The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Muthara Healthy Centre
- location
-
Muthara
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of General Ward, Maternity, Kitchen & Laundry, Theater And Administration Bloock
- output
- -
- implementation status
- Construction Of Maternity, General Ward, Kitchen & Laundry Complete And In Use. Administration Block At Letel Level
- total cost
- Ksh 7,000,000
- estimate
- Ksh 9,500,000
Kunati Health Centre
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2004
- action
- Maternity, Kitchen & Laundry, Beds & Septic Tank
- output
- -
- implementation status
- Maternity & Laundry/Kitchen Septic Tank Completed & Beds Bought
- total cost
- Ksh 4,800,000
- estimate
- Ksh 8,000,000
Mikinduri Health Centre
- location
-
Mikinduri
(in Tigania East)
- year first funded
- 2004
- action
- Maternity, Kitchen, Laundry & Septic Tank Complete
- output
- -
- implementation status
- Complete And In Use
- total cost
- Ksh 3,300,000
- estimate
- Ksh 4,000,000
Igarii/Mutethia Water Project
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2003
- action
- Construction Of 4 Storage Tanks & Pipeline
- output
- -
- implementation status
- 1 Storage Tank Complete And A Few Kms Of Piping Done
- total cost
- Ksh 3,200,000
- estimate
- Ksh 6,000,000
Constituency Office
- location
-
Muthara
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of Constituency Office
- output
- -
- implementation status
- Construction Complete And In Use
- total cost
- Ksh 3,000,000
- estimate
- Ksh 3,000,000
Kamithega/Thangatha Bridge
- location
-
Miciimikuru
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of The Bridge
- output
- -
- implementation status
- Construction Complete And In Use
- total cost
- Ksh 3,000,000
- estimate
- Ksh 3,000,000
Antuanduru Water Project
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2003
- action
- Construction Of Intake & 4 Storage Tanks & Pipeline
- output
- -
- implementation status
- Intake And 3 Storage Tanks Complete And Some 10Kms Of Piping Done
- total cost
- Ksh 2,600,000
- estimate
- Ksh 5,000,000
Karama Education Centre
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of Division Education Office
- output
- -
- implementation status
- Roofing And Partitioning Done Awaiting Plastering And Painting
- total cost
- Ksh 2,400,000
- estimate
- Ksh 3,500,000
Kunati Irrigation
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of An Intake, 5 Storage Tanks & Pipeline
- output
- -
- implementation status
- Intake Complete & A Few Kms Of Piping Done
- total cost
- Ksh 2,400,000
- estimate
- Ksh 5,000,000
Maburwa Bridge
- location
-
Buuri
(in Tigania East)
- year first funded
- 2005
- action
- Bridge Construction
- output
- -
- implementation status
- Completed
- total cost
- Ksh 2,400,000
- estimate
- Ksh 2,400,000
Luuma Secondary School
- location
-
Buuri
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 6 New Classrooms And A Staff Room
- output
- -
- implementation status
- 4Classrooms & A Staff Room Completed & In Use Construction Of 1 Classroom Started
- total cost
- Ksh 2,200,000
- estimate
- Ksh 2,000,000
Muthara Polytechnic
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Electrification Of The Institution And Construction Of A New Dormitory
- output
- -
- implementation status
- Electrification Complete And The Dorm Roofed Awaiting Plastering And Painting
- total cost
- Ksh 2,040,150
- estimate
- Ksh 2,740,150
St. Marys Secondary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 Classrooms And Electrification
- output
- -
- implementation status
- Electrification And 2 Classrooms Complete And 2 Other Classrooms Roofed
- total cost
- Ksh 2,000,000
- estimate
- Ksh 2,900,000
St Angeles Secondary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2003
- action
- Construction Of A Storey Dormitory & A Computer
- output
- -
- implementation status
- 1 Storey Dorm Building At Second Floor
- total cost
- Ksh 2,000,000
- estimate
- Ksh 3,000,000
Charuru /Thuuria Road
- location
-
Muthara
(in Tigania East)
- year first funded
- 2004
- action
- Grading The Road And Installing The Culverts
- output
- -
- implementation status
- Grading And Culverting Complete
- total cost
- Ksh 1,992,050
- estimate
- Ksh 2,000,000
Kinangaru Bridge
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of A Bridge
- output
- -
- implementation status
- Foundation Laid Down And Materials Bought
- total cost
- Ksh 1,950,000
- estimate
- Ksh 4,000,000
Antuanduru Day Secondary School
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 6 Classrooms And A Laboratory
- output
- -
- implementation status
- 5 Classrooms And An Office Complete And In Use
- total cost
- Ksh 1,800,000
- estimate
- Ksh 3,000,000
Nyambene Secondary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of A Dormitory And Toilets And A Classroom
- output
- -
- implementation status
- Construction Of Toilets And A Classroom Complete & In Use. Dormitory At Lintel Level
- total cost
- Ksh 1,800,000
- estimate
- Ksh 2,000,000
Lailuba Dispensary
- location
-
Buuri
(in Tigania East)
- year first funded
- 2004
- action
- Completion Of 2 Staff Houses, Construction Of 4 New Treatment Rooms And A Maternity Ward
- output
- -
- implementation status
- 4 Treatment Rooms & 2 Staff Houses Complete And In Use While The Construction Of The Maternity Is At Window Level
- total cost
- Ksh 1,800,000
- estimate
- Ksh 6,000,000
Kigucwa Dispensary
- location
-
Kigucwa
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 5 Treatment Rooms
- output
- -
- implementation status
- Construction Complete
- total cost
- Ksh 1,700,000
- estimate
- Ksh 2,000,000
St. Cyprian Secondary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of A Storey Library And Store
- output
- -
- implementation status
- 1 Storey Put Up, Food Store Complete & In Use
- total cost
- Ksh 1,500,000
- estimate
- Ksh 2,000,000
Irindiro Secondary School
- location
-
Akamia
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of A Dormitory & Dining Hall
- output
- -
- implementation status
- Dormitory Complete & In Use While The Dining Hall Foundation Has Been Laid Down
- total cost
- Ksh 1,500,000
- estimate
- Ksh 1,500,000
Ngutu Water Project
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of An Intake, Storage Tanks & Pipeline
- output
- -
- implementation status
- Intake Complete & A Few Kms Of Piping Done
- total cost
- Ksh 1,400,000
- estimate
- Ksh 3,500,000
Miciimikuru Day Secondary School
- location
-
Miciimikuru
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Complete And In Use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 400,000
Muthara Day Secondary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 5 Classrooms
- output
- -
- implementation status
- 5 Classrooms Compete And In Use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 3,000,000
Ncuui Day Secondary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms & Staffroom Complete And In Use
- total cost
- Ksh 1,300,000
- estimate
- Ksh 3,000,000
Muriri/ Matiandui Water Project
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of Intake, 4 Storage Tanks & Piping
- output
- -
- implementation status
- Intake Complete & Some Kms Of Piping Done
- total cost
- Ksh 1,200,000
- estimate
- Ksh 2,000,000
Kaliene Secondary School
- location
-
Kigucwa
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of A Laboratory & 2 Classrooms
- output
- -
- implementation status
- Construction Of The Lab & 2 Classrooms Complete And In Use
- total cost
- Ksh 1,200,000
- estimate
- Ksh 150,000
Ammuka Shg W
- location
-
Muthara
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 3 Storage Tanks And Piping
- output
- -
- implementation status
- Some Kms Of Piping Done
- total cost
- Ksh 1,200,000
- estimate
- Ksh 2,000,000
Githu Bridge
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2004
- action
- Bridge Construction
- output
- -
- implementation status
- Complete And In Use
- total cost
- Ksh 1,186,000
- estimate
- Ksh 2,000,000
Ametho Day Secondary School Primary School
- location
-
Miciimikuru
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 2 Classrooms Complete And In Use
- total cost
- Ksh 1,100,000
- estimate
- Ksh 4,000,000
Amugaa Day Secondary School
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete And In Use
- total cost
- Ksh 1,050,000
- estimate
- Ksh 900,000
Antuanduru A Camp
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of A.P Line And ChiefS Office
- output
- -
- implementation status
- 4 Rooms Complete A.P Lines Remaining
- total cost
- Ksh 1,018,620
- estimate
- Ksh 2,000,000
Karama Secondary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of A Multi-Purpose Hall
- output
- -
- implementation status
- Roofing On Going
- total cost
- Ksh 1,000,000
- estimate
- Ksh 3,000,000
Igarii/Antuambui Water Project
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of A Intake, Storage Tanks & Pipeline
- output
- -
- implementation status
- Intake Complete And Some Kms Of Piping Done
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Bondii Water Project
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Pipeline & Construction Of 2 Storage Tanks
- output
- -
- implementation status
- 1 Storey Building Put Up Although Not Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 150,000
Ncuui Bridge
- location
-
Muthara
(in Tigania East)
- year first funded
- 2004
- action
- Labour For The Construction Of The Bridge
- output
- -
- implementation status
- Construction Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,000,000
Ntulili Primary School
- location
-
Buuri
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed Awaiting Plastering And Painting
- total cost
- Ksh 950,000
- estimate
- Ksh 2,000,000
Kaongo Primary School
- location
-
Buuri
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed And In Use Awaiting Plastering & Painting
- total cost
- Ksh 900,000
- estimate
- Ksh 1,000,000
Rurii Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed And In Use
- total cost
- Ksh 900,000
- estimate
- Ksh 900,000
Mulika Dispensary
- location
-
Mikinduri
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 5 Treatment Rooms
- output
- -
- implementation status
- Construction Of 5 Treatment Rooms Complete But Not In Use
- total cost
- Ksh 900,000
- estimate
- Ksh 1,000,000
Rumathii Primary School
- location
-
Buuri
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed And In Use But Plastering, Doors And Windows Remaining
- total cost
- Ksh 900,000
- estimate
- Ksh 900,000
Kiithe/Mwontiri Water Project
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Intake/Pipeline & Storage Tanks
- output
- -
- implementation status
- 5 Kms Of Piping Done
- total cost
- Ksh 900,000
- estimate
- Ksh 1,500,000
Karimi Water Project
- location
-
Miciimikuru
(in Tigania East)
- year first funded
- 2003
- action
- Construction Of 3 Storage Tanks & Pipeline
- output
- -
- implementation status
- 3 Storage Tanks Complete And In Use
- total cost
- Ksh 820,000
- estimate
- Ksh 1,000,000
Nthangarine Water Project
- location
-
Karama
(in Tigania East)
- year first funded
- 2003
- action
- Intake/Pipeline & 2 Storage Tanks
- output
- -
- implementation status
- Intake & 2 Storage Tanks Complete & Some Kms Of Piping Done
- total cost
- Ksh 800,000
- estimate
- Ksh 1,800,000
Kiithe Primary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 5 New Classrooms In Use But Waits Floor, Plastering, Windows & Doors
- total cost
- Ksh 800,000
- estimate
- Ksh 900,000
Luthii Primary School
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 3 Classrooms Roofed And In Use But Awaits Plastering & Painting And The Other One At Lintel Level
- total cost
- Ksh 800,000
- estimate
- Ksh 900,000
Lunuru Dairy
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of Milk Collection Centre And Store
- output
- -
- implementation status
- Construction Completed & In Use
- total cost
- Ksh 800,000
- estimate
- Ksh 1,000,000
Ngaichiumia Water Project
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Pipe Line & Construction Of Storage Tanks & Intake
- output
- -
- implementation status
- 1 Storage Tank Complete & And A Few Kms Of Piping Done
- total cost
- Ksh 800,000
- estimate
- Ksh 2,500,000
Lanyiruu Water Project
- location
-
Buuri
(in Tigania East)
- year first funded
- 2005
- action
- Storage Tanks & Pipeline
- output
- -
- implementation status
- 2 Storage Tanks Complete And Some Kms Of Piping Done
- total cost
- Ksh 800,000
- estimate
- Ksh 1,000,000
Lubuathirua Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed And In Use
- total cost
- Ksh 800,000
- estimate
- Ksh 900,000
Thaathi Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed And In Use
- total cost
- Ksh 800,000
- estimate
- Ksh 900,000
Kamujine Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed & In Use
- total cost
- Ksh 800,000
- estimate
- Ksh 900,000
Kiarao Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 2 Classrooms Complete & In Use
- total cost
- Ksh 800,000
- estimate
- Ksh 900,000
Charuru Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed And In Use. Plastering & Painting Not Cone
- total cost
- Ksh 700,000
- estimate
- Ksh 900,000
Kaathi Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 2 Classrooms Complete
- total cost
- Ksh 700,000
- estimate
- Ksh 900,000
Gacibine Police Post
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of A Police Post
- output
- -
- implementation status
- Foundation Laid Down
- total cost
- Ksh 700,000
- estimate
- Ksh 1,000,000
Ngage A Camp
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 A.P Houses
- output
- -
- implementation status
- Construction Of 4 Rooms Complete
- total cost
- Ksh 700,000
- estimate
- Ksh 500,000
Ngega Day Secondary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete And In Use
- total cost
- Ksh 700,000
- estimate
- Ksh 7,000,000
Karama Dispensary
- location
-
Karama
(in Tigania East)
- year first funded
- 2004
- action
- Plastering & Painting Treatment Rooms & Construction Of 2 New Rooms
- output
- -
- implementation status
- 2 More New Rooms Constructed And Roofed Awaiting Plastering & Painting
- total cost
- Ksh 700,000
- estimate
- Ksh 800,000
Ntianyi Water Project
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Intake/ 3Storage Tanks/Pipeline
- output
- -
- implementation status
- 2 Storage Tanks Complete & Piping Done
- total cost
- Ksh 700,000
- estimate
- Ksh 1,500,000
Mutunduru W
- location
-
Karama
(in Tigania East)
- year first funded
- 2007
- action
- Pipeline & Storage Tanks
- output
- -
- implementation status
- Some Kms Of Piping Done
- total cost
- Ksh 700,000
- estimate
- Ksh 2,000,000
Kiremu Primary School
- location
-
Buuri
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 6 New Classrooms
- output
- -
- implementation status
- 6 Classrooms Roofed & In Use But Plastering, Doors And Windows Remaining
- total cost
- Ksh 700,000
- estimate
- Ksh 900,000
Kambela A Camp
- location
-
Buuri
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of An A.P House & ChiefS Office
- output
- -
- implementation status
- Construction Of 5 A.P Rooms Complete And In Use
- total cost
- Ksh 650,000
- estimate
- Ksh 700,000
Mbaranga Primary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete & In Use While Other 2 At Lintel Level
- total cost
- Ksh 600,000
- estimate
- Ksh 900,000
Ntamiciu Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed And In Use Awaiting Plastering And Painting
- total cost
- Ksh 600,000
- estimate
- Ksh 900,000
Maburwa Primary School
- location
-
Buuri
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed & In Use And 2 Others At Lintel Level
- total cost
- Ksh 600,000
- estimate
- Ksh 900,000
Igarii Health Centre
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 5 Treatment Rooms
- output
- -
- implementation status
- 5 Rooms Roofed But Not In Use
- total cost
- Ksh 600,000
- estimate
- Ksh 600,000
Kirima Water Project - Karama
- location
-
Karama
(in Tigania East)
- year first funded
- 2003
- action
- Construction Of Intake &Storage Tanks And Piping
- output
- -
- implementation status
- 1 Storage Tank Complete And A Few Kms Of Piping Done, Intake Under Construction
- total cost
- Ksh 600,000
- estimate
- Ksh 800,000
Uruu Water Project
- location
-
Karama
(in Tigania East)
- year first funded
- 2004
- action
- Pipes & Construction Of 3 Storage Tanks
- output
- -
- implementation status
- 2 Storage Tanks And Piping Completed
- total cost
- Ksh 600,000
- estimate
- Ksh 800,000
Charuru Water Project
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Repairs Of Intake, Construction Of Storage Tanks & Pipeline
- output
- -
- implementation status
- A Few Kms Of Piping Done
- total cost
- Ksh 600,000
- estimate
- Ksh 1,000,000
Mwerokieni Primary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed And Foundation Of The Other One Laid Down
- total cost
- Ksh 550,000
- estimate
- Ksh 900,000
Angili Primary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete & In Use
- total cost
- Ksh 550,000
- estimate
- Ksh 900,000
Karachi A Line
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of A.P Houses And ChiefS Camp
- output
- -
- implementation status
- Construction 4 Rooms Complete And In Use
- total cost
- Ksh 525,000
- estimate
- Ksh 600,000
Laibocha Primary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- 1 Class Repairs And Construction Of 3 New Ones
- output
- -
- implementation status
- Repairs Complete & 2 New Classes Complete
- total cost
- Ksh 516,000
- estimate
- Ksh 1,016,000
Athambu Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Maburwa Chiefs Camp
- location
-
Buuri
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of A.P Rooms And ChiefS Office
- output
- -
- implementation status
- 3 Rooms For Complete, A.P Lines Remaining
- total cost
- Ksh 500,000
- estimate
- Ksh 800,000
Athwana Primary School
- location
-
Mikinduri
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 1 Classroom Completed
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Akairu Primary School
- location
-
Kigucwa
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Kirimancuma Primary School
- location
-
Miciimukuru
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed & In Use But Plastering And Painting Not Done
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Ngombenjiru Primary School
- location
-
Miciimikuru
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed And In Use But Plastering & Painting Not Done
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Kinaathi Water Project
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 3 Storage Tanks & Pipeline
- output
- -
- implementation status
- Intake Complete And A Few Kms Of Piping Done
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Thangatha Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Kiithiu Water Project
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of An Intake, 4 Storage Tanks & Pipepline
- output
- -
- implementation status
- Intake Complete And A Few Kms Of Piping Done
- total cost
- Ksh 500,000
- estimate
- Ksh 2,000,000
Nyakine /Murimi W
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of A 3 Storage Tanks & Pipeline
- output
- -
- implementation status
- A Few Kms Of Piping Done
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Ikana Primary School
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Miurine Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed And In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Amugaa A Camp
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of ChiefS Camp
- output
- -
- implementation status
- Materials Bought
- total cost
- Ksh 500,000
- estimate
- Ksh 700,000
Kithare Water Project
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of Intake, 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- A Few Kms Of Piping Done
- total cost
- Ksh 500,000
- estimate
- Ksh 600,000
Mutunduru Primary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed But Awaiting Plastering, Floor, Windows, Doors & Painting
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Kobimo Water Project
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Intake /Pipeline & Storage Tanks
- output
- -
- implementation status
- Intake, One Storage Tank Complete & Some Kilometers Of Piping Done
- total cost
- Ksh 500,000
- estimate
- Ksh 800,000
Ntirutu Primary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete And In Use And 2 Others Roofed
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Lanyiruu Dispensary
- location
-
Buuri
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 5 New Treatment Rooms
- output
- -
- implementation status
- 2 Treatment Rooms Complete But Not In Use
- total cost
- Ksh 500,000
- estimate
- Ksh 2,000,000
Mukuiru Primary School
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classes In Use But Awaits Floor, Plastering, Doors & Windows
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Kirima Primary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 1 Classrooms Roofed And In Use & The Other One At Lintel Level
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Mukuani Primary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed & In Use But Awaits Plastering & Painting
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Thuuria Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 3 Class Rooms Roofed Awaiting Plastering, Doors & Painting
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Tharichia Women Self Help Group Water Project
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of Intake, Storage Tanks & Pipeline
- output
- -
- implementation status
- Intake, One Storage Tank Complete & Some Kms Of Piping Done.
- total cost
- Ksh 500,000
- estimate
- Ksh 800,000
Rumanthii Day Sec
- location
-
Buuri
(in Tigania East)
- year first funded
- 2008
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
Matabithi Primary School
- location
-
Buuri
(in Tigania East)
- year first funded
- 2008
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Materials Purchased
- total cost
- Ksh 500,000
- estimate
- Ksh 3,000,000
Kinangaru Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed & In Use But Awaits Plastering, Floor And Painting
- total cost
- Ksh 500,000
- estimate
- Ksh 900,000
Mwerokieni Bridge
- location
-
Karama
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of The Culverts Bridge
- output
- -
- implementation status
- Construction Complete
- total cost
- Ksh 450,000
- estimate
- Ksh 500,000
Antuanuu Water Project
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of Intake, 3Storage Tanks & Pipeline
- output
- -
- implementation status
- Some Kms Of Piping Done
- total cost
- Ksh 400,000
- estimate
- Ksh 800,000
Antuaduru Primary School
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 3 Classrooms Complete & In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Gitundu W
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2006
- action
- Intake, Storage Tanks & Pipeline
- output
- -
- implementation status
- Intake And One Storage Tank Complete And Some Kms Of Piping Done
- total cost
- Ksh 400,000
- estimate
- Ksh 600,000
Kibithewa/Makutano W
- location
-
Karama
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of Intake, Storage Tanks And Piping
- output
- -
- implementation status
- Intake Complete & Some Kms Of Piping Done
- total cost
- Ksh 400,000
- estimate
- Ksh 3,000,000
Kiamaroo Water Project
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Pipeline & Construction Of 3 Storage Tanks
- output
- -
- implementation status
- 1 Storage Tank Constructed And Some Kms Of Piping Done
- total cost
- Ksh 400,000
- estimate
- Ksh 800,000
Makirithiaine Water Project
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of Intake, Storage Tanks & Pipeing
- output
- -
- implementation status
- Intake &1 Storage Tank Complete And Some Kms Of Piping Done
- total cost
- Ksh 400,000
- estimate
- Ksh 800,000
Lanyiruu Dispensary
- location
-
Buuri
(in Tigania East)
- year first funded
- 2008
- action
- Construction Of 5 Treatment Rooms
- output
- -
- implementation status
- 3 Treatment Rooms Completed
- total cost
- Ksh 400,000
- estimate
- Ksh 5,000,000
Ngaintethia Water Project
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of Intake, 3 Storage Tanks & Pipeline
- output
- -
- implementation status
- Construction Of 1 Storage Tank Complete & Some Kms Of Piping Done
- total cost
- Ksh 400,000
- estimate
- Ksh 800,000
Nduluma Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed & In Use Awaiting Plastering & Painting
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Lanyiruu Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed & In Use And Foundation Laid For 2 Others
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Antuanuu Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed And In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Nguthiru Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed And In Use But Awaits Finishing
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Kailutha Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed & In Use And Foundation For Other 2 Laid Down
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Lailuba Primary School
- location
-
Buuri
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed And In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 1,000,000
Muthara Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed And In Use But Plastering & Painting No Done
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Lailuba/Kaburingi W
- location
-
Buuri
(in Tigania East)
- year first funded
- 2006
- action
- Intake, Storage Tanks & Pipeline
- output
- -
- implementation status
- Piping Done
- total cost
- Ksh 400,000
- estimate
- Ksh 600,000
Lailuba/Kandebene W
- location
-
Buuri
(in Tigania East)
- year first funded
- 2008
- action
- Storage Tanks And Piping
- output
- -
- implementation status
- 1 Storage Tank Completed
- total cost
- Ksh 400,000
- estimate
- Ksh 2,000,000
Kathanje Springfull W
- location
-
Buuri
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of Intake And A Chamber
- output
- -
- implementation status
- Intake Complete 3Kms Of Piping Done
- total cost
- Ksh 400,000
- estimate
- Ksh 500,000
Kathanene Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed & In Use But Painting & Plastering Not Done
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Mucuune Women Water Project
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of An Intake, 3 Storage Tanks & Pipeline
- output
- -
- implementation status
- Intake Complete & A Few Kms Of Piping Cone
- total cost
- Ksh 400,000
- estimate
- Ksh 1,500,000
Thuti W
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- 5 Kms Of Piping Done
- total cost
- Ksh 400,000
- estimate
- Ksh 600,000
Kirima W
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- 5 Kms Of Piping Done
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Kiangorwe Bridge
- location
-
Anakmia
(in Tigania East)
- year first funded
- 2007
- action
- Putting Of Culverts
- output
- -
- implementation status
- Culverting Done And In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 400,000
Irindiro Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 2 Classrooms Complete And In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Kathanene Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed And In Use
- total cost
- Ksh 400,000
- estimate
- Ksh 900,000
Kiuko Ka Kuru Bridge
- location
-
Karama
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of Culverts Bridge
- output
- -
- implementation status
- Construction Complete & In Use
- total cost
- Ksh 350,000
- estimate
- Ksh 400,000
Itharu Water Project
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of Intake, 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- A Few Kms Of Piping Done
- total cost
- Ksh 300,000
- estimate
- Ksh 600,000
Githuu/Kamunjine Road
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2007
- action
- Grading Of The Road
- output
- -
- implementation status
- Grading Done And In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Rarimbu Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 2 Classrooms At Lintel Level
- total cost
- Ksh 300,000
- estimate
- Ksh 900,000
Ikana Day Sec
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2008
- action
- Construction Of 4 Classrooms And An Admin Block
- output
- -
- implementation status
- Construction Started
- total cost
- Ksh 300,000
- estimate
- Ksh 5,000,000
Antuarimata W
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- 4 Kms Of Piping Done
- total cost
- Ksh 300,000
- estimate
- Ksh 800,000
Karurune Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 4 Classes Complete And In Use
- total cost
- Ksh 300,000
- estimate
- Ksh 900,000
Ametho Boarding Primary School
- location
-
Miciimikuru
(in Tigania East)
- year first funded
- 2006
- action
- Provision Of Electricity
- output
- -
- implementation status
- Electrification Done
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kirimancuma Water Project
- location
-
Miciimikuru
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- A Few Kms Of Piping Done
- total cost
- Ksh 300,000
- estimate
- Ksh 600,000
Thubuku Dairy
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of Milk Collection Centre
- output
- -
- implementation status
- Construction Started
- total cost
- Ksh 300,000
- estimate
- Ksh 1,000,000
Ngaremara Dispensary
- location
-
Buuri
(in Tigania East)
- year first funded
- 2008
- action
- Construction Of 5 Treatment Rooms
- output
- -
- implementation status
- Materials Purchased
- total cost
- Ksh 300,000
- estimate
- Ksh 5,000,000
Mitunguune Primary School
- location
-
Karama
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed & In Use, Plastering, Doors And Windows Remaining
- total cost
- Ksh 300,000
- estimate
- Ksh 900,000
Laikumukumu Dispensary
- location
-
Karama
(in Tigania East)
- year first funded
- 2008
- action
- Construction Of 5 Treatment Rooms
- output
- -
- implementation status
- Foundation Laid
- total cost
- Ksh 300,000
- estimate
- Ksh 4,000,000
Mula Chiefs Camp
- location
-
Karama
(in Tigania East)
- year first funded
- 2008
- action
- Construction Of ChiefS Offices & A.P Line
- output
- -
- implementation status
- Office At Litel Level
- total cost
- Ksh 300,000
- estimate
- Ksh 1,000,000
Kaluli Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction To Start Soon
- total cost
- Ksh 250,000
- estimate
- Ksh 900,000
Ankamia Secondary School
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Roofed And In Use But Plastering & Painting Not Done
- total cost
- Ksh 250,000
- estimate
- Ksh 900,000
Kaathi Dispensary
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 5 Treatment Rooms
- output
- -
- implementation status
- 3 Rooms Roofed But Not In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Antuarimata Primary School
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms At Window Level
- total cost
- Ksh 200,000
- estimate
- Ksh 900,000
Marega Primary School
- location
-
Mokinduri
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 1 Classroom Roofed & In Use. Plastering & Painting Not Cone
- total cost
- Ksh 200,000
- estimate
- Ksh 900,000
Thamitu Water Project
- location
-
Miciimikuru
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- A Few Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Kaliene Primary School
- location
-
Kigucwa
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 2 Classrooms At Window Level
- total cost
- Ksh 200,000
- estimate
- Ksh 900,000
Kailune Secondary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms & Repairs
- output
- -
- implementation status
- Repairs Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 900,000
Githu Dispensary
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2005
- action
- Completion Of Treatment Room
- output
- -
- implementation status
- Complete But Not In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Ankamia Dispensary
- location
-
Akamia
(in Tigania East)
- year first funded
- 2005
- action
- Block Repairs
- output
- -
- implementation status
- Repairs Complete But Not In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 800,000
Gitumbi Water Project
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- A Few Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Uriro Water Project
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- A Few Kms Of Iping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Kioru W
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- Some Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Mwitha W
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 3 Storage Tanks & Pipeline
- output
- -
- implementation status
- Some Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 700,000
Mukunga Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 4 Classrooms Roofed And In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 900,000
Amugaa Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 2 Classrooms Complete And In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 900,000
Compassion Education Centre
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction The Centre For Feeding The Orphans
- output
- -
- implementation status
- Construction Completed And In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Kaongo Water Project
- location
-
Karama
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of Intake & 2 Storage Tanks, & Piping
- output
- -
- implementation status
- Intake Complete & Few Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 1,000,000
Ikongolo Water Project
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Intake/Pipeline & 2 Storage Tanks
- output
- -
- implementation status
- Intake Complete & Some Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 800,000
Kathima Kagucwa Water Project
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of Intake Storage Tanks &Pipeline
- output
- -
- implementation status
- Intake Complete And 3Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Ntirutu/Luthii Road
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Upgrading Of The Road
- output
- -
- implementation status
- Almost 5Km Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Kilencune Wp
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2006
- action
- Intake, Storage Tanks & Pipeline
- output
- -
- implementation status
- Intake Complete And Some Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 800,000
Gachoro Wp
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2006
- action
- Intake, Storage Tanks & Pipeline
- output
- -
- implementation status
- Some Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Kaonoro/Gatolone Wp
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2006
- action
- Intake, Storage Tanks & Pipeline
- output
- -
- implementation status
- Some Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Mikumbune Wp
- location
-
Antuanduru
(in Tigania East)
- year first funded
- 2006
- action
- Intake, Storage Tanks & Pipeline
- output
- -
- implementation status
- Some Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 800,000
Safina Water Project
- location
-
Karama
(in Tigania East)
- year first funded
- 2006
- action
- Intake, Storage Tanks & Piping
- output
- -
- implementation status
- Intake Complete & Some Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Mukuani Road
- location
-
Karama
(in Tigania East)
- year first funded
- 2006
- action
- Excavation Of A Road Section
- output
- -
- implementation status
- Excavation Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Charuru Chiefs Camp
- location
-
Muthara
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of A.P Houses & ChiefS Office
- output
- -
- implementation status
- Completed And In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 400,000
Bidii Water Project
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Pipeline & 2 Storage Tanks
- output
- -
- implementation status
- Some Kms Of Piping Done
- total cost
- Ksh 200,000
- estimate
- Ksh 400,000
Kandebene A Camp
- location
-
Buuri
(in Tigania East)
- year first funded
- 2004
- action
- A.P Line
- output
- -
- implementation status
- Complete And In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Kabaune/ Mwili Road
- location
-
Muthara
(in Tigania East)
- year first funded
- 2005
- action
- Grading And Murruming The Road
- output
- -
- implementation status
- Grading And Murruming Complete
- total cost
- Ksh 200,000
- estimate
- Ksh 200,000
Charuru Dispensary
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Completion Of 3 Treatment Rooms
- output
- -
- implementation status
- Construction Done And In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 600,000
Mweromuthanga Primary School
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms At Lintel Level And Other 2 Built In Conjunction With Plan International
- total cost
- Ksh 200,000
- estimate
- Ksh 900,000
Kiguru Primary School
- location
-
Mikinduri
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 2 Classrooms Complete And In Use But Plastering & Painting To Be Done
- total cost
- Ksh 200,000
- estimate
- Ksh 900,000
Mukono Primary School
- location
-
Mikinduri
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 2 Classrooms Complete And In Use
- total cost
- Ksh 200,000
- estimate
- Ksh 900,000
Akaiga Primary School
- location
-
Mikinduri
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms At Window Level
- total cost
- Ksh 200,000
- estimate
- Ksh 900,000
Thuuri Primary School
- location
-
Mikinduri
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 1 Classroom Complete & In Use
- total cost
- Ksh 150,000
- estimate
- Ksh 900,000
Lubuathirwa W
- location
-
Muthara
(in Tigania East)
- year first funded
- 2006
- action
- Storage Tanks & Pipeline
- output
- -
- implementation status
- 1 Storage Tank Constructed And Piping Done
- total cost
- Ksh 100,000
- estimate
- Ksh 600,000
Mpitha Water Project
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 2 Storage Tanks
- output
- -
- implementation status
- A Few Kms Of Piping Done
- total cost
- Ksh 100,000
- estimate
- Ksh 0
Miciimikuru Chiefs Camp
- location
-
Miciimikuru
(in Tigania East)
- year first funded
- 2006
- action
- Repairs Of ChiefS Office
- output
- -
- implementation status
- Repairs Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 300,000
Ngutu Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2004
- action
- Labour Construction of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete And In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 900,000
Gacibine Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete And In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 900,000
Kalantina Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete And In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Ngage Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2005
- action
- Class Repairs
- output
- -
- implementation status
- Repairs Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Antuanthenge Primary School
- location
-
Akamia
(in Tigania East)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- 2 Classrooms Complete And In Use
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Mpitha W
- location
-
Ankamia
(in Tigania East)
- year first funded
- 2007
- action
- Construction Of 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- A Few Kms Of Piping Done
- total cost
- Ksh 100,000
- estimate
- Ksh 500,000
Ngongoaka Primary School
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- -
- implementation status
- Construction Of 4 Classrooms Completed
- total cost
- Ksh 100,000
- estimate
- Ksh 900,000
Undu Water Project
- location
-
Thangatha
(in Tigania East)
- year first funded
- 2006
- action
- Construction Of Intake, 2 Storage Tanks & Pipeline
- output
- -
- implementation status
- A Few Kms Of Piping Done
- total cost
- Ksh 100,000
- estimate
- Ksh 600,000
Mukuani Water Project
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of Intake, 3 Storage Tanks & Pipeline
- output
- -
- implementation status
- Intake Complete & Some Kms Of Piping Done
- total cost
- Ksh 100,000
- estimate
- Ksh 1,000,000
Biriri Bridge
- location
-
Karama
(in Tigania East)
- year first funded
- 2005
- action
- Construction Of Wooden Crossing Bridge
- output
- -
- implementation status
- Construction Complete
- total cost
- Ksh 50,000
- estimate
- Ksh 50,000