It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Asembo Master Water Project
- location
-
East /Central Asembo
(in Rarieda)
- year first funded
- 2005
- action
- Provision of water
- output
- Water available at close distance
- implementation status
- 3m.reallocated
- total cost
- Ksh 10,000,846
- estimate
- Ksh 12,000,000
Nyabera tractor hire services
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Purchase of tractor, plough and trailer
- output
- Improved farming
- implementation status
- Complete & in use
- total cost
- Ksh 3,500,000
- estimate
- Ksh 4,000,000
DO Makasembo School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Purchase of School bus
- output
- Bus
- implementation status
- Complete & in use
- total cost
- Ksh 3,500,000
- estimate
- Ksh 3,500,000
Nyakongo Girls Secondary
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Wiring electrical installation
- output
- Improved educational facilities
- implementation status
- Compete & in use
- total cost
- Ksh 3,200,000
- estimate
- Ksh 3,200,000
Rachar Secondary School
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2003
- action
- Construction of new Secondary School
- output
- Improved educational facilities
- implementation status
- Complete & in use
- total cost
- Ksh 2,960,000
- estimate
- Ksh 3,000,000
St. Philips Wera Secondary School
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2003
- action
- Construction of four Classrooms and lab
- output
- Classrooms and lab
- implementation status
- Complete & in use
- total cost
- Ksh 2,220,000
- estimate
- Ksh 3,000,000
Ndigwa Secondary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of two Classrooms
- output
- Classrooms
- implementation status
- Classrms complete, staff hss going on
- total cost
- Ksh 2,200,000
- estimate
- Ksh 1,300,000
South Asembo water project
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Supply of piped water
- output
- Water available at close distance
- implementation status
- On going
- total cost
- Ksh 2,000,000
- estimate
- Ksh 3,000,000
Pap- Kodero Health Centre
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Construction
- output
- Health centre
- implementation status
- Complete& in use
- total cost
- Ksh 1,960,000
- estimate
- Ksh 2,200,000
Rarieda Secondary School
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2005
- action
- Construction of two Classrooms and purchase of sanatorium equipments an furniture
- output
- Classrooms and equipments
- implementation status
- Complete & in use
- total cost
- Ksh 1,950,000
- estimate
- Ksh 2,000,000
Misori Dispensary
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2003
- action
- Construction of maternity ward, laboratory, male ward and supply of equipment.
- output
- Improved health facilities
- implementation status
- On going-project is at the Linton level
- total cost
- Ksh 1,760,000
- estimate
- Ksh 2,000,000
Mirando –Ong’aro secondary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of laboratory and supply of equipments
- output
- Improved educational facilities
- implementation status
- Complete & in use
- total cost
- Ksh 1,700,000
- estimate
- Ksh 2,000,000
Naya Secondary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of laboratory and supply of equipments
- output
- Equipped laboratory
- implementation status
- Complete & in use
- total cost
- Ksh 1,500,000
- estimate
- Ksh 1,600,000
Chianda High School
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of lab
- output
- Laboratory
- implementation status
- Structure complete
- total cost
- Ksh 1,500,000
- estimate
- Ksh 2,000,000
St. Johns Oboch Secondary
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2005
- action
- Construction of four Classrooms and lab
- output
- Classrooms and lab
- implementation status
- Complete & in use
- total cost
- Ksh 1,500,000
- estimate
- Ksh 2,000,000
Raliew secondary School and Comm. Water system
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Roof catchment water and construction of two Comm. Water tanks
- output
- Water a available at close distance
- implementation status
- Compete & in use
- total cost
- Ksh 1,444,230
- estimate
- Ksh 1,500,000
Lwak Mixed Primary School
- location
-
E. Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 80% complete
- total cost
- Ksh 1,400,000
- estimate
- Ksh 6,800,000
Kandaria borehole
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2005
- action
- Supply of piped water
- output
- Water available at close distance
- implementation status
- Complete & in use
- total cost
- Ksh 1,400,000
- estimate
- Ksh 1,800,000
Masala Secondary School
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Construction of a new Secondary School
- output
- Secondary School
- implementation status
- 2classrooms complete
- total cost
- Ksh 1,400,000
- estimate
- Ksh 3,000,000
Tanga Secondary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of new Secondary School
- output
- Improved educational facilities
- implementation status
- 4 classrms complete
- total cost
- Ksh 1,400,000
- estimate
- Ksh 3,000,000
Bar Aluru Dispensary
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Construction of dispensary and Dr’s House
- output
- Improved health facilities
- implementation status
- Complete
- total cost
- Ksh 1,350,000
- estimate
- Ksh 800,000
Madiany sub-district hospital
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Wiring and electrification
- output
- Electricity installed
- implementation status
- 100% installed
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,800,000
Nyagoko Dispensary
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Construction of maternity ward and supply of equipments
- output
- Maternity ward and equipment
- implementation status
- Complete & in use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,300,000
Siger secondary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2005
- action
- Construction of staff houses
- output
- Staff houses
- implementation status
- Complete & in use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,600,000
D.O. Makasembo Secondary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Construction of Admin. Block
- output
- Admin Block
- implementation status
- Complete & in use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,200,000
Nyamasore secondary School
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of 4 Classrooms
- output
- Classrooms
- implementation status
- Waling complete
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,000,000
Misori AP Residential quarters
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of 4 units, offices and a cell
- output
- Improved security
- implementation status
- Complete & in use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 1,600,000
Ragengni Community Health Centre
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2003
- action
- Construction of a new dispensary
- output
- Dispensaries
- implementation status
- Complete & in use
- total cost
- Ksh 1,260,000
- estimate
- Ksh 1,000,000
Kobonyo Primary School
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Renovation of eight Classrooms
- output
- Improved educ. facilities
- implementation status
- Complete & in use
- total cost
- Ksh 1,260,000
- estimate
- Ksh 1,300,000
Okela Secondary School
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of two Classrooms
- output
- Classrooms
- implementation status
- 60% complete
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,300,000
Kagwa Dispensary
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of maternity ward and supply of equipments
- output
- Improved health facilities
- implementation status
- Complete
- total cost
- Ksh 1,200,000
- estimate
- Ksh 1,300,000
Koudo - Malanga Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Construction of new school
- output
- school
- implementation status
- 2classrooms complete
- total cost
- Ksh 1,140,000
- estimate
- Ksh 1,200,000
Madiany Unit of mentally handicapped
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Construction of Hostel
- output
- Hostel
- implementation status
- Hostel complete & in use
- total cost
- Ksh 1,100,846
- estimate
- Ksh 2,000,000
Mahaya Secondary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Construction of lab
- output
- Laboratory
- implementation status
- Complete & in use
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,100,000
Ochieng’a Pri
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Renovation of 8 Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,300,000
Mumbo Primary
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of 4 Classrooms
- output
- Classrooms
- implementation status
- Pending finishing
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,600,000
Kopiata beach Dispensary
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of a new dispensary
- output
- Dispensary
- implementation status
- 80% Installed
- total cost
- Ksh 1,100,000
- estimate
- Ksh 1,300,000
Tuju Primary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2003
- action
- Construction of four Classrooms
- output
- Improved educational facilities
- implementation status
- Complete & in use
- total cost
- Ksh 1,060,000
- estimate
- Ksh 1,100,000
Naya Dispensary
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2003
- action
- Construction of maternity wing and supply of equipments
- output
- Improved health facilities
- implementation status
- Maternity complete & in use
- total cost
- Ksh 1,060,000
- estimate
- Ksh 1,400,000
Saradidi Secondary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Construction of School
- output
- School
- implementation status
- Started
- total cost
- Ksh 1,000,000
- estimate
- Ksh 2,000,000
Nyabera Secondary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Construction of a new Secondary School
- output
- Secondary School
- implementation status
- 80% complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 3,000,000
Lweya Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Construction of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,400,000
Kounga Dam
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2003
- action
- Excavation of water pan and disiltation
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 960,000
- estimate
- Ksh 500,000
Rageng’ni Primary School
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Renovation of 8 Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 900,000
- estimate
- Ksh 1,300,000
Boi Youth Polytechnic
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Renovation and fencing of the centre
- output
- Improved educational facilities
- implementation status
- Complete & in use
- total cost
- Ksh 900,000
- estimate
- Ksh 900,000
Rarieda Primary School
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Construction of 2 Classrooms
- output
- classrooms
- implementation status
- 2classrms complete
- total cost
- Ksh 900,000
- estimate
- Ksh 1,300,000
Kanyichudo Primary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Construction of two Classrooms +Renovation
- output
- Classrooms
- implementation status
- 2classrms complete & in use, renovation done
- total cost
- Ksh 900,000
- estimate
- Ksh 800,000
Ramba Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 4 complete & in use
- total cost
- Ksh 900,000
- estimate
- Ksh 1,300,000
Ramoya Primary
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Construction of Classrooms
- output
- Classrooms
- implementation status
- Pending finishing
- total cost
- Ksh 900,000
- estimate
- Ksh 1,600,000
Memba Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2007
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 900,000
- estimate
- Ksh 1,200,000
Ndati Bridge
- location
-
E. Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Construction
- output
- Bridge
- implementation status
- Complete
- total cost
- Ksh 876,000
- estimate
- Ksh 876,000
Asembo Bay AP Lines
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2007
- action
- Construction of AP Lines
- output
- AP Lines
- implementation status
- On-going
- total cost
- Ksh 850,000
- estimate
- Ksh 1,400,000
Kouma Dam
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Excavation of water pan
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 820,000
- estimate
- Ksh 820,000
Koloo water dam
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Excavation of water pan
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 820,000
- estimate
- Ksh 820,000
Masala Dispensary
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Construction of maternity ward and supply of equipments
- output
- Maternity ward and equipment
- implementation status
- Ward complete
- total cost
- Ksh 800,000
- estimate
- Ksh 1,300,000
Lieta Dispensary
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Purchase of equipments
- output
- Health Center
- implementation status
- Complete & in use
- total cost
- Ksh 800,000
- estimate
- Ksh 1,042,282
Obaga Dispensary
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Construction of maternity ward
- output
- Maternity ward
- implementation status
- 60% complete
- total cost
- Ksh 800,000
- estimate
- Ksh 2,000,000
Abidha health centre
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Wiring and electrification
- output
- Electricity installed
- implementation status
- On going
- total cost
- Ksh 800,000
- estimate
- Ksh 1,400,000
Bar Aluru Dam
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Excavation of water pan
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 800,000
- estimate
- Ksh 800,000
Aram Police Station
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2007
- action
- Construction of Staff quarters
- output
- Staff Quarters
- implementation status
- Complete & in use
- total cost
- Ksh 800,000
- estimate
- Ksh 1,200,000
Ongielo Dispensay
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Construction of maternity ward and supply of equipments
- output
- Maternity ward and equipment
- implementation status
- One ward complete & in use
- total cost
- Ksh 800,000
- estimate
- Ksh 1,300,000
Kunya dispensary
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Construction of 2 staff houses
- output
- Staff houses
- implementation status
- 0n-going
- total cost
- Ksh 800,000
- estimate
- Ksh 1,100,000
Naya youth Polytechnic
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2003
- action
- Renovation of the Centre
- output
- Improved educational facilities
- implementation status
- Complete & in use
- total cost
- Ksh 760,000
- estimate
- Ksh 800,000
Kusa primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 750,000
- estimate
- Ksh 800,000
Lela Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 750,000
- estimate
- Ksh 800,000
Saradidi Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Renovations of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 750,000
- estimate
- Ksh 1,600,000
Maugo Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 750,000
- estimate
- Ksh 800,000
Konjiko Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 750,000
- estimate
- Ksh 800,000
Gangu Primary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 60% complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
St. Lazarus Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- complete &in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Gunda Rut Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Mabinju Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Atemo Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 60% complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Tiga Primary School
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 60% complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Kiswaro Primary School
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 60% complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Nyamor Primary School
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Construction of two Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Manera Primary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2006
- action
- construction of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Rambugu Primary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 60% complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Kametho Primary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Ndwara Primary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 80% complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Mahaya Primary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Kamalumbe Primary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 60% complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Kaonje Primary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Construction of Classroom
- output
- Classrooms
- implementation status
- 3classrms complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Alara Primary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Kaminogedo Primary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Okiro Primary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Kandhere Pri
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Nyamasore Primary School
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 4classrms complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Ranyala Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 80% complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Ndonyo Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Ndigwa Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 5classrms complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Buru Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Construction of Classrooms
- output
- Classrooms
- implementation status
- 4classrms complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,600,000
Majango Primary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Renovation of 8 Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 2,800,000
Mirau Primary School
- location
-
S. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of 2 New Classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,200,000
St. Mathews Kandaria secondary secondary
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Construction of library
- output
- Library
- implementation status
- Complete & in use
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Kokwiri Water Project
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Extension of piped water
- output
- Water available at close distance
- implementation status
- On going
- total cost
- Ksh 700,000
- estimate
- Ksh 2,000,000
Nyaruenya Water Project
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2005
- action
- Excavation of water pan
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 700,000
- estimate
- Ksh 700,000
Kawamang’aria Primary School
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 80% complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Ujwang’a Primary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 80% complete
- total cost
- Ksh 700,000
- estimate
- Ksh 1,300,000
Luoro Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2007
- action
- Construction of Classrooms
- output
- Classrooms
- implementation status
- commenced
- total cost
- Ksh 600,000
- estimate
- Ksh 1,600,000
Bar Kogonga Primary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Re-Construction of ECD Centre
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Ruma Community Hall
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Construction of Dining Hall
- output
- Hall
- implementation status
- Funds re-allocated
- total cost
- Ksh 600,000
- estimate
- Ksh 1,800,000
Nyabera Primary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Construction of library
- output
- Library
- implementation status
- 70% complete
- total cost
- Ksh 600,000
- estimate
- Ksh 1,300,000
Akuom Primary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Almost complete
- total cost
- Ksh 600,000
- estimate
- Ksh 1,300,000
Bar Kogonga Primary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Construction of classrooms
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 600,000
- estimate
- Ksh 1,200,000
Manyuanda Health Center
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of laboratory
- output
- Laboratory
- implementation status
- Complete & in use
- total cost
- Ksh 600,000
- estimate
- Ksh 900,000
Ajigo –Kolemo-Mahanga Road
- location
-
W. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Migowa Secondary School
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Purchase of Sanitorium Equipments and furniture
- output
- Construction of Admin Block
- implementation status
- Complete & in use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Nyagoko Secondary School
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 60% complete
- total cost
- Ksh 600,000
- estimate
- Ksh 1,300,000
Ochuoga Kowi Comm. Hall
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Community Hall
- output
- Social facilities
- implementation status
- 90% complete
- total cost
- Ksh 600,000
- estimate
- Ksh 1,000,000
Abidha Boi Water Project
- location
-
E. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Piping
- output
- Water available at close distance
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 750,000
Kanyakunya Dam
- location
-
C. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Kabogi Pan
- location
-
S. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- On-going
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Ramba Secondary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2007
- action
- Construction o f Dormitory
- output
- Dormitory
- implementation status
- Compete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 4,000,000
St. Sylvesters Girls
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Part payment for School bus
- output
- School bus
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 3,200,000
Ogango Village Polytechnic
- location
-
W. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- Started
- total cost
- Ksh 500,000
- estimate
- Ksh 800,000
Raliew Primary School
- location
-
E. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- On going
- total cost
- Ksh 500,000
- estimate
- Ksh 1,200,000
Rariw Primary School
- location
-
E. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of Toilet Block and Classroom
- output
- -
- implementation status
- Toilet complete but class on-going
- total cost
- Ksh 500,000
- estimate
- Ksh 1,200,000
Kandaria Primary School
- location
-
E. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Boi Primary School
- location
-
E. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Oboch Primary School
- location
-
C.Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- Pending finishing
- total cost
- Ksh 500,000
- estimate
- Ksh 1,200,000
Got Bondo Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 500,000
- estimate
- Ksh 1,100,000
Sangla Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- 60% complete
- total cost
- Ksh 500,000
- estimate
- Ksh 750,000
Wangarot Primary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 500,000
- estimate
- Ksh 750,000
Rambira Primary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 750,000
Magare ECD
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Construction of ECD Centre
- output
- ECD Centre
- implementation status
- Started
- total cost
- Ksh 500,000
- estimate
- Ksh 1,400,000
Kasiri Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Construction of Classrooms
- output
- Classrooms
- implementation status
- Pending finishing
- total cost
- Ksh 500,000
- estimate
- Ksh 1,200,000
Kandundo Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 80% complete
- total cost
- Ksh 500,000
- estimate
- Ksh 1,300,000
Aduoyo Primary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- 60% complete
- total cost
- Ksh 500,000
- estimate
- Ksh 1,300,000
Ndori Dispensary
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of maternity ward
- output
- Maternity
- implementation status
- On-going
- total cost
- Ksh 500,000
- estimate
- Ksh 2,000,000
Siger Primary School
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- Complete in use
- total cost
- Ksh 500,000
- estimate
- Ksh 750,000
Anyuongi-Aila-Rarieda Road
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Pap Kodero-Rachar-coner ka Gowi Road
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Funds re-allocated
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Kogolo-Akele-Pap Kodero Road
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Makasembo-Kamariga Road
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Nyamasore-Ragengni Roa
- location
-
E. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- n/a
- output
- -
- implementation status
- Funds re-allocated
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Kibanga-Agok-Gudwa Road
- location
-
S. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Re-allocated
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Mahaya Village Polytechnic
- location
-
W. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 750,000
Kaudi Kitambo Road
- location
-
C. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Nyayiera-Got Bondo Road
- location
-
C. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete & in use
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Lwak-Komenya-Ongielo Road
- location
-
C.Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Luoro Water project
- location
-
C. Asembo
(in Rarieda)
- year first funded
- 2005
- action
- Roof catchment water and borehole
- output
- Water available at close distance
- implementation status
- Complete & in use
- total cost
- Ksh 460,000
- estimate
- Ksh 500,000
Mahaya health centre
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2003
- action
- Construction of health center
- output
- Health centre
- implementation status
- Complete
- total cost
- Ksh 460,000
- estimate
- Ksh 460,000
Osogo Dam
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2003
- action
- Excavation of water pan
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 460,000
- estimate
- Ksh 460,000
Chinga Dam
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Excavation of water pan
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 450,000
- estimate
- Ksh 450,000
Rambugu Dam
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Excavation of water pan
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 420,000
- estimate
- Ksh 420,000
Banda Dam
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Excavation of water pan
- output
- Water available at close dist.
- implementation status
- Complete
- total cost
- Ksh 420,000
- estimate
- Ksh 420,000
Otere Dam
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Excavation of water pan
- output
- Water available at close dist.
- implementation status
- Complete
- total cost
- Ksh 420,000
- estimate
- Ksh 420,000
Kojwaka Dam
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- construction
- output
- Improved Health facilities
- implementation status
- Complete
- total cost
- Ksh 420,000
- estimate
- Ksh 420,000
Kametho dam
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2004
- action
- Construction of dam
- output
- Dam
- implementation status
- Complete
- total cost
- Ksh 420,000
- estimate
- Ksh 420,000
Ramoya dam
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Excavation of water pan
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 420,000
- estimate
- Ksh 420,000
Okwa Nyoyo Dam
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Excavation of water pan
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 420,000
- estimate
- Ksh 420,000
Riwa dam
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2004
- action
- Construction of dam
- output
- Dam
- implementation status
- Complete
- total cost
- Ksh 420,000
- estimate
- Ksh 420,000
Kunya Primary School
- location
-
E. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 1,200,000
Min Okelo Dam
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Excavation of water pan
- output
- Water available at close distance
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Orina Dam
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2005
- action
- Excavation of water pan
- output
- Water available at close range
- implementation status
- Complete
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Yao Tinga
- location
-
C. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- Yet to start
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Kodhiambo Rapondi Dam
- location
-
E. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- Complete & in use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Maramba Dam
- location
-
E. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Konyango Dam
- location
-
C. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Bonde Dam
- location
-
W. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Kogal Dam
- location
-
S. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- On -going
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Kokise Secondary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2007
- action
- Construction of Secondary School
- output
- School
- implementation status
- Started
- total cost
- Ksh 400,000
- estimate
- Ksh 1,800,000
Gagra Secondary School
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Construction of Staff houses
- output
- Staff houses
- implementation status
- At slab level
- total cost
- Ksh 400,000
- estimate
- Ksh 1,600,000
Wambisa Primary School
- location
-
W. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 1,200,000
Mirando Primary School
- location
-
W. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 800,000
Misori Primary School
- location
-
W. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 800,000
Tanga Primary School
- location
-
W. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 700,000
Mituri Primary School
- location
-
E. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 1,200,000
Wayaga Primary School
- location
-
E. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 1,200,000
Migowa Primary School
- location
-
E. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 1,200,000
Lwala Rahongo primary School
- location
-
S. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 1,200,000
Nyangoye Primary School
- location
-
S. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 400,000
- estimate
- Ksh 1,200,000
Ongielo Primary School
- location
-
E. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- On-going
- total cost
- Ksh 400,000
- estimate
- Ksh 1,300,000
Powo Primary School
- location
-
E. Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of new Classroom
- output
- Classrooms
- implementation status
- Complete & use
- total cost
- Ksh 400,000
- estimate
- Ksh 1,200,000
Obaga Primary School
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- Complete & in use
- total cost
- Ksh 400,000
- estimate
- Ksh 1,100,000
Akom Primary School
- location
-
South Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Renovation of Classroom
- output
- Classrooms
- implementation status
- Started
- total cost
- Ksh 400,000
- estimate
- Ksh 1,000,000
Chianda Comp. Centre
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Construction of hall
- output
- Hall
- implementation status
- Re-allocated
- total cost
- Ksh 400,000
- estimate
- Ksh 1,000,000
Rabel Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Pending finishing
- total cost
- Ksh 400,000
- estimate
- Ksh 1,300,000
Wagoro dispensary
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Construction of dispensary
- output
- Dispensary
- implementation status
- Pending finishing
- total cost
- Ksh 400,000
- estimate
- Ksh 1,300,000
Rambugu Health Center
- location
-
West Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Staff houses and fencing
- output
- Staff houses
- implementation status
- 80% complete
- total cost
- Ksh 400,000
- estimate
- Ksh 1,500,000
Achar Dam
- location
-
E. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- Yet to start
- total cost
- Ksh 350,000
- estimate
- Ksh 350,000
Kasaulo Dam
- location
-
W.Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- Complete & in use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Komolo Primary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Started
- total cost
- Ksh 300,000
- estimate
- Ksh 600,000
Manyuanda A.P LIne
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of AP Lines
- output
- AP Lines
- implementation status
- Yet to start
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Naya Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Construction of Classrooms
- output
- Classrooms
- implementation status
- Started
- total cost
- Ksh 300,000
- estimate
- Ksh 1,600,000
Kawino Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2007
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- Started
- total cost
- Ksh 300,000
- estimate
- Ksh 800,000
Nyamboye Primary School
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2007
- action
- Construction of Classrooms
- output
- Classrooms
- implementation status
- Started
- total cost
- Ksh 300,000
- estimate
- Ksh 200,000
Majengo Village Polytechnic
- location
-
W. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Supply of Materials and Equipments
- output
- Equipments
- implementation status
- Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 600,000
Rakombe Primary School
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Construction of Classrooms
- output
- Classrooms
- implementation status
- Started
- total cost
- Ksh 300,000
- estimate
- Ksh 1,200,000
Majango Secondary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2007
- action
- Construction of laboratory
- output
- Laboratory
- implementation status
- Started
- total cost
- Ksh 300,000
- estimate
- Ksh 1,300,000
Tinga Kochienga Dam
- location
-
W.Asembo
(in Rarieda)
- year first funded
- 2008
- action
- Disiltation
- output
- -
- implementation status
- Funds re-allocated
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Manyuanda-LIkungu Road
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete & in use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kogonga Pond
- location
-
C. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of dam
- output
- Dam
- implementation status
- Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kitambo Primary School
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2007
- action
- Renovation of Classrooms
- output
- Classrooms
- implementation status
- New
- total cost
- Ksh 273,000
- estimate
- Ksh 0
Nyakongo Primary School
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Fencing of compound
- output
- Fence
- implementation status
- Started
- total cost
- Ksh 248,000
- estimate
- Ksh 300,000
Kowenje Dam
- location
-
C. Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Disiltation
- output
- Dam
- implementation status
- Complete & in use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ndhere dam
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Excavation of water pan
- output
- Water in dam
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kokoyo dam
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Excavation of water pan
- output
- Water in dam
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Lusi Primary School
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Construction of school
- output
- School
- implementation status
- Started
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ochien’ga dam
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Excavation of water pan
- output
- Water in dam
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyakongo –Akuom road
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete & in use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Tanga –Rachar Pap Kodero road
- location
-
West /Central Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete & in use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Kokwiri cattle Dip
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2008
- action
- Construction of cattle dip
- output
- Cattle Dip
- implementation status
- Yet to start
- total cost
- Ksh 200,000
- estimate
- Ksh 400,000
Madiany –Ramoya road
- location
-
South Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete & in use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Nyabera- Odongo road
- location
-
West Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Opening up of roads
- output
- Easier transportation
- implementation status
- Complete & in use
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Wagoro dam
- location
-
W.Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Excavation of water pan
- output
- Water in dam
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Komolo dam
- location
-
East Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Excavation of water pan
- output
- Water in dam
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Ogwedhi Dam
- location
-
Central Asembo
(in Rarieda)
- year first funded
- 2006
- action
- Excavation of water pan
- output
- Water in dam
- implementation status
- Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Chianda Primary School
- location
-
East Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Electrification of School
- output
- Electricity
- implementation status
- compete & in use
- total cost
- Ksh 114,521
- estimate
- Ksh 150,000
Gagra Primary School
- location
-
Central Uyoma
(in Rarieda)
- year first funded
- 2006
- action
- Wiring of IT Centre
- output
- Electricity installed
- implementation status
- 100% installed
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Luanda Kotieno Police Post
- location
-
Suth Uyoma
(in Rarieda)
- year first funded
- 2007
- action
- Wiring /Electrification
- output
- Electricity Installed
- implementation status
- Funds re-allocated
- total cost
- Ksh 25,000
- estimate
- Ksh 25,000