Mr. Deputy Speaker, Sir, I beg to reply.
view
-
7 Jul 2010 in National Assembly:
(a) Following the post-election violence in early 2008 and the resultant destruction of property, the two contractors requested for extension of the contract period due to the following reasons:
view
-
7 Jul 2010 in National Assembly:
(i) Building materials and construction vehicles were all destroyed and burnt by marauding gangs during post-election violence.
view
-
7 Jul 2010 in National Assembly:
(ii) Internally displaced persons occupied the building site for a period of five months. (iii) Extra works and variations were to be done.
view
-
7 Jul 2010 in National Assembly:
(iv) In adequate funding towards Development Expenditure on housing and office accommodation during the just ended financial year was also a factor.
view
-
7 Jul 2010 in National Assembly:
(b) Following the release of the funds, which we have done, the two contractors have been asked and directed to complete the works and as such, handing over and taking over of the projects has been rescheduled as follows---
view
-
7 Jul 2010 in National Assembly:
Mr. Deputy Speaker, Sir, the handing over and taking over of the projects has been rescheduled as follows:
view
-
7 Jul 2010 in National Assembly:
Kondele Police Station housing units will be handed over on 6th August. I will make sure that I am there to take over the keys.
view
-
7 Jul 2010 in National Assembly:
The Kisumu Police Station office block will be handed over on 23rd July, 2010. I hope the Questioner will be happy that we are going to take over the buildings in a monthâs time and two-weeks time respectively.
view
-
7 Jul 2010 in National Assembly:
Mr. Deputy Speaker, Sir, ordinarily, the buildings belong to the police. We cannot just take over a building without furniture. So, definitely, there will be some kind of furniture for work to continue.