The Constituencies Development Fund was established through the CDF Act, 2003 as a public funded kitty that targets development projects at the grassroots level.
It is one of the several devolved funds set up by the Government to mitigate poverty and to harmonize the spread of development throughout the country. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency. It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
It aims at ensuring a portion of the Government Annual Revenue is earmarked for constituencies to finance development projects qualified on a priority basis arrived at by members of a constituency.
Bursary Funds
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2006
- action
- Bursary Allocation
- output
- Improve Education Standards
- implementation status
- Bursary Allocated
- total cost
- Ksh 22,053,156
- estimate
- Ksh 0
Emergency Fund
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2004
- action
- Disaster Management
- output
- Mitigate Risks
- implementation status
- Meet Constituents Unforeseen Calamities Within Resources
- total cost
- Ksh 9,990,352
- estimate
- Ksh 0
Werugha Multipurpose Hall
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2004
- action
- Rehabillitation Of Old Hall
- output
- Meeting Place
- implementation status
- Ground Floor Re-Done & Furniture Bought
- total cost
- Ksh 7,100,000
- estimate
- Ksh 8,000,000
Grader Project
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2004
- action
- Buy A Constituency Grader
- output
- Make Road Construction Easy & Fast
- implementation status
- Equipment Maintainance Logistics Difficult
- total cost
- Ksh 7,000,000
- estimate
- Ksh 21,000,000
Administration
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2003
- action
- Pay For Office Administrative Expenses
- output
- Smooth Office Administration
- implementation status
- Prompt Services To All Stake Holders
- total cost
- Ksh 6,464,467
- estimate
- Ksh 0
Rural Electrification
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2008
- action
- Connect Most Of The Public Institutions With Power
- output
- Lighting & Support Jua Kali Sector Initiatives
- implementation status
- Waiting For Implementation Moderates From Rural Electrification Authority
- total cost
- Ksh 5,000,000
- estimate
- Ksh 10,000,000
Kiloghwa-Kishenyi-Lolo N
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2004
- action
- Intake Construction & Pipes Laying
- output
- Clean Water For Domestic Use
- implementation status
- Survey, Intake & Tank Complete. Pipe Purchase In Tendering Process
- total cost
- Ksh 4,500,000
- estimate
- Ksh 16,000,000
Saghasa-Vighombonyi
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2003
- action
- Construction Of Irizi Tank, Pump Installation & Pipe Laying
- output
- Access Water For Domestic Use
- implementation status
- Tank Constructed, Pump Purchased & Pipe Laying In Progress
- total cost
- Ksh 4,400,000
- estimate
- Ksh 10,000,000
Iyale-Msidunyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2004
- action
- Tank, Intake Construction & Pipe Laying
- output
- Clean Water For Domestic Use
- implementation status
- Tank, Intake Construction, Pipes Laid & Others To Be Bought
- total cost
- Ksh 4,100,000
- estimate
- Ksh 6,000,000
Kishushe
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2006
- action
- Construction Of ChiefS Office & Build A Modern Community Hall
- output
- Meeting Place
- implementation status
- Chief Office Built & Hall Biuld To Windows Level
- total cost
- Ksh 2,900,000
- estimate
- Ksh 7,000,000
Mbale
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2006
- action
- Construction of A Modern Community
- output
- Meeting Place
- implementation status
- Rough Stones & Sand Bought, Bq Done, Scoping Foundation
- total cost
- Ksh 2,700,000
- estimate
- Ksh 7,000,000
Majughu-Mwanda
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2003
- action
- Survey, Tank & Intake Construction
- output
- Clean Water For Domestic Use
- implementation status
- Survey Done, Intake & Tank Constructed
- total cost
- Ksh 2,693,605
- estimate
- Ksh 10,000,000
Kakimwaita
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2003
- action
- Sinking Of Borehole, Pump & Pipe Laying
- output
- Access Water For Domestic Use
- implementation status
- Borehole Sunk, Water Salty & Pump Submerged
- total cost
- Ksh 2,535,921
- estimate
- Ksh 36,349,860
Constituency Office
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2008
- action
- Acquire Land & Build A Cdf Office
- output
- Acquire A Permanent Office Space
- implementation status
- Land Identified, Part Development Plan In Place. Boundaries Marked Out, Waiting For The Bq
- total cost
- Ksh 2,500,000
- estimate
- Ksh 12,000,000
Ngelenyi Dam
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- Water Permit, Construction Of 3 Water Pans
- output
- Access Water For Irrigation Use
- implementation status
- Bushes Around 6 Acre Dam Cleared, Indigenous Trees Planted & Pans Just Tendered
- total cost
- Ksh 2,300,000
- estimate
- Ksh 6,000,000
Wesu District Hospital
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2008
- action
- Repair Of 4 Chamber Mortuary, Oxygen Concentrators, Wheel Chairs & Baby Incubator
- output
- Quality Health Facilities Nearer To People
- implementation status
- Mortuary Repaired & Equipment Ordered
- total cost
- Ksh 2,240,905
- estimate
- Ksh 3,000,000
Mwanyalo School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2003
- action
- 4 New Classroom Construction
- output
- Better Classrooms
- implementation status
- 4 Classes Completed & Other 4 Raised To Window Level
- total cost
- Ksh 2,150,000
- estimate
- Ksh 5,000,000
Sangeroko
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2006
- action
- Purchase Of Equipment, Construction Of Lab & 2 Staff Houses
- output
- Health Facilities Nearer To People
- implementation status
- Equipment Bought - 2 Staff Houses Constructed & At Plastering Stage
- total cost
- Ksh 2,100,000
- estimate
- Ksh 3,000,000
Recurrent Expenditure
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2008
- action
- Meet Office Recurrent Expences
- output
- Smooth Office Administration
- implementation status
- Fueling Of Motor Cycles, Maintainace Of All Office Epuipment
- total cost
- Ksh 2,016,680
- estimate
- Ksh 0
Mbela Secondary School
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms & A Laboratory
- output
- Better Lerning Enviroment
- implementation status
- 2Classrooms Complete
- total cost
- Ksh 2,010,000
- estimate
- Ksh 5,500,000
Mghange Dawida
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2008
- action
- Construction Of A Modern Community Hall
- output
- Meeting Place
- implementation status
- Bq& Arc Drawings Done, Tendering Stage
- total cost
- Ksh 2,000,000
- estimate
- Ksh 7,000,000
Sirienyi School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2004
- action
- Construction Of 2 New Classrooms And Renovations
- output
- Better Classrooms
- implementation status
- Renovations Done & 2 New Classrooms Done But Missing Doors & Windows
- total cost
- Ksh 2,000,000
- estimate
- Ksh 2,000,000
Mwangea School
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation Of 7 Classrooms, Building Of Pre-School.
- output
- Better Classrooms
- implementation status
- Renovations Done, 1 Class Complete, Toilet Excavated
- total cost
- Ksh 2,000,000
- estimate
- Ksh 5,277,079
Wundanyi Cooling Plant
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2008
- action
- Build Shell/Building To Accommodate Cooling Plant
- output
- Support Agri-Business
- implementation status
- Waiting For Project Approval By Cdf Board
- total cost
- Ksh 2,000,000
- estimate
- Ksh 5,000,000
Jkuat Taita
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2008
- action
- Install Lpg Facilities
- output
- Provide Improved & Environment Friendly Energy
- implementation status
- Tendering Process In Progress
- total cost
- Ksh 2,000,000
- estimate
- Ksh 0
Funju Secondary School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2004
- action
- Construction Of 4 New Classrooms & A Laboratory
- output
- Better Classrooms
- implementation status
- 3 Classrooms Completed & Furnished
- total cost
- Ksh 1,910,000
- estimate
- Ksh 5,000,000
Mjajenyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Tank & Intake Construction & Pipe Laying
- output
- Clean Water For Domestic Use
- implementation status
- Tank, Intake Construction Complete Pipes In Tendering Process
- total cost
- Ksh 1,900,000
- estimate
- Ksh 6,000,000
Mwarekeronyi
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2006
- action
- Intake Construction & Pipes Laying
- output
- Access Water For Domestic Use
- implementation status
- Intake Done, Purchase Of Pipes In Tendering Process
- total cost
- Ksh 1,900,000
- estimate
- Ksh 5,000,000
Monitoring & Evaluation
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2008
- action
- Capacity Build M&E Activities Of Cdf Projects
- output
- Ensure Projects Are Implemented As Required
- implementation status
- Exercise Carried Out Periodically & Advice To Pmc Provided Where Need Arises
- total cost
- Ksh 1,839,416
- estimate
- Ksh 0
Snr Chief Mwangeka
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2006
- action
- Dorm Construction
- output
- Better Environment
- implementation status
- Work In Progress
- total cost
- Ksh 1,800,000
- estimate
- Ksh 5,000,000
Manalonyi
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2006
- action
- Construction Of Intake, Tank & Pipe Laying
- output
- Access Water For Domestic Use
- implementation status
- Intake Constructed, Pipes Laid
- total cost
- Ksh 1,800,000
- estimate
- Ksh 3,000,000
Ndumbinyi School
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of 2 New Classroom & Renovations
- output
- Conducive Learning Environment
- implementation status
- 2 New Classroom Constructed
- total cost
- Ksh 1,700,000
- estimate
- Ksh 5,277,079
Ngolia School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of 4New Classrooms
- output
- Conducive Learning Environment
- implementation status
- Classes Raised To Window Level & Furniture Made
- total cost
- Ksh 1,600,000
- estimate
- Ksh 5,227,079
Mwanda
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of A Modern Community Hall & Offices
- output
- Meeting Place
- implementation status
- Extending Foundation As Advised By Dwo
- total cost
- Ksh 1,600,000
- estimate
- Ksh 7,000,000
Mwanda Dispensary
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2007
- action
- Tank Construction & Pipe Laying
- output
- Access Water For Domestic Use
- implementation status
- Pipes Tendering In Progress
- total cost
- Ksh 1,600,000
- estimate
- Ksh 6,000,000
Ngerenyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2008
- action
- n/a
- output
- -
- implementation status
- 200,000/= from emergency
- total cost
- Ksh 1,500,000
- estimate
- Ksh 7,000,000
Nguraru School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation Of 7 Classrooms
- output
- Better Classrooms
- implementation status
- Renovations Done
- total cost
- Ksh 1,500,000
- estimate
- Ksh 5,000,000
Funju/Mwaroko
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2006
- action
- Intake Construction & Pipes Laying
- output
- Access Water For Domestic Use
- implementation status
- Intake Done, Some Pipes Laid & More To Be Bought
- total cost
- Ksh 1,500,000
- estimate
- Ksh 3,786,619
Mlamba School
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2004
- action
- New Classroom Construction
- output
- Better Classrooms
- implementation status
- 3 New Classrooms Complete
- total cost
- Ksh 1,500,000
- estimate
- Ksh 5,000,000
Mghange Dawida
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2005
- action
- Purchase Of Equipment, Construction Of Lab & 2 Staff Houses
- output
- Health Facilities Nearer To People
- implementation status
- Equipment Bought -2 Staff Houses Tender In Progress
- total cost
- Ksh 1,500,000
- estimate
- Ksh 3,000,000
Mraru
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2007
- action
- Bridge Construction
- output
- Easier Transport
- implementation status
- Funds Inadequate
- total cost
- Ksh 1,500,000
- estimate
- Ksh 2,000,000
Choke School
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2003
- action
- Renovation Of 3 Classrooms & Purchase Of Desks
- output
- Better Classrooms
- implementation status
- Renovations Done & Desks Purchased
- total cost
- Ksh 1,450,000
- estimate
- Ksh 5,000,000
Mwataru
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2003
- action
- Purchase Of Piping Materials
- output
- Access Water For Domestic Use
- implementation status
- Materials Bought
- total cost
- Ksh 1,400,000
- estimate
- Ksh 5,000,000
Kiamachughu School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of 4New Classrooms
- output
- Conducive Learning Environment
- implementation status
- 4 Classrooms Built Not Plastered & Equipped With Wooden Desks, Tables & Chairs
- total cost
- Ksh 1,400,000
- estimate
- Ksh 5,227,079
Mbauro School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Renovations Done
- total cost
- Ksh 1,300,000
- estimate
- Ksh 5,000,000
Loghia
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Survey, Intake, Tank & Pipes Laying
- output
- Clean Water For Domestic Use
- implementation status
- Survey, Intake, Tank Complete & Pipes In Tendering Process
- total cost
- Ksh 1,200,000
- estimate
- Ksh 2,000,000
Mbanga Ngwale
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2005
- action
- Intake Renovations, Tank Construction & Pipes Laying
- output
- Clean Water For Domestic Use
- implementation status
- Tank Constructed & Pipes Laid
- total cost
- Ksh 1,200,000
- estimate
- Ksh 4,000,000
Sangenyi School
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Renovations & Desks Purchased
- total cost
- Ksh 1,200,000
- estimate
- Ksh 5,000,000
Iyale School
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2006
- action
- Construction Of 3 New Classroom
- output
- Conducive Learning Environment
- implementation status
- 2 Classes Complete, 3Rd At Foundation Level
- total cost
- Ksh 1,200,000
- estimate
- Ksh 5,000,000
Daku School
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2006
- action
- Construction Of 4 New Classrooms
- output
- Conducive Learning Environment
- implementation status
- 2 Classrooms Complete, 2 Built Without Doors And Windows
- total cost
- Ksh 1,200,000
- estimate
- Ksh 5,227,079
Sangenyi Kishushe
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2007
- action
- Pipes Laying
- output
- Clean Water For Domestic Use
- implementation status
- Pipes Tendering In Progress
- total cost
- Ksh 1,100,000
- estimate
- Ksh 2,000,000
Nyache School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations Of 4 Classrooms
- output
- Better Classrooms
- implementation status
- Renovations Done & Furniture Bought
- total cost
- Ksh 1,100,000
- estimate
- Ksh 5,000,000
Kishushe School
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2005
- action
- Renovations & Construction Of 1 New Classroom
- output
- Conducive Learning Environment
- implementation status
- Class Build But Without Windows & Door
- total cost
- Ksh 1,100,000
- estimate
- Ksh 2,000,000
Shigharo School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Renovations Complete
- total cost
- Ksh 1,100,000
- estimate
- Ksh 5,000,000
Shimbo School
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Text Books
- output
- Better Classrooms & Good Results
- implementation status
- Books Purchased
- total cost
- Ksh 1,100,000
- estimate
- Ksh 3,000,000
Toro
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Survey, Intake, Tank & Pipes Laying
- output
- Clean Water For Domestic Use
- implementation status
- Survey, Intake & Tank Complete. Pipes In Tendering Process
- total cost
- Ksh 1,100,000
- estimate
- Ksh 6,354,650
Matasenyi
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2003
- action
- Pipes Laying
- output
- Clean Water For Domestic Use
- implementation status
- Pipes Tendering In Progress
- total cost
- Ksh 1,100,000
- estimate
- Ksh 5,000,000
Ngonda Nursery Hall
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- New Construction
- output
- Meeting Place
- implementation status
- Hall Biult, & Plastic Chairs Bought
- total cost
- Ksh 1,100,000
- estimate
- Ksh 2,000,000
Mwanda School
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2003
- action
- Renovations
- output
- Better Classrooms
- implementation status
- 2 Classes Constructed
- total cost
- Ksh 1,050,000
- estimate
- Ksh 5,000,000
Funju School
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of 4 New Classroom
- output
- Increased Enrollment
- implementation status
- 3 Incomplete Classrooms Constructed
- total cost
- Ksh 1,018,237
- estimate
- Ksh 2,500,000
Wumingu Cooling Plant
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2008
- action
- Murram Access Road
- output
- Ensure Road Is Accessible Always
- implementation status
- Waiting For Project Approval By Cdf Board
- total cost
- Ksh 1,000,000
- estimate
- Ksh 3,000,000
Mghange Nyika Dispensary
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2009
- action
- Biuld A Marternity Ward
- output
- Ouality Health Care
- implementation status
- Foundation Being Laid
- total cost
- Ksh 1,000,000
- estimate
- Ksh 3,000,000
Werugha Dispensary
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2009
- action
- Biuld A Twin Staff House
- output
- Retention Of Government Health Workers
- implementation status
- Tendering Process Ongoing
- total cost
- Ksh 1,000,000
- estimate
- Ksh 1,500,000
Shanga-Msangarinyi
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Tank, Intake Construction & Pipe Laying
- output
- Clean Water For Domestic Use
- implementation status
- Tank, Intake Construction & Pipes Laid
- total cost
- Ksh 1,000,000
- estimate
- Ksh 3,000,000
Mazizi-Safughi
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Intake, Servey, Electricity Connection&Pipe Laying
- output
- Clean Water For Domestic Use
- implementation status
- Kplc Deposit Of 700,000/= Paid. Electricity Not Connected
- total cost
- Ksh 1,000,000
- estimate
- Ksh 5,000,000
Shagha School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2006
- action
- Renovations & Construction Of 1 New Classroom
- output
- Conducive Learning Environment
- implementation status
- Class Build But Without Windows & Door
- total cost
- Ksh 1,000,000
- estimate
- Ksh 0
Mwarombo School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Renovations & Desks Purchased
- total cost
- Ksh 1,000,000
- estimate
- Ksh 5,000,000
Mwarungu School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2004
- action
- Workshop Construction & Purchase Of Tools
- output
- Acquisition Of Technical Skills
- implementation status
- Ground Floor Complete
- total cost
- Ksh 1,000,000
- estimate
- Ksh 5,000,000
Maghimbinyi School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- Renovations Of 8 Classes
- output
- Better Classrooms
- implementation status
- Renovations Done & Put Windows & Glasses
- total cost
- Ksh 900,000
- estimate
- Ksh 5,227,079
Kidule School
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2006
- action
- Construction Of 2 New Classroom
- output
- Conducive Learning Environment
- implementation status
- 1 Class Complete. Materials For 2Nd Classroom Now On Site
- total cost
- Ksh 900,000
- estimate
- Ksh 5,000,000
Ngulu School
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Floors Of 8 Classes Done & Window Glasses For 6 Classes Bought
- total cost
- Ksh 900,000
- estimate
- Ksh 5,227,079
Mwakishimba School
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Renovations & Desks Purchased
- total cost
- Ksh 900,000
- estimate
- Ksh 5,000,000
St. Johns Secondary School
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2006
- action
- Construction Of New Toilet & Laboratory
- output
- Better Sanitary & Science Facilities
- implementation status
- Toilet Complete, Laboratory Works In Tendering Process
- total cost
- Ksh 900,000
- estimate
- Ksh 5,000,000
Mlechi School
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2005
- action
- Renovations Of 4 Classrooms
- output
- Better Classrooms
- implementation status
- Incomplete
- total cost
- Ksh 900,000
- estimate
- Ksh 5,227,079
Mghalu Secondary School
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2005
- action
- Furniture & Construction Of 2 New Classrooms
- output
- Better Learning Environment
- implementation status
- Chairs & Desks Bought, Construction Works In Tendering Stage.
- total cost
- Ksh 850,000
- estimate
- Ksh 3,000,000
Enviroment Project
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2008
- action
- Plant Indigenous Trees
- output
- Enhance Our Water Catchments
- implementation status
- Prolonged Drought Caused Delayed Implementation
- total cost
- Ksh 828,296
- estimate
- Ksh 3,000,000
Mwandiria
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2009
- action
- Construction Of A Bridge
- output
- Easier Transport
- implementation status
- Tendering Process
- total cost
- Ksh 800,000
- estimate
- Ksh 1,200,000
Sungululu School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation Of Computer Rooms
- output
- Better Classrooms
- implementation status
- Renovations Done
- total cost
- Ksh 800,000
- estimate
- Ksh 5,000,000
Mwaroko School
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Verandah Done Halfway, Desks & Cupboard Bought
- total cost
- Ksh 800,000
- estimate
- Ksh 5,000,000
Canon Kituri School
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2006
- action
- Dorm Construction
- output
- Better Environment
- implementation status
- Work In Progress
- total cost
- Ksh 800,000
- estimate
- Ksh 5,000,000
Mbanga Ngombe
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2005
- action
- Intake Construction & Pipes Laying
- output
- Clean Water For Domestic Use
- implementation status
- Survey Done, Intake In Progress
- total cost
- Ksh 800,000
- estimate
- Ksh 4,000,000
Paranga School
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations Of 4 Classrooms
- output
- Better Classrooms
- implementation status
- Renovations Done
- total cost
- Ksh 800,000
- estimate
- Ksh 5,000,000
Mwafunja
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2007
- action
- Construction Of A Bridge
- output
- Easier Transport
- implementation status
- Bridge Constructed, To Build Gabions
- total cost
- Ksh 800,000
- estimate
- Ksh 1,000,000
MaynaRoad School
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2003
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Renovations Complete
- total cost
- Ksh 750,000
- estimate
- Ksh 5,000,000
Maghimbinyi School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2006
- action
- Renovations Of 5 Classrooms
- output
- Better Classrooms
- implementation status
- Renovations Done & Furniture Bought
- total cost
- Ksh 700,000
- estimate
- Ksh 5,227,079
Mdundonyi-Mbale Line
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2006
- action
- Intake Construction & Pipes Laying
- output
- Access Water For Irrigation Use
- implementation status
- Intake Constructed.
- total cost
- Ksh 700,000
- estimate
- Ksh 1,000,000
Kitumbi School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2006
- action
- Construction Of 2 New Classrooms
- output
- Better Classrooms
- implementation status
- 2 Classes Raised To Lintel, Roofing Material & Half Iron Sheets
- total cost
- Ksh 700,000
- estimate
- Ksh 7,880,590
Ngilinyi School
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2006
- action
- Construction Of 2 New Classroom
- output
- Conducive Learning Environment
- implementation status
- 1 Classroom Complete, Materials For Other Classroom To Be Procured
- total cost
- Ksh 700,000
- estimate
- Ksh 5,000,000
Msangarinyi School
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Renovations Done
- total cost
- Ksh 700,000
- estimate
- Ksh 5,227,079
Mdundonyi Mbal School
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2007
- action
- Construction Of A New Pre-School
- output
- Increased Enrollment
- implementation status
- 1 Classroom Completed Without Doors And Toilet Dug.
- total cost
- Ksh 700,000
- estimate
- Ksh 500,000
Ngelenyi-Choke
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2007
- action
- Purchase Of Piping Materials
- output
- Access Water For Domestic Use
- implementation status
- Tendering In Progress
- total cost
- Ksh 700,000
- estimate
- Ksh 2,000,000
Shanga-Mlondo
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2003
- action
- Intake Construction & Pipes Laying
- output
- Access Water For Domestic Use
- implementation status
- Intake Constructed.
- total cost
- Ksh 650,000
- estimate
- Ksh 3,000,000
Mwanda
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2005
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 600,000
- estimate
- Ksh 1,000,000
Kiwinda School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2006
- action
- New Classroom Construction
- output
- Better Classrooms
- implementation status
- Work In Progress
- total cost
- Ksh 600,000
- estimate
- Ksh 2,000,000
Ngangao School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- Dining Hall Construction & Purchase Of Text Books
- output
- Access Books, Good Results
- implementation status
- Text Books Purchased, Construction Materials On Site
- total cost
- Ksh 600,000
- estimate
- Ksh 3,000,000
Werugha School
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Renovations Completed
- total cost
- Ksh 600,000
- estimate
- Ksh 5,000,000
Ngongidinyi School
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2007
- action
- Renovations Of 2 Classrooms
- output
- Better Classrooms
- implementation status
- Renovations Done
- total cost
- Ksh 600,000
- estimate
- Ksh 2,000,000
Irido/Irodo B
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- General Maintenance, Intake Construction & Pipe Laying
- output
- Clean Water For Domestic Use
- implementation status
- Intake Built, Maintenance Done & Pipe Laying In Progress
- total cost
- Ksh 600,000
- estimate
- Ksh 1,000,000
Tambaru
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Tank Construction & Pipe Laying
- output
- Water For Irrigation
- implementation status
- Pipes Laid
- total cost
- Ksh 600,000
- estimate
- Ksh 2,000,000
Tinde
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2006
- action
- Intake, Tank & Pipes
- output
- Access Water For Domestic Use
- implementation status
- Intake Tank Complete
- total cost
- Ksh 600,000
- estimate
- Ksh 672,184
Mdundonyi-Mchorongonyi
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Tank Construction & Pipe Laying
- output
- Clean Water For Domestic Use
- implementation status
- Tank Complete & Pipes Laying Complete
- total cost
- Ksh 550,000
- estimate
- Ksh 600,000
Sasenyi-Paranga
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2003
- action
- Purchase Of Piping Materials
- output
- Access Water For Domestic Use
- implementation status
- Tendering In Progress
- total cost
- Ksh 520,000
- estimate
- Ksh 2,500,000
St. James School
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Renovations Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
Wumingu School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2006
- action
- Renovations Of 4 Classrooms
- output
- Better Classrooms
- implementation status
- Materials Purchased
- total cost
- Ksh 500,000
- estimate
- Ksh 5,227,079
Mlilo School
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of 2 New Classrooms
- output
- Conducive Learning Environment
- implementation status
- 2 New Classes Constructed
- total cost
- Ksh 500,000
- estimate
- Ksh 5,277,079
Nyambu School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Roofing & Flooring Of 6 Classes, Nursery School Toilet Done
- total cost
- Ksh 500,000
- estimate
- Ksh 5,227,079
Lushangonyi School
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2006
- action
- Classroom Renovations & Build 1 Toilet
- output
- Better Classrooms
- implementation status
- Renovations Done, Toilet Sunk & Materials Procured
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
Fighinyi School
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Renovations Completed
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
St. Johns School
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2004
- action
- Renovations
- output
- Better Classrooms
- implementation status
- Classrooms Renovated
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
Mlawa School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2004
- action
- New Classroom Construction
- output
- Better Classrooms
- implementation status
- New Class Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
Ngonda School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- n/a
- output
- -
- implementation status
- inuse
- total cost
- Ksh 500,000
- estimate
- Ksh 0
Dalmas Moka Secondary School
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2005
- action
- Purchase Of Text Books
- output
- Access Books For Better Results
- implementation status
- Books Purchased
- total cost
- Ksh 500,000
- estimate
- Ksh 3,000,000
Draggrey School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2009
- action
- Construction Of 1 Classroom & Furniture
- output
- Offer More Form One Vacaces To Locals
- implementation status
- Waiting For Bill Of Quontites
- total cost
- Ksh 500,000
- estimate
- Ksh 2,000,000
St Marys Lushangonyi
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2009
- action
- Construction Of 1 Classroom & Furniture
- output
- Offer More Form One Vacaces To Locals
- implementation status
- Waiting For Bill Of Quontites
- total cost
- Ksh 500,000
- estimate
- Ksh 2,000,000
Mwanda School
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2004
- action
- Renovation
- output
- Acquisition Of Technical Skills
- implementation status
- Renovations Done
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
Mbale School
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2004
- action
- Renovation
- output
- Acquisition Of Technical Skills
- implementation status
- Renovations Done
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
Mwangafwa School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2004
- action
- Renovation
- output
- Acquisition Of Technical Skills
- implementation status
- Workshop Complete
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
Mwangoto
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2006
- action
- Intake Construction & Pipes Laying
- output
- Access Water For Domestic Use
- implementation status
- Intake Constructed.
- total cost
- Ksh 500,000
- estimate
- Ksh 5,000,000
Mbaramghondi
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2007
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 500,000
- estimate
- Ksh 500,000
Sungulu Kitukunyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2009
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 500,000
- estimate
- Ksh 700,000
Saghasa
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2006
- action
- Build A Hall
- output
- Meeting Place
- implementation status
- Hall Build, Plascic Chairs Bought, Next Time A Tv
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Wundanyi Disabled Persons
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2004
- action
- Purchase Of Tools
- output
- Independency
- implementation status
- Amount Not Fully Utilized, Will Be Given Cidc Shed
- total cost
- Ksh 500,000
- estimate
- Ksh 1,000,000
Choke-Wanganga
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2007
- action
- Purchase Of Piping Materials
- output
- Access Water For Domestic Use
- implementation status
- Tendering In Progress
- total cost
- Ksh 450,000
- estimate
- Ksh 2,000,000
Mwanguwi
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2006
- action
- De-Silt A Dam
- output
- Access Water For Irrigation Use
- implementation status
- Dam De-Silted
- total cost
- Ksh 450,000
- estimate
- Ksh 600,000
Marumange-Nursery
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Build A Hall
- output
- Meeting Place
- implementation status
- Renovations Done,Project On Church Land
- total cost
- Ksh 450,000
- estimate
- Ksh 1,000,000
Choke-Lushangonyi
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2006
- action
- Intake Construction & Pipes Laying
- output
- Access Water For Domestic Use
- implementation status
- Survey Done, Intake In Progress
- total cost
- Ksh 400,000
- estimate
- Ksh 10,694,772
Mwangola Girls
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2006
- action
- New Construction
- output
- Better Classrooms
- implementation status
- Foundation Done
- total cost
- Ksh 400,000
- estimate
- Ksh 5,000,000
Irienyi Dam
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2006
- action
- Desilting
- output
- Access Water For Domestic Use
- implementation status
- Dam Desilted
- total cost
- Ksh 400,000
- estimate
- Ksh 500,000
Mazizi-Mwakishamba
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2004
- action
- Intake Construction & Pipes Laying
- output
- Access Water For Domestic Use
- implementation status
- Intake Constructed.
- total cost
- Ksh 390,000
- estimate
- Ksh 2,000,000
Mwamracha
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2003
- action
- Intake Construction & Pipes Laying
- output
- Clean Water For Domestic Use
- implementation status
- Intake Construction & Pipes Laid
- total cost
- Ksh 350,000
- estimate
- Ksh 2,000,000
Mwanamsha
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Intake Construction & Pipes Laying
- output
- Clean Water For Domestic Use
- implementation status
- Intake Construction & Pipes Laid
- total cost
- Ksh 300,000
- estimate
- Ksh 500,000
Solome
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2007
- action
- Intake Construction & Pipes Laying
- output
- Access Water For Domestic Use
- implementation status
- Tendering In Progress
- total cost
- Ksh 300,000
- estimate
- Ksh 2,000,000
Mdundonyi School
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2007
- action
- Construction Of 2 Classrooms
- output
- Better Classrooms
- implementation status
- 1 Classroom Built Without Doors & Windows
- total cost
- Ksh 300,000
- estimate
- Ksh 5,000,000
Werugha Library
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2007
- action
- Electricity Connection & Wiring
- output
- Encourage Reading Culture In The Village
- implementation status
- Wiring Done, Waiting For Power Connection By Kplc
- total cost
- Ksh 300,000
- estimate
- Ksh 1,000,000
Jipe Kishushe
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2008
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 300,000
- estimate
- Ksh 600,000
Mwanguwi-Mogho-Mghamb
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2007
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 300,000
- estimate
- Ksh 300,000
Kapp Project
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2008
- action
- Make Tables For Drying Macadamia Nuts
- output
- Support Agri-Business
- implementation status
- Waiting For Project Approval By Cdf Board
- total cost
- Ksh 300,000
- estimate
- Ksh 1,000,000
Kiwani
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2006
- action
- Intake Construction & Pipes Laid
- output
- Access Water For Domestic Use
- implementation status
- Intake Constructed. Pipes Laid
- total cost
- Ksh 300,000
- estimate
- Ksh 2,000,000
Kisughusa Madima
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2006
- action
- Intake Pipes
- output
- Access Water For Irrigation
- implementation status
- Intake Rehabilitated, Pipes Laid
- total cost
- Ksh 300,000
- estimate
- Ksh 1,000,000
Chome
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2004
- action
- Intake Construction & Pipes Laid
- output
- Clean Water For Domestic Use
- implementation status
- Intake & Pipes Laying Complete
- total cost
- Ksh 300,000
- estimate
- Ksh 1,000,000
Kitumbi School
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of Dormitory
- output
- Enhanced Boarding Facilities
- implementation status
- Materials Bought
- total cost
- Ksh 250,000
- estimate
- Ksh 4,000,000
Mshinyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of A Bridge
- output
- Easier Transport
- implementation status
- Bridge Constructed
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Mwakiwiwi School
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2005
- action
- Purchase Of Text Books
- output
- Access Books For Better Results
- implementation status
- Books Purchased
- total cost
- Ksh 200,000
- estimate
- Ksh 3,000,000
Wesu School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2007
- action
- Construction Of 1 Classroom & Furniture
- output
- Increased Enrollment
- implementation status
- 1 Classroom Completed & Furnished
- total cost
- Ksh 200,000
- estimate
- Ksh 250,000
Dighare-Kitume
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2007
- action
- Pipes Laying
- output
- Clean Water For Domestic Use
- implementation status
- Pipes Tendering In Progress
- total cost
- Ksh 200,000
- estimate
- Ksh 2,000,000
Mlondo-Mraru-Mghambinyi
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2007
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 200,000
- estimate
- Ksh 250,000
Mwarangenyi-Mbula
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2007
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Kituri-Ruma-Wesu
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2007
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 200,000
- estimate
- Ksh 300,000
Mnyuchi-Sirienyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2007
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 200,000
- estimate
- Ksh 400,000
Lushangonyi
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2009
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Lashu
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2008
- action
- Stone Breaking & Bush Clearing
- output
- Build An Access Road
- implementation status
- Roads Maintained
- total cost
- Ksh 200,000
- estimate
- Ksh 500,000
Daku-Kishushe
- location
-
Kishushe
(in Wundanyi)
- year first funded
- 2003
- action
- Survey & Intake
- output
- Access Water For Domestic Use
- implementation status
- Survey & Intake Done
- total cost
- Ksh 187,835
- estimate
- Ksh 2,000,000
Chale/Mkororo
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of A Bridge
- output
- Easier Transport
- implementation status
- Bridge Constructed
- total cost
- Ksh 182,000
- estimate
- Ksh 300,000
Kishenyi
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2007
- action
- Bridge Construction
- output
- Easier Transport
- implementation status
- Funds Inadequate
- total cost
- Ksh 150,000
- estimate
- Ksh 900,000
Kighala Nursery Hall
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Renovations
- output
- Meeting Place
- implementation status
- Renovations Done
- total cost
- Ksh 150,000
- estimate
- Ksh 200,000
Kighala Kipotonyi
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of A Bridge
- output
- Easier Transport
- implementation status
- Bridge Constructed
- total cost
- Ksh 100,406
- estimate
- Ksh 200,000
Taita Youth Complex Mghange
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2006
- action
- New Construction
- output
- Meeting Place
- implementation status
- Architectural Plan Complete
- total cost
- Ksh 100,000
- estimate
- Ksh 10,000,000
Kilwala Mbenge Mrangi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2007
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 100,000
- estimate
- Ksh 300,000
Kitukunyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2006
- action
- Construction of A Modern Community
- output
- Meeting Place
- implementation status
- Funding Insufficient, Money In Main Account
- total cost
- Ksh 100,000
- estimate
- Ksh 3,000,000
Chome School
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2006
- action
- Purchase Of Furniture
- output
- Sufficient Furniture For The Students
- implementation status
- Furniture Purchased
- total cost
- Ksh 100,000
- estimate
- Ksh 200,000
Mrumenyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2006
- action
- Intake Construction
- output
- Access Water For Domestic Use
- implementation status
- Intake Done
- total cost
- Ksh 100,000
- estimate
- Ksh 300,000
Mangalenyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2006
- action
- Intake Construction
- output
- Access Water For Domestic Use
- implementation status
- Intake Done
- total cost
- Ksh 100,000
- estimate
- Ksh 300,000
Irido Intake
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2006
- action
- Intake Construction
- output
- Access Water For Domestic Use
- implementation status
- Intake Done
- total cost
- Ksh 100,000
- estimate
- Ksh 500,000
Kidakiwi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2006
- action
- Survey & Intake
- output
- Access Water For Domestic Use
- implementation status
- Intake Done
- total cost
- Ksh 100,000
- estimate
- Ksh 2,327,461
Ndonga Sungululu
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2003
- action
- Survey & Intake
- output
- Access Water For Domestic Use
- implementation status
- Survey & Intake Done
- total cost
- Ksh 100,000
- estimate
- Ksh 100,000
Kiangungu-Msidunyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2003
- action
- Survey & Intake
- output
- Access Water For Domestic Use
- implementation status
- Survey & Intake Done
- total cost
- Ksh 100,000
- estimate
- Ksh 3,000,000
Sangenyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2007
- action
- Bush Clearing & Road Shaping
- output
- Easier Transport
- implementation status
- Roads Maintained
- total cost
- Ksh 100,000
- estimate
- Ksh 400,000
Aringanga Sungulu
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2003
- action
- Survey & Intake
- output
- Access Water For Domestic Use
- implementation status
- Survey & Intake Done
- total cost
- Ksh 80,000
- estimate
- Ksh 800,000
Kishenyi
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 70,000
- estimate
- Ksh 100,000
Ngulu
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Construction Of A Bridge
- output
- Easier Transport
- implementation status
- Bridge Constructed
- total cost
- Ksh 65,000
- estimate
- Ksh 120,000
Mghange Nyika
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 50,000
- estimate
- Ksh 100,000
Iyale
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Masumbenyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Mghange Dawinda
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Sughululu
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Mtukunyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Mghambonyi
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- n/a
- output
- -
- implementation status
- -
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Lushangonyi
- location
-
Mghange
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Mwanda
- location
-
Mwanda
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Malela
- location
-
Werugha
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Ngilenyi
- location
-
Wundanyi
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Nyache
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Mwasungia
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Iriwa
- location
-
Mbale
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000
Mwangorua
- location
-
Wumingu
(in Wundanyi)
- year first funded
- 2005
- action
- Renovation & Purchase Of Dip Chemical
- output
- Healthy Animals
- implementation status
- Renovations Done, Dip Chemicals Purchased
- total cost
- Ksh 20,000
- estimate
- Ksh 100,000