estimate
Ksh 621,640

Bomwagamo Chiefs Office

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of chief's offices
output
Efficient administration
implementation status
Plastering and pflooring and painting to be done
total cost
Ksh 800,000
estimate
Ksh 800,000

Chinche primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2004
action
Construction of Latrines
output
Improve hygiene
implementation status
Completed and in use
total cost
Ksh 800,000
estimate
Ksh 600,000

St. Pauls Omonayo secondary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2004
action
Construction of Dormitory
output
improve learning conditions
implementation status
Dorm completed
total cost
Ksh 800,000
estimate
Ksh 661,000

St. Thomas Moore secondary School

location
Esise (in North Mugirango Borabu)
year first funded
2005
action
Construction of Admin Block
output
Admin Block and computers
implementation status
completed admin. Block
total cost
Ksh 800,000
estimate
Ksh 825,125

Riomego/Magwagwa Dispensary

location
Borangi (in North Mugirango Borabu)
year first funded
2004
action
Construction of faciltity
output
Provide health services
implementation status
Ceiling, paiting,wiring the remaining part
total cost
Ksh 800,000
estimate
Ksh 1,388,128

St. James Nyaronde secondary

location
Mekenene (in North Mugirango Borabu)
year first funded
2004
action
lab construction
output
Improve science subjects
implementation status
complete
total cost
Ksh 780,000
estimate
Ksh 1,055,536

Gesabakwa Bridge

location
Esise (in North Mugirango Borabu)
year first funded
2006
action
Construction of bridge
output
Improve communication
implementation status
completed
total cost
Ksh 770,000
estimate
Ksh 771,570

Nyaramba Special Unit

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2004
action
Special Unit Construction
output
Meet special cases
implementation status
Complete
total cost
Ksh 768,000
estimate
Ksh 1,017,966

Kiamanyomba Dispensary

location
Borangi (in North Mugirango Borabu)
year first funded
2008
action
Construction of faciltity
output
Provide health services
implementation status
At walling
total cost
Ksh 750,000
estimate
Ksh 1,366,480

St. Francis Kerema secondary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2004
action
Lab Construction & renovation of 4 Classrooms
output
improve learning conditions
implementation status
Renovation completed, Lab on roofing
total cost
Ksh 750,000
estimate
Ksh 850,600

Rianyakangi primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2005
action
Construction of 4 Classrooms
output
Reduction of learning congestion
implementation status
Completed and in use
total cost
Ksh 700,000
estimate
Ksh 969,000

Tindereti secondary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2008
action
Construction of Classrooms
output
Reduction of learning congestion
implementation status
Not yet started
total cost
Ksh 700,000
estimate
Ksh 1,501,250

riasimiti bridge

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2009
action
Construction of bridge
output
To provide accessibity to the community
implementation status
new
total cost
Ksh 700,000
estimate
Ksh 4,800,000

Kahawa secondary School

location
Esise (in North Mugirango Borabu)
year first funded
2005
action
Construction of library & wiring
output
Reduction of learning congestion
implementation status
Completed and in use
total cost
Ksh 700,000
estimate
Ksh 794,933

Amakura primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2005
action
Construction of Admin. Block
output
Reduction of learning congestion
implementation status
Changed to wiring . Done and completed
total cost
Ksh 700,000
estimate
Ksh 650,000

Omonono primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2006
action
Construction of Office with 3 Classrooms
output
Reduction of learning congestion
implementation status
Roofing
total cost
Ksh 650,000
estimate
Ksh 600,000

Nyankongo primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2006
action
Construction of 2 Classrooms
output
Reduce congestion
implementation status
complete and in use
total cost
Ksh 650,000
estimate
Ksh 300,000

Nyakenimo primary

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2005
action
Construction of 4 Classrooms
output
Reduction of learning congestion
implementation status
Finishing with flooring and plastering
total cost
Ksh 650,000
estimate
Ksh 1,700,000

St. Joseph's Lietego secondary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Classroooms construction
output
Reduce congestion
implementation status
Finishing of structure
total cost
Ksh 630,000
estimate
Ksh 1,130,000

Nyageita primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2005
action
Construction of 2 Classrooms
output
Reduce congestion
implementation status
complete and in use
total cost
Ksh 600,000
estimate
Ksh 514,680

Sere Dispensary

location
Obwari (in North Mugirango Borabu)
year first funded
2005
action
Construction of faciltity
output
Health Services
implementation status
At foundation level
total cost
Ksh 600,000
estimate
Ksh 5,296,829

Keneni STU Police Post

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2005
action
Construction of Post
output
Efficient administration
implementation status
At roofing
total cost
Ksh 600,000
estimate
Ksh 470,000

Nderema primary School

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2004
action
Construction of Classrooms
output
Reduction of learning congestion
implementation status
Finishing with plastering and flooring
total cost
Ksh 597,000
estimate
Ksh 657,000

Nyansiongo W. Springs

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2003
action
Protection
output
Water
implementation status
8 springs protected
total cost
Ksh 580,000
estimate
Ksh 580,000

Omonayo secondary Comp. Project

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Procurement of computers
output
Computer literacy
implementation status
Computers bought
total cost
Ksh 560,000
estimate
Ksh 801,300

Ibara DOK primary

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Materials on site
total cost
Ksh 550,000
estimate
Ksh 533,540

Emboye primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2006
action
Construction of 2 Classrooms
output
Reduction of learning congestion
implementation status
Need plastering and painting
total cost
Ksh 520,000
estimate
Ksh 812,566

Moteoguto primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
plastering anfd flooring
total cost
Ksh 500,000
estimate
Ksh 1,528,160

Nyandoche Ibere Disp

location
Mekenene (in North Mugirango Borabu)
year first funded
2006
action
Construction of faciltity
output
Provide health services
implementation status
Roofing done. Plastering, flooring and painting needed
total cost
Ksh 500,000
estimate
Ksh 1,150,975

Kiabonyoru secondary Comp. Project

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Procurement of computers
output
Computer literacy
implementation status
Computers bought
total cost
Ksh 500,000
estimate
Ksh 300,000

Nyangoge primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2006
action
Renovation of Classrooms
output
Classrooms
implementation status
Renovation done
total cost
Ksh 500,000
estimate
Ksh 200,000

Eaka- Mabariri Road

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2008
action
Bush clearing
output
Passable road
implementation status
rehabilitaton
total cost
Ksh 500,000
estimate
Ksh 592,000

Kioge- Nyangoso Road

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2004
action
Bush clearing
output
Passable road
implementation status
completed
total cost
Ksh 500,000
estimate
Ksh 592,000

Nyabweri Dispensary

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2008
action
Construction of faciltity
output
Health Services
implementation status
At foundation level
total cost
Ksh 500,000
estimate
Ksh 1,720,800

Monga primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofed. Need doors windows, floor and plastering
total cost
Ksh 500,000
estimate
Ksh 726,526

Nyamonuri primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of 3 Classrooms
output
Reduction of learning congestion
implementation status
Classrooms at lintel
total cost
Ksh 500,000
estimate
Ksh 544,440

Kebariga primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of 1 Class Plastering done partly
output
Reduction of learning congestion
implementation status
Roofing done. Need plastering, flooring and painting
total cost
Ksh 500,000
estimate
Ksh 555,280

Biego secondary Comp. Project

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Procurement of computers
output
Computer literacy
implementation status
Computers are being procured
total cost
Ksh 460,000
estimate
Ksh 801,300

Esise W. Project

location
Esise (in North Mugirango Borabu)
year first funded
2003
action
4 Springs protected
output
Clean water provision
implementation status
4 completed
total cost
Ksh 453,196
estimate
Ksh 380,000

Ribwago Water Project

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2004
action
Construction of piped water
output
Proximity to water
implementation status
Await Cheque to complete
total cost
Ksh 450,000
estimate
Ksh 200,000

Tindereti Dispensary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2008
action
Construction of faciltity
output
Provide health services
implementation status
Not started
total cost
Ksh 450,000
estimate
Ksh 0

Mokomoni primary

location
Kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of 2 Classrooms
output
Reduction of learning congestion
implementation status
At lintels. Need roofing
total cost
Ksh 450,000
estimate
Ksh 988,000

Monyara primary

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of 2 Classrooms
output
Reduction of learning congestion
implementation status
Finishing with flooring and plastering
total cost
Ksh 450,000
estimate
Ksh 2,066,980

Mageri primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2004
action
Construction of 2 Classrooms and hall
output
Reduction of learning congestion
implementation status
Completed and in use
total cost
Ksh 450,000
estimate
Ksh 1,008,900

Kiabiraa primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction 2 of Classrooms
output
Reduction of learning congestion
implementation status
One roofed another on lintels
total cost
Ksh 450,000
estimate
Ksh 413,850

Nyagacho primary

location
Mekenene (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofing. Need funds to finish with plastrring,flooring
total cost
Ksh 450,000
estimate
Ksh 10,000,000

Keginga secondary School

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Classroooms construction
output
Reduction of learning congestion
implementation status
Project never stated
total cost
Ksh 400,000
estimate
Ksh 7,945,972

Ensoko primary School

location
Esise (in North Mugirango Borabu)
year first funded
2006
action
Construction of Classroom
output
Reduce congestion
implementation status
Finishing of structure
total cost
Ksh 400,000
estimate
Ksh 300,000

Etono DEB primary

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2005
action
Construction of Classrooms
output
Reduction of learning congestion
implementation status
200,000 Emergency for roofing done. Plastering & flooring to be done
total cost
Ksh 400,000
estimate
Ksh 993,000

Eronge DEB primary

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofed. Need doors windows, floor and plastering
total cost
Ksh 400,000
estimate
Ksh 1,057,500

Nyanchoka primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Finishing. Need windows and doors, plastering and flooring
total cost
Ksh 400,000
estimate
Ksh 881,095

St. Gonzaga Gonza W.Project

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2006
action
Construction of piped water
output
Proximity to water
implementation status
Water supply in school
total cost
Ksh 400,000
estimate
Ksh 3,500,000

Nyageita/Rirumi W. Project

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2006
action
piped water
output
Safe water
implementation status
phase 1 complete
total cost
Ksh 400,000
estimate
Ksh 400,000

Eaka primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of Classrooms
output
Reduction of learning congestion
implementation status
Finishing with plastering and flooring
total cost
Ksh 400,000
estimate
Ksh 621,560

Kiabonyoru W. Springs

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2003
action
Protection
output
Water
implementation status
6 springs protection completed
total cost
Ksh 380,000
estimate
Ksh 180,000

Rigena primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2008
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Not started
total cost
Ksh 350,000
estimate
Ksh 700,000

Riang'ombe primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintels
total cost
Ksh 350,000
estimate
Ksh 350,000

Matunwa primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintels
total cost
Ksh 350,000
estimate
Ksh 1,400,000

Kebuse primary School

location
Esise (in North Mugirango Borabu)
year first funded
2006
action
Construction of Classroom
output
Reduce congestion
implementation status
Finishing of structure
total cost
Ksh 350,000
estimate
Ksh 4,000,000

Kegogi primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2005
action
Construction and renovation of Classrooms
output
Reduction of learning congestion
implementation status
Finishing of 1 classroom. 4 rooms renovated
total cost
Ksh 350,000
estimate
Ksh 408,000

Endiba primary

location
Kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Wiring
output
Lighting system
implementation status
wiring done on 14 classrooms. 5 remains
total cost
Ksh 350,000
estimate
Ksh 2,532,726

Nyakwerema primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of Latrines. 4 for staff and five for girls
output
Improve hygiene
implementation status
complete and in use
total cost
Ksh 350,000
estimate
Ksh 271,980

Nyabweri Polytechnic

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2003
action
Construction of faciltity's study rooms
output
Provide technical training
implementation status
2 Completed
total cost
Ksh 344,000
estimate
Ksh 609,760

Gozaga Gonzaga secondary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2006
action
Construction of Classrooms lab, adm. block & Computers
output
Computers and classrooms
implementation status
Ongoing. At foundation
total cost
Ksh 320,000
estimate
Ksh 7,557,283

Memisi primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintels
total cost
Ksh 310,000
estimate
Ksh 200,000

Rianyaemo primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Awaits Funds to commence
total cost
Ksh 300,000
estimate
Ksh 1,200,000

Rigoko secondary School

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2004
action
Construction of lab & Equipment
output
Improve science subjects
implementation status
At lintels
total cost
Ksh 300,000
estimate
Ksh 800,000

Mogusii Dispensary

location
Mekenene (in North Mugirango Borabu)
year first funded
2006
action
Construction of faciltity
output
Provide health services
implementation status
complete
total cost
Ksh 300,000
estimate
Ksh 925,413

Kitaru primary

location
Mekenene (in North Mugirango Borabu)
year first funded
2007
action
Construction of 2 Classrooms
output
Reduction of learning congestion
implementation status
At lintels
total cost
Ksh 300,000
estimate
Ksh 886,000

Biego primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At walling
total cost
Ksh 300,000
estimate
Ksh 841,648

Nsicha primary

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At walling
total cost
Ksh 300,000
estimate
Ksh 792,836

Kiabonyoru primary

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Renovation of Classrooms
output
Reduction of learning congestion
implementation status
Renovation done
total cost
Ksh 300,000
estimate
Ksh 866,350

Nyabikomu primary

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At walling
total cost
Ksh 300,000
estimate
Ksh 1,871,000

Egentubi primary

location
Kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of toilets &Classrooms
output
Reduction of learning congestion
implementation status
Toilets complete
total cost
Ksh 300,000
estimate
Ksh 790,000

Nyagware primary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2006
action
Renovation of 9 Classrooms
output
Improve structures
implementation status
Completed
total cost
Ksh 300,000
estimate
Ksh 469,000

Manga Chief's Office

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of chiefs offices
output
Efficient administration
implementation status
Procurement of materials and digging foundation
total cost
Ksh 300,000
estimate
Ksh 862,100

Erandi Water Project

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of piped water
output
Proximity to water
implementation status
Construction is on. CDF funds used to purcahase some materials
total cost
Ksh 292,784
estimate
Ksh 400,000

Eaka Coffee Factory

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2007
action
Renovation of factory facilities
output
Improve coffee factiory
implementation status
Drying bed made
total cost
Ksh 260,000
estimate
Ksh 734,080

St. Gonzaga Gonza secondary Comp. Project

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Procurement of computers
output
Computer literacy
implementation status
Computers bought
total cost
Ksh 260,000
estimate
Ksh 801,300

Menyenya secondary Comp. Project

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Procurement of computers
output
Computer literacy
implementation status
Funds reallocatted to electrity project
total cost
Ksh 260,000
estimate
Ksh 801,300

Mecheo secondary Comp. Project

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Procurement of computers
output
Computer literacy
implementation status
Computers bought
total cost
Ksh 260,000
estimate
Ksh 801,300

Riontonyi Police Post

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2008
action
Construction of Post
output
Efficient administration
implementation status
Not started
total cost
Ksh 250,000
estimate
Ksh 770,000

Kiomachingi primary

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of Classrooms
output
Reduction of learning congestion
implementation status
Finishing one classrooom. 2 others at foundation
total cost
Ksh 250,000
estimate
Ksh 813,460

Ntana primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Finishing with flooring and plastering
total cost
Ksh 250,000
estimate
Ksh 2,078,850

Kerobo Dispensary

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2007
action
Construction of faciltity's store for IFAD funded construction
output
Health Services
implementation status
Completed
total cost
Ksh 250,000
estimate
Ksh 188,800

Kiabonyoru Cheifs Office

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2005
action
Renovation of chiefs offices
output
Efficient administration
implementation status
Completed and in use
total cost
Ksh 250,000
estimate
Ksh 468,520

Borabu primary

location
Mekenene (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofing done. Plastering, flooring and painting needed
total cost
Ksh 250,000
estimate
Ksh 1,980,600

Mwongori primary

location
Mekenene (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofing done. Plastering, flooring and painting needed
total cost
Ksh 250,000
estimate
Ksh 1,947,241

Nyansiongo DOK primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintel lvel
total cost
Ksh 212,000
estimate
Ksh 1,857,600

Mekenene W. Springs

location
Mekenene (in North Mugirango Borabu)
year first funded
2005
action
Spring protection
output
Proximity to water
implementation status
3 springs protected.
total cost
Ksh 200,843
estimate
Ksh 200,843

Nderema Dispensary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2004
action
Purchase of equipment
output
Health Services
implementation status
Completed
total cost
Ksh 200,000
estimate
Ksh 200,000

Kiomara dispensary

location
Bokeira (in North Mugirango Borabu)
year first funded
2006
action
Purchase of equipment
output
Health Services
implementation status
Completed
total cost
Ksh 200,000
estimate
Ksh 2,381,000

Nyabweri primary School

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofing done. Need plastering, flooring and painting
total cost
Ksh 200,000
estimate
Ksh 540,600

Etono Boarding primary

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Classroom needs windows and painting
total cost
Ksh 200,000
estimate
Ksh 1,146,630

Nyamiacho Bridge

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2006
action
Construction of bridge
output
Improve communication
implementation status
Completed
total cost
Ksh 200,000
estimate
Ksh 200,000

Omosocho primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintels
total cost
Ksh 200,000
estimate
Ksh 238,430

Raitigo Dam

location
Esise (in North Mugirango Borabu)
year first funded
2004
action
Rehabilitation
output
Dam
implementation status
complete
total cost
Ksh 200,000
estimate
Ksh 3,712,500

Tente Dam

location
Esise (in North Mugirango Borabu)
year first funded
2004
action
Rehabilitation
output
Dam
implementation status
complete
total cost
Ksh 200,000
estimate
Ksh 200,000

Eturungi Dispensary

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2008
action
Construction of faciltity
output
Health Services
implementation status
At foundation level
total cost
Ksh 200,000
estimate
Ksh 4,393,207

Kineni secondary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Equipment for Lab
output
Improve science subjects
implementation status
Equipment bought.
total cost
Ksh 200,000
estimate
Ksh 1,001,250

Gesibei primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofing. Need funds to finish with plastrring,flooring
total cost
Ksh 200,000
estimate
Ksh 2,787,170

Raitigo disp

location
esise (in North Mugirango Borabu)
year first funded
2009
action
n/a
output
-
implementation status
not known
total cost
Ksh 200,000
estimate
Ksh 200,000

Eaka Coffee Factory

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2009
action
Renovation of factory facilities
output
Improve coffee factiory
implementation status
renovation going on
total cost
Ksh 160,000
estimate
Ksh 200,000

Rieko Bridge

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2006
action
Construction of bridge
output
Improve communication
implementation status
Completed
total cost
Ksh 150,000
estimate
Ksh 150,000

Nyageita Tea Buying Centre

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Renovation of factory facilities
output
Improve tea centres
implementation status
Partily done
total cost
Ksh 150,000
estimate
Ksh 468,154

Kegogi Tea Buying Centre

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Renovation of factory facilities
output
Improve tea factory
implementation status
Materials on site
total cost
Ksh 150,000
estimate
Ksh 300,000

Mekenene primary

location
Mekenene (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofing done. Plastering, flooring and painting needed
total cost
Ksh 150,000
estimate
Ksh 2,420,500

Nyaronde primary

location
Mekenene (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofing done. Plastering, flooring and painting needed
total cost
Ksh 150,000
estimate
Ksh 350,000

Mogusii primary

location
Mekenene (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofing done. Plastering, flooring and painting needed
total cost
Ksh 150,000
estimate
Ksh 1,321,300

Mekenene Chiefs Office

location
Mekenene (in North Mugirango Borabu)
year first funded
2008
action
Construction of office
output
Improve administration
implementation status
Not issued with cheque
total cost
Ksh 150,000
estimate
Ksh 750,000

Riamanoti primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Roofing. Need funds to finish with plastrring,flooring
total cost
Ksh 150,000
estimate
Ksh 350,000

Manga Police Post

location
Esise (in North Mugirango Borabu)
year first funded
2008
action
Wiring of the police houses
output
Efficient administration
implementation status
not completed
total cost
Ksh 150,000
estimate
Ksh 0

Mabariri Coffee Factory

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2007
action
Renovation of factory facilities
output
Improve coffee factiory
implementation status
Drying bed made
total cost
Ksh 150,000
estimate
Ksh 734,080

Keginga primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintel lvel
total cost
Ksh 100,000
estimate
Ksh 350,000

Nyansiongo DEB primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of toilets &Classrooms
output
Improve hygiene
implementation status
Rooofing
total cost
Ksh 100,000
estimate
Ksh 350,000

Tindereti primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintel lvel
total cost
Ksh 100,000
estimate
Ksh 350,000

Itumbe primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintel lvel
total cost
Ksh 100,000
estimate
Ksh 350,000

Saigangiya primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintel lvel
total cost
Ksh 100,000
estimate
Ksh 350,000

Mogusii W. Project

location
Mekenene (in North Mugirango Borabu)
year first funded
2008
action
Spring protection
output
Proximity to water
implementation status
Not issued with cheque
total cost
Ksh 100,000
estimate
Ksh 100,000

Isoge primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintel lvel
total cost
Ksh 100,000
estimate
Ksh 757,000

Menyenya primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintel lvel
total cost
Ksh 100,000
estimate
Ksh 350,000

Masige primary

location
Nyansiongo (in North Mugirango Borabu)
year first funded
2008
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
Not started
total cost
Ksh 100,000
estimate
Ksh 732,050

moteoguto tea buying centreprimary School

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2009
action
Renovation of factory facilities
output
Improve tea leaf collection
implementation status
Just issued a cheque
total cost
Ksh 100,000
estimate
Ksh 100,000

Manga DEB primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintels
total cost
Ksh 100,000
estimate
Ksh 350,000

Mecheo primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintels
total cost
Ksh 100,000
estimate
Ksh 350,000

Mebeno Cattle Dip

location
Esise (in North Mugirango Borabu)
year first funded
2008
action
Rehabilitation of dip
output
Improve cattle rearing actvities
implementation status
not completed
total cost
Ksh 100,000
estimate
Ksh 0

Kerema Polytechnic

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Facility's Classroom Construction
output
Provide technical training
implementation status
At walling
total cost
Ksh 100,000
estimate
Ksh 740,895

Kerema Pri

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At walling
total cost
Ksh 100,000
estimate
Ksh 740,895

Kerenda Tea Buying Centre

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2008
action
Contruction of factory facilities
output
Improve tea centres
implementation status
Materials on site
total cost
Ksh 100,000
estimate
Ksh 0

Riomoruri Tea Buying Centre

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2008
action
Contruction of factory facilities
output
Improve tea centres
implementation status
Materials on site
total cost
Ksh 100,000
estimate
Ksh 0

Ekerubo W. Project

location
Mekenene (in North Mugirango Borabu)
year first funded
2008
action
Spring protection
output
Proximity to water
implementation status
Not issued with cheque
total cost
Ksh 100,000
estimate
Ksh 100,000

Nyageita Tea Buying Centre

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2008
action
Renovation of factory facilities
output
Improve tea factory
implementation status
Procurement of materials
total cost
Ksh 100,000
estimate
Ksh 0

Kioge dispensary

location
Bokeira (in North Mugirango Borabu)
year first funded
2008
action
Construction of faciltity
output
Health Services
implementation status
Foundation setting
total cost
Ksh 100,000
estimate
Ksh 0

Esise primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintels
total cost
Ksh 100,000
estimate
Ksh 1,700,300

Endemu primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintels
total cost
Ksh 100,000
estimate
Ksh 664,000

Rietego primary

location
Esise (in North Mugirango Borabu)
year first funded
2007
action
Construction of 1 Classroom
output
Reduction of learning congestion
implementation status
At lintels
total cost
Ksh 100,000
estimate
Ksh 350,000

Mokomoni Water Project

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Spring protection
output
Clean water provision
implementation status
Not yet started
total cost
Ksh 73,196
estimate
Ksh 100,000

Omonono W. Springs

location
Kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Spring protection
output
Clean water provision
implementation status
Not yet started
total cost
Ksh 73,196
estimate
Ksh 100,000

Nyangoge W. Springs

location
Kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Spring protection
output
Clean water provision
implementation status
1 spring protection done
total cost
Ksh 73,196
estimate
Ksh 100,000

Nyaramba Water Project

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Spring protection
output
Clean water provision
implementation status
2 springs under protected
total cost
Ksh 73,196
estimate
Ksh 695,670

Egentubi Tea Buying Centre

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Construction of factory facilities
output
Improve tea centres
implementation status
At lintels
total cost
Ksh 50,000
estimate
Ksh 1,103,456

Eng'eta Tea Buying Centre

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Renovation of factory facilities
output
Improve tea centres
implementation status
Materials on site
total cost
Ksh 50,000
estimate
Ksh 649,240

Omosocho Tea Buying Centre

location
kiabonyoru (in North Mugirango Borabu)
year first funded
2007
action
Renovation of factory facilities
output
Improve tea centres
implementation status
Materials on site
total cost
Ksh 50,000
estimate
Ksh 300,000

Nyakenimo Coffee Factory

location
Bomwagamo (in North Mugirango Borabu)
year first funded
2007
action
Renovation of factory facilities
output
Improve coffee factiory
implementation status
Drying bed made
total cost
Ksh 50,000
estimate
Ksh 734,080