14 Aug 2018 in National Assembly:
THAT, despite having not formally served upon the affected land owners with the necessary legal notices – and therefore without compensation - the KRC in association with China Communications Construction Company (CCCC), the NLC and the local Provincial The electronic version of the Official Hansard Report is for information purposes only. Acertified version of this Report can be obtained from the Hansard Editor.
view
14 Aug 2018 in National Assembly:
THAT, despite having not formally served upon the affected land owners with the necessary legal notices – and therefore without compensation - the KRC in association with China Communications Construction Company (CCCC), the NLC and the local Provincial The electronic version of the Official Hansard Report is for information purposes only. Acertified version of this Report can be obtained from the Hansard Editor.
view
14 Aug 2018 in National Assembly:
Administration, through a number of uncoordinated public gatherings harangued and intimidated the land owners and other project affected persons to relocate and allow what they then termed as early entry to the China Communications Construction Company areas for the urgent purpose of construction of the SGR Phase 2A on the understanding that the NLC will fasttrack their compensation;
view
14 Aug 2018 in National Assembly:
Administration, through a number of uncoordinated public gatherings harangued and intimidated the land owners and other project affected persons to relocate and allow what they then termed as early entry to the China Communications Construction Company areas for the urgent purpose of construction of the SGR Phase 2A on the understanding that the NLC will fasttrack their compensation;
view
14 Aug 2018 in National Assembly:
THAT, in order to gain early entry, KRC and CCCC promised the residents of these areas that public utilities like electricity and water would not be affected by the construction;
view
14 Aug 2018 in National Assembly:
THAT, in order to gain early entry, KRC and CCCC promised the residents of these areas that public utilities like electricity and water would not be affected by the construction;
view
14 Aug 2018 in National Assembly:
THAT, in some instances where the land owners refused to allow early access by the company, the CCCC gained entry by force with the assistance of the Kenya Police Service officers deployed to protect the project company;
view
14 Aug 2018 in National Assembly:
THAT, in some instances where the land owners refused to allow early access by the company, the CCCC gained entry by force with the assistance of the Kenya Police Service officers deployed to protect the project company;
view
14 Aug 2018 in National Assembly:
THAT, consequently, the houses, farms, business and homes of affected persons were demolished to allow for early access by the company despite not affording the owners of those parcels an opportunity to look for alternative land to settle; `
view
14 Aug 2018 in National Assembly:
THAT, consequently, the houses, farms, business and homes of affected persons were demolished to allow for early access by the company despite not affording the owners of those parcels an opportunity to look for alternative land to settle; `
view