20 Mar 2024 in Senate:
The electronic version of the Senate Hansard Report is for information purposesonly. A certified version of this Report can be obtained from the Director, Hansard and AudioServices, Senate.
view
20 Mar 2024 in Senate:
This has culminated in the accumulation of significant pending bills from certified works. Contractors have consequently been reluctant to complete the works in the affected projects, citing non-payment of their dues. The Government through the National Treasury is working on a mechanism to facilitate significant reduction of clearing of pending bills in the near future. This will result in the full resumption of completion of affected projects countrywide. The roads under the jurisdiction of Kenya National Highways Authority (KeNHA) in Nandi County have been managed through performance-based maintenance contracts and routine maintenance contracts depending on the planned intervention and available ...
view
20 Mar 2024 in Senate:
This has culminated in the accumulation of significant pending bills from certified works. Contractors have consequently been reluctant to complete the works in the affected projects, citing non-payment of their dues. The Government through the National Treasury is working on a mechanism to facilitate significant reduction of clearing of pending bills in the near future. This will result in the full resumption of completion of affected projects countrywide. The roads under the jurisdiction of Kenya National Highways Authority (KeNHA) in Nandi County have been managed through performance-based maintenance contracts and routine maintenance contracts depending on the planned intervention and available ...
view
20 Mar 2024 in Senate:
The electronic version of the Senate Hansard Report is for information purposesonly. A certified version of this Report can be obtained from the Director, Hansard and AudioServices, Senate.
view
20 Mar 2024 in Senate:
The electronic version of the Senate Hansard Report is for information purposesonly. A certified version of this Report can be obtained from the Director, Hansard and AudioServices, Senate.
view
20 Mar 2024 in Senate:
The project was originally schedule for completion in August 2022, a long time ago, but this has since been revised to August, 2025 due to inadequate budgetary allocation that have led to the contractor being unable to complete the projects due to cash flow challenges. Mr. Speaker, Sir, just for the comfort of the other Senators who might not have asked a similar question, this is what I told you earlier. That in the entire country, about Kshs60 billion is spend in KERRA roads from Mombasa to Malaba, Lokichogio to Loitokitok. All of them suffer this kind of consequences. That ...
view
20 Mar 2024 in Senate:
The project was originally schedule for completion in August 2022, a long time ago, but this has since been revised to August, 2025 due to inadequate budgetary allocation that have led to the contractor being unable to complete the projects due to cash flow challenges. Mr. Speaker, Sir, just for the comfort of the other Senators who might not have asked a similar question, this is what I told you earlier. That in the entire country, about Kshs60 billion is spend in KERRA roads from Mombasa to Malaba, Lokichogio to Loitokitok. All of them suffer this kind of consequences. That ...
view
20 Mar 2024 in Senate:
Thank you, Mr. Speaker, Sir. The total number of farm tractors presented for post-accident inspection are as tabulated below-
view
20 Mar 2024 in Senate:
Thank you, Mr. Speaker, Sir. The total number of farm tractors presented for post-accident inspection are as tabulated below-
view
20 Mar 2024 in Senate:
Thank you, Mr. Speaker, Sir. The Ministry, through the KeRRA, upgraded to bitumen standards a section of the Lwakhakha-Chwele-Kimilili-Kamukuywa road, namely the Lwakhakha- Korosiondet-Tulienge-Sirisia-Namwela-Chwele road (C815) as part of the Low Volume Seal Roads (LVSR) Programme. If the Senator was to go even further in his Question, he will notice that the Road is wearing out. It is one of the LVSR I was talking about, the Low Volume Seal Roads. The 30-kilometre section, which is under the KeRRA was completed in 2019 providing access to the Lwakhakha border point, thereby offering an alternative route to Uganda. The completion of ...
view