The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.

It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

Projects in Nyando

Nyang`Ande Health Centre

location
Kawino (in Nyando)
year first funded
2003
action
Construction of Dispensary Block & 2 Staff Houses
output
Out-Patient Block & 2 Staff Houses
implementation status
Complete & In Use
total cost
Ksh 5,150,000
estimate
Ksh 5,000,000

Arombo Secondary School

location
Kawino (in Nyando)
year first funded
2008
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
On-Going
total cost
Ksh 5,000,000
estimate
Ksh 2,000,000

Nyakongo Dispensary

location
Wawidhi (in Nyando)
year first funded
2003
action
Construction of Maternity Block & 2 Staff Houses
output
Maternity Ward & 2 Staff Houses
implementation status
Complete
total cost
Ksh 4,660,000
estimate
Ksh 4,000,000

Konim Secondary School

location
Onjiko (in Nyando)
year first funded
2004
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
Complete & In Use
total cost
Ksh 4,000,000
estimate
Ksh 4,000,000

Olasi Dispensary

location
East Kano (in Nyando)
year first funded
2003
action
Construction of Dispensary Block & 2 Staff Houses
output
Out-Patient Block & 2 Staff Houses
implementation status
Complete & In Use
total cost
Ksh 3,850,000
estimate
Ksh 4,100,000

Okanja Secondary School

location
Kakola (in Nyando)
year first funded
2005
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
Complete & In Use
total cost
Ksh 3,800,000
estimate
Ksh 3,750,000

Pala Secondary School

location
Awasi (in Nyando)
year first funded
2006
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
On-Going
total cost
Ksh 3,750,000
estimate
Ksh 4,500,000

Nyakakana Secondary School

location
Kochieng (in Nyando)
year first funded
2004
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
Complete & In Use
total cost
Ksh 3,700,000
estimate
Ksh 3,650,000

Wanga`Nga Secondary School

location
Awasi (in Nyando)
year first funded
2006
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
On-Going
total cost
Ksh 3,550,000
estimate
Ksh 0

Apondo Secondary School

location
Wawidhi (in Nyando)
year first funded
2006
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
On-Going
total cost
Ksh 3,425,000
estimate
Ksh 4,500,000

Karanda Secondary School

location
Kakola (in Nyando)
year first funded
2006
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
On-Going
total cost
Ksh 3,350,000
estimate
Ksh 4,600,000

St. Camulus Ogwedhi Secondary School

location
Wawidhi (in Nyando)
year first funded
2006
action
Laboratory & 2 Classrooms
output
Construction Of Laboratory & 2 Classrooms
implementation status
On-Going
total cost
Ksh 3,325,000
estimate
Ksh 0

Oren Secondary School

location
Awasi (in Nyando)
year first funded
2004
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
Complete & In Use
total cost
Ksh 3,320,000
estimate
Ksh 3,270,000

Ayucha Secondary School

location
Awasi (in Nyando)
year first funded
2004
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
Complete & In Use
total cost
Ksh 3,200,000
estimate
Ksh 3,200,000

Holo Orucho Water Project

location
East Kano (in Nyando)
year first funded
2005
action
Distribution Of Water To The Sorrounding Homes
output
Piped Water To The Community
implementation status
On-Going
total cost
Ksh 3,000,000
estimate
Ksh 0

Rabuor Health Centre

location
Kochieng (in Nyando)
year first funded
2004
action
Construction Of Maternity Ward
output
Maternity Ward
implementation status
On-Going
total cost
Ksh 2,850,000
estimate
Ksh 2,850,000

Kowuor Primary School

location
Kochogo (in Nyando)
year first funded
2005
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
Complete & In Use
total cost
Ksh 2,825,000
estimate
Ksh 2,825,000

Masogo Dispensary

location
Kombura (in Nyando)
year first funded
2005
action
Construction Of Dispensary
output
Out-Patient Block
implementation status
Complete & In Use
total cost
Ksh 2,725,000
estimate
Ksh 2,225,000

East Kano Location Chief's Camp

location
East Kano (in Nyando)
year first funded
2004
action
Construction Of Chiefs Office And Social Hall
output
Chiefs Offices & Social Hall
implementation status
Complete & In Use
total cost
Ksh 2,550,000
estimate
Ksh 0

Arombo Access Road

location
Kawino (in Nyando)
year first funded
2005
action
Construction Of Access Road To The School
output
Access Road To Arombo Sec School
implementation status
On-Going
total cost
Ksh 2,550,000
estimate
Ksh 0

Kobura Girls Secondary School

location
Kombura (in Nyando)
year first funded
2007
action
Construction Of (4) Classrooms & Admin. Block
output
4 Classrooms & Admin. Block
implementation status
On-Going
total cost
Ksh 2,408,000
estimate
Ksh 4,200,000

Kanyagwal Health Centre

location
Kanyagwal (in Nyando)
year first funded
2004
action
Construction Of Dispensary
output
Out-Patient Block
implementation status
Complete & In Use
total cost
Ksh 2,400,000
estimate
Ksh 2,400,000

Bunde Health Centre

location
Kakola (in Nyando)
year first funded
2003
action
Construction Of Maternity Ward
output
Maternity Ward
implementation status
On-Going
total cost
Ksh 2,200,000
estimate
Ksh 1,750,000

Katolo Mixed Secondary School

location
East Kano (in Nyando)
year first funded
2008
action
Construction of 6 Classrooms
output
6 Classrooms
implementation status
On-Going
total cost
Ksh 2,050,000
estimate
Ksh 6,000,000

Ahero Girls Secondary School

location
Kakola (in Nyando)
year first funded
2008
action
Construction Of (4) Classrooms
output
4 Classrooms
implementation status
On-Going
total cost
Ksh 2,000,000
estimate
Ksh 0

Kodete-Wangneno Road

location
East Kano (in Nyando)
year first funded
2008
action
Grading Of Road
output
Graded Road
implementation status
not known
total cost
Ksh 2,000,000
estimate
Ksh 0

Migingo Secondary School

location
Kochieng (in Nyando)
year first funded
2004
action
Construction of Admin & Tuition Block
output
Admin & Tuition Block
implementation status
Complete & In Use
total cost
Ksh 2,000,000
estimate
Ksh 1,200,000

Rabuor Primary School

location
Kochieng (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 2,000,000
estimate
Ksh 2,000,000

Holo Dispensary

location
East Kano (in Nyando)
year first funded
2005
action
Construction Of Dispensary
output
Out-Patient Block
implementation status
Complete But Not In Use
total cost
Ksh 1,925,000
estimate
Ksh 1,925,000

Nyamware Primary School

location
Kochieng (in Nyando)
year first funded
2007
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 1,913,501
estimate
Ksh 0

Onjiko Secondary School

location
Kakola (in Nyando)
year first funded
2006
action
Murraming Of The Access Road To The School
output
Road
implementation status
Complete & In Use
total cost
Ksh 1,900,000
estimate
Ksh 0

Ombaka Secondary School

location
Kakola (in Nyando)
year first funded
2007
action
Construction Of (4) Classrooms & Admin. Block
output
5 Classrooms & Admin. Block
implementation status
On-Going
total cost
Ksh 1,900,000
estimate
Ksh 3,800,000

Bunde Secondary School

location
Kakola (in Nyando)
year first funded
2005
action
Construction Of Administration Block
output
Administration Block
implementation status
Complete & In Use
total cost
Ksh 1,850,000
estimate
Ksh 1,800,000

Ahero Sub Distrct Hospital

location
Kakola (in Nyando)
year first funded
2007
action
Construction Of Theatre
output
Theatre
implementation status
On-Going
total cost
Ksh 1,850,000
estimate
Ksh 11,000,000

Kochogo Secondary School

location
Kochogo (in Nyando)
year first funded
2005
action
Construction of Laboratory & 2 Classrooms
output
Laboratory & 2Classrooms
implementation status
Lab Complete & In Use. Classroms On-Going
total cost
Ksh 1,845,000
estimate
Ksh 795,000

Withur Water Project

location
Bwanda (in Nyando)
year first funded
2003
action
Rehabilitation & Reticulation Of Water
output
Piped Water To The Community
implementation status
Stalled
total cost
Ksh 1,800,000
estimate
Ksh 1,800,000

Rabuor Water Project

location
Kochieng (in Nyando)
year first funded
2006
action
Reticulation Of Water
output
Piped Water To The Community
implementation status
Complete & In Use
total cost
Ksh 1,665,000
estimate
Ksh 1,165,000

Nduru Secondary School

location
Kawino (in Nyando)
year first funded
2008
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 1,600,000
estimate
Ksh 1,800,000

Kogwedhi Primary School

location
Wawidhi (in Nyando)
year first funded
2004
action
Construction Of (4) Classrooms
output
4 Classrooms
implementation status
On-Going
total cost
Ksh 1,550,000
estimate
Ksh 0

Alendu Ayweyo Water

location
Wawidhi (in Nyando)
year first funded
2005
action
Distribution Of Water To The Sorrounding Homes
output
Piped Water To The Community
implementation status
On-Going
total cost
Ksh 1,500,000
estimate
Ksh 0

West Kano Kadhiambo Out Growers Rice Schooleme

location
Kawino (in Nyando)
year first funded
2007
action
Rehabilitation Of Irrigation Scheme
output
Rehabilitated Water Canals
implementation status
On-Going
total cost
Ksh 1,500,000
estimate
Ksh 0

Awasi Water Project

location
Awasi (in Nyando)
year first funded
2005
action
Distribution Of Water To The Sorrounding Homes
output
Piped Water To The Community
implementation status
On-Going
total cost
Ksh 1,450,000
estimate
Ksh 0

Alendu Secondary School

location
Kochieng (in Nyando)
year first funded
2005
action
Construction Of (2) Classrooms Block
output
2 Classrooms
implementation status
Complete & In Use
total cost
Ksh 1,450,000
estimate
Ksh 1,400,000

Disi Primary School

location
Kochogo (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
Complete & In Use
total cost
Ksh 1,400,000
estimate
Ksh 0

Lela Primary School

location
Kombura (in Nyando)
year first funded
2008
action
Construction Of (3) Classrooms
output
3 Classroom
implementation status
Complete & In Use
total cost
Ksh 1,400,000
estimate
Ksh 0

Kolal Primary School

location
Kawino (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
Complete & In Use
total cost
Ksh 1,400,000
estimate
Ksh 0

Obugi Primary School

location
Kochogo (in Nyando)
year first funded
2005
action
Construction Of (3) Classrooms & Fecing
output
3 Classrooms
implementation status
Complete & In Use
total cost
Ksh 1,375,000
estimate
Ksh 0

Mao Primary School

location
Kawino (in Nyando)
year first funded
2006
action
Construction Of (4) Classrooms
output
4 Classrooms
implementation status
On-Going
total cost
Ksh 1,350,000
estimate
Ksh 0

St. Christopher Ayweyo Secondary School

location
Onjiko (in Nyando)
year first funded
2004
action
Construction of 2 Classroom Block
output
2 Classrooms
implementation status
Complete & In Use
total cost
Ksh 1,350,000
estimate
Ksh 1,350,000

Bungu Koraga Primary School

location
Kochieng (in Nyando)
year first funded
2007
action
Construction Of (5) Classrooms
output
5 Classrooms
implementation status
On-Going
total cost
Ksh 1,350,000
estimate
Ksh 0

Kamunda Primary School

location
Awasi (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
Complete & In Use
total cost
Ksh 1,300,000
estimate
Ksh 0

Osino Primary School

location
Kakola (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
Complete But Not In Use
total cost
Ksh 1,300,000
estimate
Ksh 1,300,000

Boya Water Project

location
Onjiko (in Nyando)
year first funded
2006
action
Distribution Of Water To The Sorrounding Homes
output
Piped Water To The Community
implementation status
Complete & In Use
total cost
Ksh 1,265,000
estimate
Ksh 1,500,000

Ojere Primary School

location
Kochogo (in Nyando)
year first funded
2005
action
Construction Of (6) Classrooms
output
6 Classrooms
implementation status
On-Going
total cost
Ksh 1,250,000
estimate
Ksh 0

Kokwoyo Water Project

location
Wawidhi (in Nyando)
year first funded
2003
action
Distribution Of Water To The Sorrounding Homes
output
Piped Water To The Community
implementation status
Stalled
total cost
Ksh 1,220,000
estimate
Ksh 0

Alendu Primary School

location
Kochieng (in Nyando)
year first funded
2006
action
Construction Of (4) Classrooms
output
4 Classrooms
implementation status
On-Going
total cost
Ksh 1,200,000
estimate
Ksh 0

Onongno Primary School

location
Kombura (in Nyando)
year first funded
2005
action
Construction Of (3) Classrooms & Pit Latrines
output
4 Classrooms & Pit Latrines
implementation status
On-Going
total cost
Ksh 1,200,000
estimate
Ksh 0

Odienya Primary School

location
Kawino (in Nyando)
year first funded
2005
action
Construction Of (2) Classrooms
output
2 Classrooms
implementation status
On-Going
total cost
Ksh 1,150,000
estimate
Ksh 0

Withur Primary School

location
Bwanda (in Nyando)
year first funded
2008
action
Construction Of Pit Latrines & 2 Classrooms
output
Pit Latrines Lassrooms
implementation status
Complete & In Use
total cost
Ksh 1,100,000
estimate
Ksh 0

Mbega Primary School

location
Kochieng (in Nyando)
year first funded
2005
action
Construction Of (8) Classrooms
output
8 Classrooms
implementation status
On-Going
total cost
Ksh 1,100,000
estimate
Ksh 0

Nyomwaro Primary School

location
Kochogo (in Nyando)
year first funded
2004
action
Construction Of (4) Classrooms
output
4 Classrooms
implementation status
On-Going
total cost
Ksh 1,100,000
estimate
Ksh 0

Dispensary In Onjiko Location

location
Onjiko (in Nyando)
year first funded
2007
action
Out-Patient Block
output
Out-Patient Block
implementation status
Stalled
total cost
Ksh 1,093,681
estimate
Ksh 1,093,681

Otieno Oyoo Secondary School

location
Kochieng (in Nyando)
year first funded
2009
action
Purchase Of School Bus
output
School Bus
implementation status
not known
total cost
Ksh 1,000,000
estimate
Ksh 0

Traders Sheds At Ahero Market

location
Kakola (in Nyando)
year first funded
2009
action
n/a
output
-
implementation status
not known
total cost
Ksh 1,000,000
estimate
Ksh 0

Nyalenda Water Project

location
Onjiko (in Nyando)
year first funded
2005
action
Distribution Of Water To The Sorrounding Homes
output
Piped Water To The Community
implementation status
On-Going
total cost
Ksh 1,000,000
estimate
Ksh 0

Kolunga Water Project

location
Onjiko (in Nyando)
year first funded
2005
action
Distribution Of Water To The Sorrounding Homes
output
Piped Water To The Community
implementation status
On-Going
total cost
Ksh 1,000,000
estimate
Ksh 0

Angoro Primary School

location
Awasi (in Nyando)
year first funded
2006
action
Construction Of (2) Skeleton Classrooms
output
2 Classrooms
implementation status
On-Going
total cost
Ksh 1,000,000
estimate
Ksh 0

Kokwoyo Primary School

location
Onjiko (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 995,291
estimate
Ksh 0

Ojienda Primary School

location
Awasi (in Nyando)
year first funded
2005
action
Completion Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 950,000
estimate
Ksh 0

Onera Primary School

location
Awasi (in Nyando)
year first funded
2006
action
Completion Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 950,000
estimate
Ksh 0

Ugwe Primary School

location
Kawino (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 950,000
estimate
Ksh 0

Onjiko Kobongo Primary School

location
Onjiko (in Nyando)
year first funded
2005
action
Construction Of (4) Classrooms
output
4 Classrooms
implementation status
On-Going
total cost
Ksh 920,000
estimate
Ksh 0

Boya Primary School

location
Onjiko (in Nyando)
year first funded
2007
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
Complete And In Use
total cost
Ksh 900,000
estimate
Ksh 0

Bunde Primary School

location
Kakola (in Nyando)
year first funded
2006
action
Construction Of (4) Classrooms
output
4 Classrooms
implementation status
On-Going
total cost
Ksh 900,000
estimate
Ksh 0

Kibarwa Primary School

location
Kawino (in Nyando)
year first funded
2008
action
Construction of 2 Classrooms
output
2 Classrooms
implementation status
Complete & In Use
total cost
Ksh 900,000
estimate
Ksh 0

Siany Kabonyo Primary School

location
Kawino (in Nyando)
year first funded
2008
action
Construction Of (2) Classrooms
output
2 Classrooms
implementation status
On-Going
total cost
Ksh 900,000
estimate
Ksh 0

Kombura Chiefs Camp

location
Kombura (in Nyando)
year first funded
2006
action
Construction Of Chiefs Office
output
Chiefs Office
implementation status
On-Going
total cost
Ksh 900,000
estimate
Ksh 0

Kamita Primary School

location
Onjiko (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 900,000
estimate
Ksh 0

Reru Primary School

location
Bwanda (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 825,000
estimate
Ksh 0

Masune Ayweyo Rice Schooleme

location
Onjiko (in Nyando)
year first funded
2007
action
Rehabilitation Of Irrigation Scheme
output
Rehabilitated Water Canals
implementation status
Complete & In Use
total cost
Ksh 820,000
estimate
Ksh 0

Nyachoda Irrigation Schooleme

location
Wawidhi (in Nyando)
year first funded
2007
action
Rehabilitation Of Irrigation Scheme
output
Rehabilitated Water Canals
implementation status
On-Going
total cost
Ksh 800,000
estimate
Ksh 0

Kakola/Tura Irrig Schooleme

location
Kakola (in Nyando)
year first funded
2007
action
Rehabilitation Of Irrigation Scheme
output
Rehabilitated Water Canals
implementation status
Stalled
total cost
Ksh 800,000
estimate
Ksh 0

Kadete Primary School

location
Bwanda (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
2 Classrooms
implementation status
Complete & In Use
total cost
Ksh 775,000
estimate
Ksh 0

Nyalenda Primary School

location
Onjiko (in Nyando)
year first funded
2006
action
Construction of Administration Block
output
Administration Block
implementation status
Complete & In Use
total cost
Ksh 750,000
estimate
Ksh 0

Ogenya Primary School

location
Bwanda (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 750,000
estimate
Ksh 0

Bondo Kachola Primary School

location
Awasi (in Nyando)
year first funded
2005
action
Construction Of (4) Classrooms
output
4 Classrooms
implementation status
On-Going
total cost
Ksh 750,000
estimate
Ksh 0

Awach Irrigation Schooleme

location
East Kano (in Nyando)
year first funded
2007
action
Rehabilitation Of Irrigation Scheme
output
Rehabilitated Water Canals
implementation status
On-Going
total cost
Ksh 722,676
estimate
Ksh 0

Nyang`Ande Primary School

location
Kawino (in Nyando)
year first funded
2006
action
Completion Of (2) Classrooms Block
output
2 Classrooms
implementation status
On-Going
total cost
Ksh 708,000
estimate
Ksh 0

Sare Primary School

location
East Kano (in Nyando)
year first funded
2009
action
Plastering Of 8 Classrooms
output
-
implementation status
not known
total cost
Ksh 700,000
estimate
Ksh 0

Kanyangoro Primary School

location
East Kano (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 700,000
estimate
Ksh 0

Wanganga Bridge

location
Awasi (in Nyando)
year first funded
2007
action
Construction of Bridge On Nyaitho Stream
output
Bridge
implementation status
Complete & In Use
total cost
Ksh 700,000
estimate
Ksh 0

Karombe Primary School

location
Kombura (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 675,000
estimate
Ksh 0

Kasangany Primary School

location
Bwanda (in Nyando)
year first funded
2005
action
Construction of 2 Classrooms & Admin Block
output
2 Classrooms & Admin Block
implementation status
On-Going
total cost
Ksh 650,000
estimate
Ksh 0

Korwana Primary School

location
Kawino (in Nyando)
year first funded
2005
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 650,000
estimate
Ksh 0

Nyamurundu Primary School

location
Kawino (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 600,000
estimate
Ksh 0

Achego Primary School

location
(in Nyando)
year first funded
2009
action
Construction Of (1) Classrooms
output
One Classroom
implementation status
On-Going
total cost
Ksh 600,000
estimate
Ksh 0

Wanga`Nga Primary School

location
Awasi (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 600,000
estimate
Ksh 0

Rongo Primary School

location
Kochieng (in Nyando)
year first funded
2008
action
Construction Of Pit Latrine
output
Pit Latrine
implementation status
Complete & In Use
total cost
Ksh 600,000
estimate
Ksh 0

Onjiko Primary School

location
Kochogo (in Nyando)
year first funded
2006
action
Completion Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 575,000
estimate
Ksh 0

Kandaria Primary School

location
Kawino (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 550,000
estimate
Ksh 0

Miguye Primary School

location
Kochieng (in Nyando)
year first funded
2007
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 550,000
estimate
Ksh 0

Bonde Kakoko Primary School

location
Kombura (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
Complete And In Use
total cost
Ksh 525,000
estimate
Ksh 0

Nyarombe Primary School

location
East Kano (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 500,000
estimate
Ksh 0

Nyakakana Primary School

location
Kochieng (in Nyando)
year first funded
2009
action
Construction Of (1) Classroom
output
1 Classroom
implementation status
On-Going
total cost
Ksh 500,000
estimate
Ksh 0

Korowe Primary School

location
Kombura (in Nyando)
year first funded
2007
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 500,000
estimate
Ksh 0

Kochieng Primary School

location
Kochieng (in Nyando)
year first funded
2009
action
Construction Of (1) Classroom
output
1 Classroom
implementation status
Complete & In Use
total cost
Ksh 500,000
estimate
Ksh 0

Kawino Water Project

location
Kawino (in Nyando)
year first funded
2009
action
Distribution Of Water To The Sorrounding Homes
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 0

East Kochieng Water Project

location
Kochieng (in Nyando)
year first funded
2008
action
Distribution Of Water To The Sorrounding Homes
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 0

Alendu Water Project

location
Kochieng (in Nyando)
year first funded
2008
action
Distribution Of Water To The Sorrounding Homes
output
Piped Water To The Community
implementation status
On-Going
total cost
Ksh 500,000
estimate
Ksh 0

Ombaka Primary School

location
Bwanda (in Nyando)
year first funded
2009
action
n/a
output
-
implementation status
not known
total cost
Ksh 500,000
estimate
Ksh 0

Nyakongo Primary School

location
Wawidhi (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 475,000
estimate
Ksh 0

Okiro Primary School

location
Onjiko (in Nyando)
year first funded
2005
action
Construction Of (4) Classrooms
output
4 Classrooms
implementation status
On-Going
total cost
Ksh 470,000
estimate
Ksh 0

Akwanya Primary School

location
Awasi (in Nyando)
year first funded
2005
action
Reconstruction Of Damaged Classrooms
output
Rehabilitated Classrooms
implementation status
Complete & In Use
total cost
Ksh 460,000
estimate
Ksh 460,000

Kochogo Chiefs Camp

location
Kochogo (in Nyando)
year first funded
2006
action
Construction Of Chiefs Office
output
Chiefs Office
implementation status
Stalled
total cost
Ksh 450,000
estimate
Ksh 0

Luora Ayweyo Primary School

location
Wawidhi (in Nyando)
year first funded
2009
action
Construction Of (1) Classroom
output
1 Classroom
implementation status
not known
total cost
Ksh 400,000
estimate
Ksh 0

Kobura Primary School

location
Kombura (in Nyando)
year first funded
2005
action
Construction Of (2) Classrooms
output
2 Classrooms
implementation status
On-Going
total cost
Ksh 400,000
estimate
Ksh 0

Yogo Primary School

location
East Kano (in Nyando)
year first funded
2006
action
Reconstruction Of Damaged Classrooms
output
Rehabilitated Classrooms
implementation status
Complete & In Use
total cost
Ksh 400,000
estimate
Ksh 0

Kagimba Primary School

location
Kochogo (in Nyando)
year first funded
2008
action
Construction Of Pit Latrines & Plastering Of 8 Classrooms
output
Pit Latrine
implementation status
Complete & In Use
total cost
Ksh 400,000
estimate
Ksh 0

Kasuna Primary School

location
Kakola (in Nyando)
year first funded
2008
action
Construction Of Pit Latrine And Finishing Of Three Classrooms
output
Pit Latrine And Three Classrooms
implementation status
Complete & In Use
total cost
Ksh 400,000
estimate
Ksh 0

Ranjira Primary School

location
Kochieng (in Nyando)
year first funded
2006
action
Construction Of (4) Classrooms
output
4 Classrooms
implementation status
On-Going
total cost
Ksh 400,000
estimate
Ksh 0

Oren Primary School

location
Awasi (in Nyando)
year first funded
2008
action
Construction Of (1) Classroom
output
1 Classroom
implementation status
On-Going
total cost
Ksh 400,000
estimate
Ksh 0

Okana Primary School

location
Kochieng (in Nyando)
year first funded
2008
action
Completion Of (1) Classroom
output
1 Classroom
implementation status
On-Going
total cost
Ksh 400,000
estimate
Ksh 0

Ahero Teachers Education Resource Centre

location
Kakola (in Nyando)
year first funded
2006
action
Construction of Office Block
output
Office Block
implementation status
On-Going
total cost
Ksh 350,000
estimate
Ksh 0

Ahero Town Council

location
Kakola (in Nyando)
year first funded
2006
action
Construction Of Jua Kali Shades
output
Jua Kali Shades
implementation status
On-Going
total cost
Ksh 350,000
estimate
Ksh 0

Kamita Secondary School

location
Wawidhi (in Nyando)
year first funded
2007
action
Construction Of 5 Classrooms & Admin. Block
output
5 Classrooms & Admin. Block
implementation status
Stalled
total cost
Ksh 350,000
estimate
Ksh 4,500,000

Awasi Secondary School

location
Awasi (in Nyando)
year first funded
2006
action
Completion Of (2) Classroom Block
output
2 Classrooms
implementation status
Complete & In Use
total cost
Ksh 350,000
estimate
Ksh 350,000

Apondo Primary School

location
Wawidhi (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 350,000
estimate
Ksh 0

Bwanda Chief's Camp

location
Bwanda (in Nyando)
year first funded
2006
action
Construction Of Chiefs Office
output
Chiefs Office
implementation status
Stalled
total cost
Ksh 300,000
estimate
Ksh 0

Miringo Primary School

location
Onjiko (in Nyando)
year first funded
2006
action
Reconstruction Of Damaged Classrooms
output
Rehabilitated Classrooms
implementation status
Complete & In Use
total cost
Ksh 300,000
estimate
Ksh 0

Kolunga Primary School

location
Onjiko (in Nyando)
year first funded
2005
action
Construction of Admin Block
output
Administration Block
implementation status
Complete & In Use
total cost
Ksh 300,000
estimate
Ksh 0

Holo Orucho Primary School

location
East Kano (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 300,000
estimate
Ksh 0

St. Annes Ahero Primary School

location
Kakola (in Nyando)
year first funded
2005
action
Construction Of Library
output
Library
implementation status
Complete & In Use
total cost
Ksh 300,000
estimate
Ksh 0

Waradho Primary School

location
Wawidhi (in Nyando)
year first funded
2008
action
Construction Of 7 Classrooms And Admin Block
output
7 Classrooms And Administration Block
implementation status
On-Going
total cost
Ksh 300,000
estimate
Ksh 0

Nyamasao Primary School

location
Kakola (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 300,000
estimate
Ksh 0

Ogwedhi Primary School

location
Wawidhi (in Nyando)
year first funded
2007
action
Construction Of (2) Classrooms
output
2 Classrooms
implementation status
On-Going
total cost
Ksh 300,000
estimate
Ksh 0

West Kochieng Location

location
Kochieng (in Nyando)
year first funded
2005
action
Construction Of Chiefs Office
output
Chiefs Office
implementation status
On-Going
total cost
Ksh 280,000
estimate
Ksh 0

Nduru Primary School

location
Kawino (in Nyando)
year first funded
2006
action
Completion Of (2) Classrooms Block
output
2 Classrooms
implementation status
On-Going
total cost
Ksh 207,000
estimate
Ksh 0

Nyachoda Primary School

location
Wawidhi (in Nyando)
year first funded
2008
action
Constructio Of (1) Classrooms
output
1 Classroom
implementation status
On-Going
total cost
Ksh 200,000
estimate
Ksh 0

Arombo Primary School

location
Kawino (in Nyando)
year first funded
2006
action
Construction Of Pit Latrine
output
Pit Latrine
implementation status
Complete & In Use
total cost
Ksh 200,000
estimate
Ksh 0

Ahero Youth Polytechnic

location
Onjiko (in Nyando)
year first funded
2006
action
Rehabilitation Of Classrooms
output
Rehabilitated Classrooms
implementation status
not known
total cost
Ksh 200,000
estimate
Ksh 0

Lela Secondary School

location
Kombura (in Nyando)
year first funded
2008
action
Electrical Wiring
output
Electricity
implementation status
Complete & In Use
total cost
Ksh 120,000
estimate
Ksh 0

Masogo Primary School

location
Kombura (in Nyando)
year first funded
2006
action
Construction Of (3) Classrooms
output
3 Classrooms
implementation status
On-Going
total cost
Ksh 100,000
estimate
Ksh 0

Olasi Primary School

location
East Kano (in Nyando)
year first funded
2008
action
Construction Of Pit Latrine
output
Pit Latrine
implementation status
Complete & In Use
total cost
Ksh 100,000
estimate
Ksh 0

Nyamware North Assistant Chief's Office

location
Kochieng (in Nyando)
year first funded
2008
action
Construction Of Ass. Chief'S Office
output
Ass. Chief'S Office
implementation status
not known
total cost
Ksh 100,000
estimate
Ksh 0

Nyando Do's Office

location
Kakola (in Nyando)
year first funded
2005
action
Electrical Wiring
output
Electricity
implementation status
Complete & In Use
total cost
Ksh 100,000
estimate
Ksh 0

Ayucha Primary School

location
Awasi (in Nyando)
year first funded
2008
action
Construction Of Pit Latrine
output
Pit Latrine
implementation status
Complete & In Use
total cost
Ksh 100,000
estimate
Ksh 0

Kowuor Secondary School

location
Wawidhi (in Nyando)
year first funded
2007
action
Construction Of 6 Classrooms & Admin. Block
output
6 Classrooms & Admin. Block
implementation status
On-Going
total cost
Ksh 58,000
estimate
Ksh 4,500,000

Nyamware Beach

location
Kochieng (in Nyando)
year first funded
2008
action
Electrical Wiring
output
Electricity
implementation status
not known
total cost
Ksh 50,000
estimate
Ksh 0

Nduru Beach

location
Kawino (in Nyando)
year first funded
2008
action
Electrical Wiring
output
Electricity
implementation status
On-Going
total cost
Ksh 50,000
estimate
Ksh 0