The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.

It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.

Projects in Wajir North

Buna Boys Secondary School

location
Buna (in Wajir North)
year first funded
2005
action
n/a
output
Improve Education
implementation status
Complete
total cost
Ksh 8,025,865
estimate
Ksh 8,025,865

Wataraya Water Pan

location
Bute (in Wajir North)
year first funded
2005
action
Excavate A New Pan
output
Improve Water
implementation status
Complete
total cost
Ksh 5,000,000
estimate
Ksh 5,000,000

Kulani Water Project

location
Gurar (in Wajir North)
year first funded
2006
action
n/a
output
Improve Water
implementation status
Complete
total cost
Ksh 4,000,000
estimate
Ksh 4,000,000

Gagaba Water Project

location
Dugo (in Wajir North)
year first funded
2006
action
n/a
output
Improve Water
implementation status
Complete
total cost
Ksh 4,000,000
estimate
Ksh 4,000,000

Leveling Of Showriqako Hill

location
Gurar (in Wajir North)
year first funded
2005
action
Improve Road Network
output
Improve Roads
implementation status
Complete
total cost
Ksh 4,000,000
estimate
Ksh 4,000,000

Ajawa Water Pan

location
Ajawa (in Wajir North)
year first funded
2006
action
A New Pan
output
Improve Water Standard
implementation status
Complete
total cost
Ksh 3,500,000
estimate
Ksh 2,500,000

Excavation Of Anew Pan

location
Buna (in Wajir North)
year first funded
2007
action
Excavation Of Ter Pan
output
Improve Water Facilities
implementation status
Not Yet Started
total cost
Ksh 2,500,000
estimate
Ksh 2,500,000

District Commissioner House In Bute

location
Bute (in Wajir North)
year first funded
2007
action
Construction Of Dc House
output
Improve Administration Facilities.
implementation status
No Yet Started.
total cost
Ksh 2,500,000
estimate
Ksh 2,500,000

Construction Of Maternity Ward In Bute

location
Bute (in Wajir North)
year first funded
2003
action
Site Survey. Construction of Maternity Ward
output
Support Health Facilities
implementation status
Complete
total cost
Ksh 2,300,000
estimate
Ksh 2,300,000

Drilling Of Borehole In Quadama

location
Quadama (in Wajir North)
year first funded
2003
action
Drilled Water Supply
output
Improve Water Supply
implementation status
Drilled
total cost
Ksh 2,000,787
estimate
Ksh 2,000,787

Drilling Of Borehole In Dobu

location
Quadama (in Wajir North)
year first funded
2004
action
Drilled Borehole
output
Improve Water
implementation status
Drilled
total cost
Ksh 2,000,000
estimate
Ksh 2,000,000

Expansion Of Road Network In Gurar

location
Gurar (in Wajir North)
year first funded
2007
action
Expansion Of Road
output
Improve Road Net Work
implementation status
Not Yet Started
total cost
Ksh 2,000,000
estimate
Ksh 2,000,000

Danaba Water pan

location
Danaba (in Wajir North)
year first funded
2006
action
A New Pan
output
Improve Water Atandard
implementation status
Complete
total cost
Ksh 2,000,000
estimate
Ksh 2,000,000

Drilling Of Borehole In Ajawa

location
Ajawa (in Wajir North)
year first funded
2004
action
Drilled Borehole
output
Improve Water
implementation status
Drilled
total cost
Ksh 2,000,000
estimate
Ksh 2,000,000

Quadama Dispensary

location
Quadama (in Wajir North)
year first funded
2006
action
Construction of A Dispensary And 2 Toilets
output
Improve Health
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Excavation Of A New Water Pan Ingirir

location
Ingirir (in Wajir North)
year first funded
2007
action
Excavation Of A New Pan
output
Improve Water Access
implementation status
No Work Yet Done
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Bute Library Hall

location
Bute (in Wajir North)
year first funded
2007
action
Construction Of Reading Hall
output
Improving Education Standard
implementation status
Not Yet Started
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Laboratory For Bute Girls Secondary School

location
Bute (in Wajir North)
year first funded
2007
action
Construction Of A Laboratory
output
Improvement Of Education Standards
implementation status
Not Yet Started
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Adadijole Dispensary

location
Orgoji (in Wajir North)
year first funded
2006
action
n/a
output
Improve Health
implementation status
Ongoing
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Dispensary In Dugo

location
Dugo (in Wajir North)
year first funded
2005
action
Improve Road Network
output
Improve Health
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Dispensary In Orgoji

location
Orgoji (in Wajir North)
year first funded
2005
action
Construction of Dispensary And 2 Toilets
output
Improve Health
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Quadama Dispensary

location
Quadama (in Wajir North)
year first funded
2004
action
Construction of Dispensary And 2 Toilets
output
Improve Health Standard
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Bute Girls School

location
Bute (in Wajir North)
year first funded
2004
action
Survey, Construction of A House
output
To Improve Housing In School
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

H M House In Bute Girls Secondary School

location
Bute (in Wajir North)
year first funded
2004
action
Construction Of Staff House
output
Support Housing In School
implementation status
Complete
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Ingirir Dispensary

location
Ingirir (in Wajir North)
year first funded
2006
action
Construction of A Dispensary And 2 Toilets
output
-
implementation status
Ongoing
total cost
Ksh 1,500,000
estimate
Ksh 1,500,000

Bute Helu Pump House

location
Bute Helu (in Wajir North)
year first funded
2006
action
To Be Reallocated For A Dormitory
output
Improve Education
implementation status
-
total cost
Ksh 1,200,000
estimate
Ksh 1,200,000

Rooms For Administration Police

location
Ajawa (in Wajir North)
year first funded
2007
action
Construction Of 3 Rooms
output
Improve Security House
implementation status
Not Yet Started
total cost
Ksh 1,200,000
estimate
Ksh 1,200,000

Danaba School

location
Danaba (in Wajir North)
year first funded
2007
action
Construction Of 3 Classroom
output
Improve Education Facilities
implementation status
Not Yet Started
total cost
Ksh 1,200,000
estimate
Ksh 1,200,000

Gurar School

location
Gurar (in Wajir North)
year first funded
2006
action
Renovation Of 8 Classrooms
output
-
implementation status
Complete
total cost
Ksh 1,200,000
estimate
Ksh 1,200,000

Additional Fund To Gagaba Water Project

location
Dugo (in Wajir North)
year first funded
2007
action
Excavation Of New Pan
output
Improve Water Facilities
implementation status
Compete And In Use
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Disilting Of Quadama Pan

location
Quadama (in Wajir North)
year first funded
2004
action
Disilt A Pan
output
Improve Water
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Disilting Of Pan Korondille

location
Korondille (in Wajir North)
year first funded
2005
action
Disilt A Pan
output
Improve Water
implementation status
Complete
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Saka Girls Secondary School

location
Saka (Gsa) (in Wajir North)
year first funded
2006
action
Construction of A Domitory
output
Improve Education Standard
implementation status
-
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Additional Funding To Wataraya Water Project In Bute

location
Bute (in Wajir North)
year first funded
2007
action
Excavation Of Water Pan
output
Improve Water Facilities
implementation status
Complete And In Use
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Godoma Primary School

location
Godoma (in Wajir North)
year first funded
2007
action
Construction Of Adormitory
output
Improve Housing Facilities
implementation status
Not Yet Started
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Additional Fund To Ajawa Pan

location
Ajawa (in Wajir North)
year first funded
2007
action
Excavation Of Apan
output
Improve Water Standard
implementation status
Completed
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Korondille Primary School

location
Korondille (in Wajir North)
year first funded
2007
action
Construction Of 1 Dormitory
output
Improve Education Facilities
implementation status
Not Yet Started
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Bute Helu Primary School

location
Bute Helu (in Wajir North)
year first funded
2007
action
Construction Of A Dormitory
output
Improve Education Standards
implementation status
No Work Yet Done
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Desilting A Pan In Qudama

location
Qudama (in Wajir North)
year first funded
2007
action
Desilting A Water Pan
output
Improve Water Access
implementation status
No Work Yet Done
total cost
Ksh 1,000,000
estimate
Ksh 1,000,000

Buna New Primary School

location
Buna (in Wajir North)
year first funded
2003
action
Site Survey, Construction of 2No. Classrooms, Toilet, Water Tank
output
Support Education Programme
implementation status
Complete
total cost
Ksh 850,000
estimate
Ksh 850,000

Orgoji Water Pan

location
Ogorji (in Wajir North)
year first funded
2004
action
Excavate A New Pan
output
Improve Water
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 800,000

Equipping Of Dispensaryies

location
Godama, Dugo, Ogorji, Malkagufu, Qudama, Adadijole. (in Wajir North)
year first funded
2007
action
Equipping Of Dispensaries
output
Improve Access To Health Facilities
implementation status
No Work Yet Done
total cost
Ksh 800,000
estimate
Ksh 800,000

Water Tank At Korondille

location
Korondille (in Wajir North)
year first funded
2007
action
Construction Of A Water Tank
output
Improve Access To Water
implementation status
Not Yet Started
total cost
Ksh 800,000
estimate
Ksh 800,000

Fanabua Primary School

location
Buna (in Wajir North)
year first funded
2007
action
Construction Of 2 Classrooms
output
Improve Education Facilities
implementation status
Not Yet Started
total cost
Ksh 800,000
estimate
Ksh 800,000

Dugo School

location
Dugo (in Wajir North)
year first funded
2007
action
Construction Of Class Room
output
Improve Education Facilities
implementation status
Not Yet Started
total cost
Ksh 800,000
estimate
Ksh 800,000

Integrated Primary School

location
Bute (in Wajir North)
year first funded
2007
action
Construction Of 2 Classrooms
output
Improvement Of Education Standards
implementation status
Not Yet Started.
total cost
Ksh 800,000
estimate
Ksh 800,000

Malaba Primary School

location
Bute (in Wajir North)
year first funded
2006
action
Renovation 8 Classrooms
output
Improve Education Standard
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 800,000

Noclassrooms In Ogorji

location
Ogorji (in Wajir North)
year first funded
2006
action
Construction of Classrooms
output
Improve Education
implementation status
On Going
total cost
Ksh 800,000
estimate
Ksh 800,000

Water Tank On Lakole North

location
Lakole North (in Wajir North)
year first funded
2006
action
Reallocated For 2 Classrooms
output
-
implementation status
On Going
total cost
Ksh 800,000
estimate
Ksh 800,000

Ajawa Dispensary

location
Ajawa (in Wajir North)
year first funded
2005
action
Renovate A Dispensary
output
Improve Health
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 800,000

No Classrooms In Dugo

location
Dugo (in Wajir North)
year first funded
2005
action
Construction of 2 No. Classrooms
output
Improve Education
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 800,000

Noclassrooms In Ingirir

location
Ingirir (in Wajir North)
year first funded
2005
action
Construction of 2 No. Classrooms
output
Improve Education
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 800,000

Noclassrooms In Danaba

location
Danaba (in Wajir North)
year first funded
2005
action
Construction of 2 No. Classrooms
output
Improve Education
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 800,000

Ajawa Water Pan

location
Ajawa (in Wajir North)
year first funded
2004
action
Construction of Pan
output
Improve Water
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 800,000

Water Pan In Ingirir

location
Ingirir (in Wajir North)
year first funded
2003
action
Site Survey, Excavate Water Pan
output
Help Water Issue
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 800,000

Dugo Water Pan

location
Dugo (in Wajir North)
year first funded
2004
action
Excavate A Pan
output
Improve Water
implementation status
Complete
total cost
Ksh 800,000
estimate
Ksh 800,000

Noclassrooms In Quadama

location
Quadama (in Wajir North)
year first funded
2004
action
Construction of 2 Classrooms
output
To Improve Education Standard
implementation status
Complete
total cost
Ksh 750,000
estimate
Ksh 750,000

Noclassrooms In Ingirir

location
Ingirir (in Wajir North)
year first funded
2004
action
Construction of 2 Classrooms
output
Improve Education Standard
implementation status
Complete
total cost
Ksh 750,000
estimate
Ksh 750,000

Noclassrooms In Adadijole

location
Ogorji (in Wajir North)
year first funded
2004
action
Construction of A Classroom
output
Improve Education
implementation status
Complete
total cost
Ksh 700,000
estimate
Ksh 700,000

Distilling Of Pan In Danaba

location
Danaba (in Wajir North)
year first funded
2004
action
Disilt A Pan
output
Improve Water
implementation status
Complete
total cost
Ksh 600,000
estimate
Ksh 600,000

Equipping Bute Community Library

location
Bute (in Wajir North)
year first funded
2004
action
Equip Library
output
Improve Library Service
implementation status
Equipped
total cost
Ksh 560,000
estimate
Ksh 560,000

Head Teacher House In Buna Secondary School

location
Buna (in Wajir North)
year first funded
2007
action
Completion Of Head Teacher House
output
Improve Education Facilities
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 500,000

Furniture In Bute Girls

location
Bute (in Wajir North)
year first funded
2006
action
Purchase Furniture For School
output
Improve Education
implementation status
Complete
total cost
Ksh 500,000
estimate
Ksh 500,000

Underground Wall Tank For Bute Boys Secondary School

location
Bute (in Wajir North)
year first funded
2007
action
Construction Of Water Tank
output
Improving Water Facilities
implementation status
Not Yet Started
total cost
Ksh 500,000
estimate
Ksh 500,000

One Classroom In Korondille

location
Korondille (in Wajir North)
year first funded
2006
action
Construction of A Classroom
output
Improve Education
implementation status
-
total cost
Ksh 400,000
estimate
Ksh 400,000

Furniture In Bute Boys

location
Bute (in Wajir North)
year first funded
2006
action
Procumbent Stage
output
-
implementation status
-
total cost
Ksh 300,000
estimate
Ksh 300,000

Bute Arid Zone Primary School

location
Bute (in Wajir North)
year first funded
2007
action
Purchase Of Furnitures
output
Improving Education Facilities
implementation status
Not Yet Started
total cost
Ksh 300,000
estimate
Ksh 300,000

Pipe Of Water In Bute Secondary School

location
Bute (in Wajir North)
year first funded
2003
action
Pipe Water
output
Support Waer In School
implementation status
Complee
total cost
Ksh 270,000
estimate
Ksh 270,000

Bute Air Strip

location
Bute (in Wajir North)
year first funded
2004
action
Air Strip Constructed
output
-
implementation status
not known
total cost
Ksh 143,999
estimate
Ksh 143,999