It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

Projects in Nyakach

Emergency Reserve

location
PapOnditi (in Nyakach)
year first funded
2004
action
For Emergency Situations
output
Disusters Addressed
implementation status
not known
total cost
Ksh 9,983,940
estimate
Ksh 0

Office Administration

location
PapOnditi (in Nyakach)
year first funded
2003
action
Management And Supervision
output
Project Implementation
implementation status
On Going
total cost
Ksh 5,922,999
estimate
Ksh 0

Ds Office

location
PapOnditi (in Nyakach)
year first funded
2004
action
Construction of Do's Office
output
Do?S Office
implementation status
Finishing
total cost
Ksh 3,300,000
estimate
Ksh 2,550,000

Cdf Vehicle

location
Pap Onditi (in Nyakach)
year first funded
2005
action
Procurement
output
-
implementation status
Complete
total cost
Ksh 3,037,350
estimate
Ksh 3,037,350

Ramula Odowa Secondary School

location
Oboch (in Nyakach)
year first funded
2007
action
Construction Of Classrooms
output
Classrooms
implementation status
Not Started
total cost
Ksh 3,000,000
estimate
Ksh 3,000,000

Community Development Centre

location
Central Nyakach (in Nyakach)
year first funded
2004
action
Construction of Community Centre
output
Community Centre
implementation status
Plastering
total cost
Ksh 2,750,000
estimate
Ksh 2,000,000

Oriang Earth Dam

location
Thurdibuoro (in Nyakach)
year first funded
2004
action
Construction of Water
output
Water
implementation status
Stalled
total cost
Ksh 2,700,000
estimate
Ksh 2,796,334

Cherwa Dispensary

location
North E Nyakach (in Nyakach)
year first funded
2003
action
Construction of Dispensary
output
Dispensary
implementation status
Plastering
total cost
Ksh 2,553,333
estimate
Ksh 2,914,784

Radienya Dispensary

location
South Nyakach (in Nyakach)
year first funded
2003
action
Construction of Dispensary
output
Dispensary
implementation status
Plastering
total cost
Ksh 2,469,085
estimate
Ksh 2,366,898

Nyakach Constituency Office

location
Pap Onditi (in Nyakach)
year first funded
2007
action
n/a
output
-
implementation status
Not Started
total cost
Ksh 2,300,000
estimate
Ksh 2,300,000

South Nyakach Coffee Factory

location
South Nyakach (in Nyakach)
year first funded
2004
action
Construction of Coffee Factory
output
Coffee Factory
implementation status
Plastering
total cost
Ksh 2,200,000
estimate
Ksh 1,657,134

Gari Dispensary

location
Oboch (in Nyakach)
year first funded
2003
action
Construction of Dispensary
output
Dispensary
implementation status
Fitting
total cost
Ksh 2,105,000
estimate
Ksh 2,161,920

Bonde Maternity

location
Nyalunya (in Nyakach)
year first funded
2004
action
Construction of Maternity Ward
output
Maternity Ward
implementation status
Finishing
total cost
Ksh 2,100,000
estimate
Ksh 3,023,688

Onyuongo Medical Clinic

location
East Nyakach (in Nyakach)
year first funded
2004
action
Construction of Medical Clinic
output
Medical Clinic
implementation status
Fitting
total cost
Ksh 2,050,000
estimate
Ksh 2,514,900

Sangoro Dispensary

location
Thurdibuoro (in Nyakach)
year first funded
2006
action
Construction of Dispensary Foundation
output
Dispensary Foundation
implementation status
Ongoing
total cost
Ksh 2,000,000
estimate
Ksh 2,581,000

Pedo Dispensary

location
Central Nyakach (in Nyakach)
year first funded
2004
action
Construction of Dispensary
output
Dispensary
implementation status
Fitting
total cost
Ksh 2,000,000
estimate
Ksh 2,004,892

Nyabola Dispensary

location
Nyalunya (in Nyakach)
year first funded
2004
action
Construction of Dispensary
output
Dispensary
implementation status
Newest
total cost
Ksh 1,850,000
estimate
Ksh 2,362,137

Katito Youth Polytechnic

location
South Nyakach (in Nyakach)
year first funded
2006
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 1,850,000
estimate
Ksh 1,350,000

Chiefs Camp

location
West Nyakach (in Nyakach)
year first funded
2004
action
Construction of Chief's Camp
output
Chief?S Camp
implementation status
not known
total cost
Ksh 1,800,000
estimate
Ksh 0

Rangul Community Development Centre

location
Rangul (in Nyakach)
year first funded
2003
action
Construction of Community Centre
output
Community Centre
implementation status
Complete
total cost
Ksh 1,660,000
estimate
Ksh 1,748,378

Camp-Upper Nyakach Do

location
South West Nyakach (in Nyakach)
year first funded
2006
action
Construction Of Offices
output
Offices
implementation status
Foundation Level
total cost
Ksh 1,600,000
estimate
Ksh 3,500,000

Sangoro Secondary School

location
Thurtiboro (in Nyakach)
year first funded
2006
action
Construction of Laboratory
output
Labaratory
implementation status
Foundation Level
total cost
Ksh 1,503,737
estimate
Ksh 150,373,775

Oboch Community Centre

location
Oboch (in Nyakach)
year first funded
2004
action
Construction of Community Centre
output
Community Centre
implementation status
Ongoing
total cost
Ksh 1,500,000
estimate
Ksh 0

Nyabola Mixed Secondary School

location
Nyalunya (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 1,400,000
estimate
Ksh 100,000

Nyabola Sec

location
Nyalunya (in Nyakach)
year first funded
2008
action
Construction Of Admin. Block
output
Classrooms
implementation status
On Going
total cost
Ksh 1,350,000
estimate
Ksh 1,350,000

Nyadina Primary School

location
West Nyakach (in Nyakach)
year first funded
2003
action
Construction 4 Classrooms And Staffroom
output
Classrooms To Serve 435 Students
implementation status
Complete
total cost
Ksh 1,305,810
estimate
Ksh 705,000

Water Pond S

location
PapOnditi (in Nyakach)
year first funded
2004
action
Construction of Water
output
Water
implementation status
Complete
total cost
Ksh 1,300,000
estimate
Ksh 1,202,700

Nnyakach Chiefs Camp

location
North East Nyakach (in Nyakach)
year first funded
2006
action
Construction of Chief's Camp
output
Chief?S Camp
implementation status
Newest
total cost
Ksh 1,300,000
estimate
Ksh 300,000

Olembo Community Water Project

location
PapOnditi (in Nyakach)
year first funded
2004
action
Construction of Water
output
Water
implementation status
On-Going
total cost
Ksh 1,100,000
estimate
Ksh 1,000,000

St. Patrick Obange Primary School

location
West Nyakach (in Nyakach)
year first funded
2003
action
Construction -4 Classrooms
output
Classrooms To Serve 552 Students
implementation status
Finishing To Completed
total cost
Ksh 1,086,190
estimate
Ksh 580,000

Gul Maembe Primary School

location
South West Nyakach (in Nyakach)
year first funded
2005
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 1,060,000
estimate
Ksh 820,000

M&E

location
PapOnditi (in Nyakach)
year first funded
2005
action
n/a
output
-
implementation status
Ongoing
total cost
Ksh 1,055,867
estimate
Ksh 0

Lisana Primary School

location
Asao (in Nyakach)
year first funded
2008
action
Construction Of 4 Classrooms
output
Classrooms
implementation status
Yet To Start
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Kogola Girls Secondary School

location
PapOnditi (in Nyakach)
year first funded
2008
action
Construction Of Tuition Block
output
-
implementation status
Yet To Start
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Sigoti Health Centre

location
Sigoti (in Nyakach)
year first funded
2007
action
Contruction
output
Ward
implementation status
Slab Level
total cost
Ksh 1,000,000
estimate
Ksh 0

Ng'Adi & Ato Yieng'O Box Culvets Projects

location
Rangul (in Nyakach)
year first funded
2008
action
Construction Of 2 Concrete And Steel Reinforced Box Culverts On Ng'Adi & Ato Yieng'O Streams
output
Bridges
implementation status
Ongoing
total cost
Ksh 1,000,000
estimate
Ksh 0

Sango Buru Primary School

location
West Nyakach (in Nyakach)
year first funded
2003
action
Construction of Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 975,000
estimate
Ksh 775,000

Anding'o Opanga Maternity

location
Thurdibuoro (in Nyakach)
year first funded
2003
action
Construction of Maternity Ward
output
Maternity Ward
implementation status
Painting
total cost
Ksh 910,000
estimate
Ksh 810,000

Orobi Primary School

location
South West Nyakach (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
Fitting
total cost
Ksh 910,000
estimate
Ksh 510,000

Asao Chiefs Office-

location
Asao (in Nyakach)
year first funded
2008
action
Construction Of Offices And Other Offices For Locational Hods
output
Offices
implementation status
Yet To Start
total cost
Ksh 900,000
estimate
Ksh 0

Achego Youth Polytechnic

location
South Nyakach (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 890,000
estimate
Ksh 890,000

Siany Secondary School

location
South Nyakach (in Nyakach)
year first funded
2006
action
Construction of 3 Classrooms
output
3 Classrooms
implementation status
Plastering
total cost
Ksh 850,000
estimate
Ksh 450,000

Kangombe Water

location
Rangul (in Nyakach)
year first funded
2005
action
Water Project
output
Water
implementation status
On Going
total cost
Ksh 850,000
estimate
Ksh 300,000

St. Hilarius Nyabondo Mixed

location
South Nyakach (in Nyakach)
year first funded
2003
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 835,000
estimate
Ksh 535,000

Kobeto Primary School

location
Asao (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 830,000
estimate
Ksh 630,000

Konditi Primary School

location
Nyalunya (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 822,000
estimate
Ksh 25,000

Nyongonga Secondary School

location
West Nyakach (in Nyakach)
year first funded
2005
action
Construction of Classrooms
output
Classrooms
implementation status
Plastering
total cost
Ksh 803,510
estimate
Ksh 703,510

Kandaria Secondary School

location
East Nyakach (in Nyakach)
year first funded
2003
action
Construction of Classrooms
output
Classrooms
implementation status
Plastering
total cost
Ksh 770,000
estimate
Ksh 570,000

Nyakwere Dispensary

location
Thurdibuoro (in Nyakach)
year first funded
2008
action
Construction Of Dispensary
output
-
implementation status
Yet To Start
total cost
Ksh 750,000
estimate
Ksh 0

Ndori Secondary School

location
East Nyakach (in Nyakach)
year first funded
2005
action
Construction of 2 Classrooms
output
2 Classrooms
implementation status
Roofing
total cost
Ksh 750,000
estimate
Ksh 400,000

Kagwel Primary School

location
Asao (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 730,000
estimate
Ksh 430,000

Ragen Secondary School

location
Central Nyakach (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 700,000
estimate
Ksh 400,000

Pap Onditi Water Point

location
Pap Onditi (in Nyakach)
year first funded
2006
action
Construction of Water
output
Water
implementation status
Ongoing
total cost
Ksh 700,000
estimate
Ksh 500,000

St. Marys Nyamarimba Girls Sec

location
South West Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 700,000
estimate
Ksh 400,000

Oboch Dispensary

location
Oboch (in Nyakach)
year first funded
2003
action
Construction of Dispensary
output
Dispensary
implementation status
Painting To Finish
total cost
Ksh 690,000
estimate
Ksh 490,000

Kanyalwal Primary School

location
Ragul (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 683,400
estimate
Ksh 483,400

Jimo Water Project

location
East Nyakach (in Nyakach)
year first funded
2003
action
Water Project
output
Water
implementation status
Complete
total cost
Ksh 680,000
estimate
Ksh 680,000

Keyo Nyadundo Primary School

location
South Nyakach (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
Plastering
total cost
Ksh 675,000
estimate
Ksh 225,000

Nyamarumbe Primary School

location
Ragul (in Nyakach)
year first funded
2004
action
Construction of 8 Classrooms
output
8 Classrooms To Serve 267 Students
implementation status
Lintel Level
total cost
Ksh 650,000
estimate
Ksh 450,000

Olembo Primary School

location
PapOnditi (in Nyakach)
year first funded
2003
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 645,555
estimate
Ksh 445,555

Rakwaro Secondary School

location
South West Nyakach (in Nyakach)
year first funded
2005
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 640,000
estimate
Ksh 340,000

Rariera Kokech Primary School

location
Asao (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 630,000
estimate
Ksh 130,000

Kandaria Water Project

location
PapOnditi (in Nyakach)
year first funded
2006
action
Construction of Water
output
Water
implementation status
Ongoing
total cost
Ksh 600,000
estimate
Ksh 400,000

Lisana Secondary School

location
Asao (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 600,000
estimate
Ksh 350,000

St Antony Secondary School

location
Oboch (in Nyakach)
year first funded
2006
action
Rehabilitation
output
Classrooms
implementation status
Ongoing
total cost
Ksh 600,000
estimate
Ksh 100,000

Pap-Onditi Police Station

location
PapOnditi (in Nyakach)
year first funded
2008
action
Construction OcsS Office And Wiring Of Police Residential Houses
output
Offices And Wiring
implementation status
Yet To Start
total cost
Ksh 600,000
estimate
Ksh 0

Asao Footbridge Project

location
Rangul (in Nyakach)
year first funded
2008
action
Construction Of Concrete And Steel Reinforced Footbidge On Lower Asao Rriverl
output
Footbridge
implementation status
Ongoing
total cost
Ksh 600,000
estimate
Ksh 0

Nyangonga Primary School

location
West Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 600,000
estimate
Ksh 300,000

Miruka Primary School

location
North Nyakach (in Nyakach)
year first funded
2004
action
Construction of 3 Classes
output
3 Classes
implementation status
Finishing
total cost
Ksh 590,000
estimate
Ksh 390,000

Ngomo Primary School

location
North East Nyakach (in Nyakach)
year first funded
2003
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 576,667
estimate
Ksh 376,667

Michura Primary School

location
East Nyakach (in Nyakach)
year first funded
2003
action
Construction of Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 575,000
estimate
Ksh 275,000

Bishop Okumu Secondary School

location
Oboch (in Nyakach)
year first funded
2003
action
Electrification
output
Lighting Of Classrooms
implementation status
Complete
total cost
Ksh 570,000
estimate
Ksh 170,000

Bur Kamach Primary School

location
South West Nyakach (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 550,000
estimate
Ksh 310,000

Urudi Secondary School

location
Rangul (in Nyakach)
year first funded
2004
action
Construction of 2 Classrooms
output
2Classrooms
implementation status
Lintel Level
total cost
Ksh 550,000
estimate
Ksh 350,000

Nyaksure Primary School

location
PapOnditi (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 545,555
estimate
Ksh 345,555

Bwaja Primary School

location
North Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 540,000
estimate
Ksh 340,000

Urudi Primary School

location
Rangul (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 533,300
estimate
Ksh 183,300

Kanyateng Primary School

location
Asao (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 530,000
estimate
Ksh 330,000

Nduga Primary School

location
Asao (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 530,000
estimate
Ksh 230,000

Kasao Primary School

location
Rangul (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 500,000
estimate
Ksh 250,000

Mbugura Primary School

location
Thurtiboro (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 500,000
estimate
Ksh 300,000

Nyabondo Boys

location
South Nyakach (in Nyakach)
year first funded
2007
action
Purchase Generator
output
Generator
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 500,000

Nyakach Girls Secondary School

location
Oboch (in Nyakach)
year first funded
2008
action
Roofing Of Dining Hall
output
dining Hall
implementation status
Ongoing
total cost
Ksh 500,000
estimate
Ksh 500,000

Pap-Onditi Chiefs Office

location
PapOnditi (in Nyakach)
year first funded
2008
action
Construction Of Offices And Other Offices For Locational Hods
output
Offices
implementation status
Yet To Start
total cost
Ksh 500,000
estimate
Ksh 0

Kabuya Primary School

location
Nyalunya (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 490,000
estimate
Ksh 240,000

Nyalunya Primary School

location
Nyalunya (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Windows To Complete
total cost
Ksh 475,000
estimate
Ksh 225,000

Miriu Daraja

location
Oboch (in Nyakach)
year first funded
2003
action
Construction of Bridges
output
Bridges
implementation status
Stalled
total cost
Ksh 470,000
estimate
Ksh 235,000

Ragen A Primary School

location
Nyalunya (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 470,000
estimate
Ksh 70,000

Ogeko Primary School

location
South West Nyakach (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
Complete
total cost
Ksh 450,000
estimate
Ksh 310,000

Ochwado Primary School

location
North Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 440,000
estimate
Ksh 240,000

Wasare Primary School

location
Rangul (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 433,300
estimate
Ksh 183,300

Rae Mixed Primary School

location
North Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 410,000
estimate
Ksh 410,000

ThuRoadibuoro Primary School

location
Thurtiboro (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 400,000
estimate
Ksh 200,000

Rakwaro Primary School

location
South West Nyakach (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 400,000
estimate
Ksh 360,000

Omwango Primary School

location
Thurtiboro (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 400,000
estimate
Ksh 200,000

Nyamanyinya Primary School

location
South West Nyakach (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 400,000
estimate
Ksh 200,000

Kokungu Primary School

location
North Eastnyakach (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
-
total cost
Ksh 400,000
estimate
Ksh 100,000

Konditi Primary School

location
Nyalunya (in Nyakach)
year first funded
2008
action
Plastering Of Four Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 400,000
estimate
Ksh 400,000

Rangul Crush Pen

location
Rangul (in Nyakach)
year first funded
2008
action
Construction of 4 Crush- Pens
output
4 Crush- Pens
implementation status
Ongoing
total cost
Ksh 400,000
estimate
Ksh 400,000

Nyamarimba Maternity

location
South Nyakach (in Nyakach)
year first funded
2003
action
Construction of Maternity Ward
output
Maternity Ward
implementation status
Complete
total cost
Ksh 360,000
estimate
Ksh 360,000

Othith Primary School

location
Oboch (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 350,000
estimate
Ksh 350,000

Lower Nyakach Divisional H/Q

location
PapOnditi (in Nyakach)
year first funded
2008
action
Wiring Of Administrative Police Houses.
output
Electricity
implementation status
On Going
total cost
Ksh 350,000
estimate
Ksh 0

Bodi Mixed Secondary School

location
South Nyakach (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 340,000
estimate
Ksh 340,000

Obwon Primary School

location
South West Nyakach (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 300,000
estimate
Ksh 300,000

Innis Primary School

location
Oboch (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 300,000

Kagwel Primary School Scool

location
Asao (in Nyakach)
year first funded
2008
action
Plastering Of 3 Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 300,000

Ochwado Primary School

location
North (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 300,000

Olwalo Primary School

location
Central (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 300,000

Sigoti Primary School

location
East (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 300,000

Lisana Primary School

location
Asawo (in Nyakach)
year first funded
2004
action
Construction of 2 Classrooms
output
2 Classrooms
implementation status
Painting
total cost
Ksh 300,000
estimate
Ksh 300,000

Oboch Primary School

location
Oboch (in Nyakach)
year first funded
2008
action
Construction Of Classrooms
output
-
implementation status
not known
total cost
Ksh 300,000
estimate
Ksh 300,000

Wenwa Primary School

location
North East Nyakach (in Nyakach)
year first funded
2004
action
Construction of 2 Classrooms
output
2 Classrooms
implementation status
Lintel Level
total cost
Ksh 300,000
estimate
Ksh 150,000

Bolo Girls Secondary School

location
Thurdibuoro (in Nyakach)
year first funded
2008
action
Plastering Of Classroom
output
Classrooms
implementation status
On Going
total cost
Ksh 300,000
estimate
Ksh 300,000

Moro Secondary School

location
South Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 300,000
estimate
Ksh 100,000

St. Charles Lwanga Ndori

location
East Nyakach (in Nyakach)
year first funded
2007
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 300,000
estimate
Ksh 100,000

Central Nyakach Water Project

location
PapOnditi (in Nyakach)
year first funded
2006
action
Construction of Water
output
Water
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 300,000

Kamichura Water Project

location
East Nyakach (in Nyakach)
year first funded
2006
action
Water Project
output
Water
implementation status
On Going
total cost
Ksh 300,000
estimate
Ksh 300,000

Upper Nyalunya Water Project

location
PapOnditi (in Nyakach)
year first funded
2006
action
Construction of Water
output
Water
implementation status
Ongoing
total cost
Ksh 300,000
estimate
Ksh 300,000

Siany Primary School

location
South Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 295,000
estimate
Ksh 95,000

Chiefs Office

location
Nyalunya (in Nyakach)
year first funded
2004
action
Construction of Chief's Camp
output
Chief?S Camp
implementation status
Complete
total cost
Ksh 250,000
estimate
Ksh 200,000

Nyakach Girls

location
Oboch (in Nyakach)
year first funded
2007
action
Built Water Tank
output
-
implementation status
not known
total cost
Ksh 250,000
estimate
Ksh 250,000

Bishop Ngala Sec

location
Oboch (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
On Going
total cost
Ksh 250,000
estimate
Ksh 250,000

Otho Abwao Primary School

location
Thurdibuoro (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 250,000
estimate
Ksh 250,000

Olembo Primary School

location
PapOnditi (in Nyakach)
year first funded
2008
action
Roofing Of 3 Classrooms
output
Classrooms
implementation status
Not Yet Started
total cost
Ksh 250,000
estimate
Ksh 250,000

Mbugra Primary School

location
Thurdibuoro (in Nyakach)
year first funded
2008
action
Construction Of Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 250,000
estimate
Ksh 250,000

Kusa Primary School

location
Nyalunya (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 250,000
estimate
Ksh 250,000

Kawili Primary School

location
Central (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 250,000
estimate
Ksh 250,000

Akado Primary School

location
East (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 250,000
estimate
Ksh 250,000

Kabuya Primary School

location
Nyalunya (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 250,000
estimate
Ksh 250,000

Anding'o Olasi Primary School

location
Thurdibuoro (in Nyakach)
year first funded
2008
action
Construction Of 1 Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 250,000
estimate
Ksh 250,000

Kamtudi Primary School

location
Thurdibuoro (in Nyakach)
year first funded
2008
action
Construction Of 1 Classroom
output
Classrooms
implementation status
Ongoing
total cost
Ksh 250,000
estimate
Ksh 250,000

Kandiege Primary School

location
PapOnditi (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 245,555
estimate
Ksh 45,555

Ngege Primary School

location
South Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 212,500
estimate
Ksh 112,500

Obuora Primary School

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 210,000
estimate
Ksh 10,000

Pedo Primary School

location
Central Nyakach (in Nyakach)
year first funded
2003
action
Construction of 2 Classrooms
output
2 Classrooms
implementation status
Doors And Windows Fitting Plastering
total cost
Ksh 210,000
estimate
Ksh 160,000

Pap-Onditi Police

location
Pap Onditi (in Nyakach)
year first funded
2006
action
Construction Of Police Post
output
Police Post
implementation status
Not Started
total cost
Ksh 200,000
estimate
Ksh 500,000

Bishop Okumu Sec

location
Oboch (in Nyakach)
year first funded
2008
action
Construction Of Classroom
output
Classrooms
implementation status
On Going
total cost
Ksh 200,000
estimate
Ksh 200,000

Olwalo Primary School

location
Central Nyakach (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Completed
total cost
Ksh 200,000
estimate
Ksh 200,000

Ngope Primary School

location
South West Nyakach (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 200,000
estimate
Ksh 250,000

Kamtudi Primary School

location
Thurtiboro (in Nyakach)
year first funded
2006
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 200,000
estimate
Ksh 200,000

Nyaksure Primary School

location
PapOnditi (in Nyakach)
year first funded
2008
action
Roofing Of Classroom And Administration Block
output
Classrooms
implementation status
Ongoing
total cost
Ksh 200,000
estimate
Ksh 200,000

Kodum Primary School

location
PapOnditi (in Nyakach)
year first funded
2008
action
Plastering Of Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 200,000
estimate
Ksh 200,000

Pap Lisana Primary School

location
PapOnditi (in Nyakach)
year first funded
2003
action
Fencing & Construction
output
3 Clasess & Fences For 453 Pupils
implementation status
On Going
total cost
Ksh 195,555
estimate
Ksh 295,555

Onyuogo R Primary School

location
PapOnditi (in Nyakach)
year first funded
2003
action
Construction of 1 Classroom
output
1 Classroom
implementation status
Foundation
total cost
Ksh 195,555
estimate
Ksh 195,555

Tulu Primary School

location
Nyalunya (in Nyakach)
year first funded
2003
action
Constructin
output
Classrooms
implementation status
Lintel Level
total cost
Ksh 175,000
estimate
Ksh 25,000

Bur Kamwana Primary School

location
Central Nyakach (in Nyakach)
year first funded
2003
action
Construction of 8 Classrooms
output
8 Classrooms
implementation status
Finishing
total cost
Ksh 160,000
estimate
Ksh 160,000

Olwa Primary School

location
South Nyakach (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 160,000
estimate
Ksh 160,000

Magunga Primary School

location
North East Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 155,000
estimate
Ksh 155,000

Anding'o Ulasi Primary School

location
Thurtiboro (in Nyakach)
year first funded
2006
action
Construction of 7 Classes
output
7 Classes
implementation status
Ongoing
total cost
Ksh 150,000
estimate
Ksh 150,000

Kabete Primary School

location
South Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 150,000
estimate
Ksh 250,000

Nyalwalo Primary School

location
West Nyakach (in Nyakach)
year first funded
2006
action
Construction of 2 Class Rooms
output
2 Class Rooms
implementation status
not known
total cost
Ksh 150,000
estimate
Ksh 150,000

Miriu Primary School

location
Oboch (in Nyakach)
year first funded
2008
action
Rennovation Of Classrooms
output
Classrooms
implementation status
Ongoing
total cost
Ksh 150,000
estimate
Ksh 150,000

Kowire Primary School

location
North East Nyakach (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 140,000
estimate
Ksh 290,000

Nyabola Primary School

location
Nyalunya (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 135,000
estimate
Ksh 35,000

Ochol Primary School

location
South Nyakach (in Nyakach)
year first funded
2004
action
Wiring Of Classes
output
Lighting Of School
implementation status
Complete
total cost
Ksh 112,500
estimate
Ksh 212,500

Kogola Primary School

location
PapOnditi (in Nyakach)
year first funded
2005
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 100,000
estimate
Ksh 100,000

Nyadina Secondary School

location
West Nyakach (in Nyakach)
year first funded
2006
action
Construction of 2 Classes
output
2 Classes
implementation status
Floor Finishing
total cost
Ksh 100,000
estimate
Ksh 100,000

Magunga Secondary School

location
North East Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 85,000
estimate
Ksh 55,000

Dirubi Mixed Secondary School

location
South Nyakach (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 70,000
estimate
Ksh 70,000

Kawili Primary School

location
Central Nyakach (in Nyakach)
year first funded
2003
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 60,000
estimate
Ksh 210,000

Odhong Primary School

location
South Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 60,000
estimate
Ksh 60,000

Regen MPrimary School

location
Central Nyakach (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 50,000
estimate
Ksh 50,000

Ogilo Komulo Primary School

location
Central Nyakach (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 50,000
estimate
Ksh 50,000

St. Peters Kogola Primary School

location
PapOnditi (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 45,555
estimate
Ksh 45,555

Kodum Primary School

location
PapOnditi (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 45,555
estimate
Ksh 45,555

Moro Primary School

location
PapOnditi (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 45,555
estimate
Ksh 45,555

Bugo Primary School

location
Nyalunya (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 40,000
estimate
Ksh 40,000

Obugi Primary School

location
Nyalunya (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 40,000
estimate
Ksh 40,000

Thurgem Secondary School

location
North East Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 40,000
estimate
Ksh 40,000

Kusa Primary School

location
Nyalunya (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
On Going
total cost
Ksh 40,000
estimate
Ksh 40,000

Achi-Ngure Primary School

location
South West Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 30,000
estimate
Ksh 50,000

Pawtenge Primary School

location
North East Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 30,000
estimate
Ksh 30,000

Akado Primary School

location
East Nyakach (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 25,000
estimate
Ksh 25,000

Oremo Primary School

location
North Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 20,000
estimate
Ksh 20,000

Rae Girls Secondary School

location
North Nyakach (in Nyakach)
year first funded
2004
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 20,000
estimate
Ksh 20,000

Rae Primary School

location
Asawo (in Nyakach)
year first funded
2004
action
Construction of Classrooms
output
Classrooms
implementation status
On Going
total cost
Ksh 20,000
estimate
Ksh 20,000

Miriu Primary School

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Nyalnganya Primary School

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Oboch Primary School

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Othith Primary School

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Ramula Odowa Primary School

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Sigoti Primary School

location
East Nyakach (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Kajimbo Primary School

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Chachi Primary School

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Apoko Primary School

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Anis Education Centre

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Nyakach Mixed Primary School

location
Oboch (in Nyakach)
year first funded
2003
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 10,000
estimate
Ksh 10,000

Nyamarimba Primary School

location
South West Nyakach (in Nyakach)
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 0
estimate
Ksh 50,000

Bungu Mary Primary School

location
South West Nyakach (in Nyakach)
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 0
estimate
Ksh 50,000

Barkawarinda Primary School

location
South West Nyakach (in Nyakach)
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 0
estimate
Ksh 50,000

Anding'o Bware Primary School

location
South West Nyakach (in Nyakach)
action
Rehabilitation
output
Classrooms
implementation status
Complete
total cost
Ksh 0
estimate
Ksh 50,000

Odino Water Project

location
South West Nyakach (in Nyakach)
action
Water Project
output
Water
implementation status
On Going
total cost
Ksh 0
estimate
Ksh 400,000