  • 19 Apr 2023 in National Assembly: I thank some banks that, as a result of our interventions, they have been kind to contractors because a number of them could easily have lost their properties through auctions. This is because of non-payment of facilities that they have received. The same information will be tabled and each Member of this House will have an opportunity, through your kind Office, Hon. Speaker, to see the projects in their counties or constituencies and understand the situation. I will repeat that, unfortunately, this is an inherited situation. I know many Kenyans are asking themselves why the Ministry is not facilitating construction ... view
  • 19 Apr 2023 in National Assembly: M/s Simora Group Limited and commenced on 16th August 2021.The contract sum for Phase II of the Kalisasi-Mumbuni Road (Kalisasi-Ikime section) is Ksh38,172,976.95. The contract for the construction of the 1-kilometre road was awarded to M/s M & J Holding Limited and commenced on 30th September 2022. The contract period for Phase I was 18 months and the works were expected to be completed by16th February 2023.The contractor has completed all the instructed major works and has requested for a substantial completion inspection, which will be conducted at the end of this month. The contract period for Phase II was ... view
  • 19 Apr 2023 in National Assembly: is 12.87 kilometres. The 10 kilometres from Migwani Town to Tulia Town have been completed, including some town roads. Therefore, the percentage of physical works completed for this additional section is 29.6 per cent, bringing the total completion of the entire project to 90.5 per cent. The project end of Defect Notification Period (DNP) is on 4th October 2023. However, the contractor has suspended works due to delayed payment of certificates amounting to Ksh1,155,896,907 and delayed land acquisition. The two factors are likely to affect the contract period. However, the Government has provided Ksh150 million in the Financial Year 2023/2024 ... view
  • 19 Apr 2023 in National Assembly: Hon. Speaker, I have not answered the Question. It would be good for good record to proceed and respond to the Question by the Hon. Member. I sympathise with the situation because I think there was an earlier Question that perhaps he did not really ask for the HANSARD, but I have already answered. view
  • 19 Apr 2023 in National Assembly: Hon. Speaker, I will proceed with Question No. 83 The construction of Mwingi-Slaughter House Road was done as part of the project for the construction of upgrading to bitumen standards of 3.7 kilometres KCB-Slaughter House Road in Mwingi, Kitui County, whose employer was the Department of Slum Upgrading under the State Department of Housing and Urban Development. I wish to state that, the Kenya Urban Roads Authority (KURA) was only called upon to provide project oversight role. The Project had 2 lots, that is lot 1 and 2. The Project contract sum was Ksh137,707,776.00 which covered 3.7 kilometers as indicated ... view
  • 19 Apr 2023 in National Assembly: The electronic version of the Official Hansard Report is for information purposesonly. A certified version of this Report can be obtained from the Hansard Editor. view
  • 19 Apr 2023 in National Assembly: Hon. Speaker, if you allow me, I will start with the question asked by Hon. Cynthia Muge about what we are doing concerning the roads. This will help in answering all the questions that have been asked. As I had already said, I think I should table the list officially in the House. Once I do that, in the subsequent conversations in the near future, Members will have a reference point of all the contracts in the entire 800 projects. From there, if Hon. Members want to consult with the agency or the Ministry, we are available. Two, I have ... view
  • 19 Apr 2023 in National Assembly: Thank you, Hon. Deputy Speaker. I know a number of questions are almost related. A generic answer would have been: ‘When the money is available’. First, let me delve into the main question on the Expressway by Hon. Mulyungi. The traffic status report of the Expressway since inauguration is indicated below: The total number of vehicles which have used the Expressway from its inception until the end of March 2023 was 12,491,403. The breakdown is as follows: 1. From May-June 2022, the total traffic volume was 1,257, 019 which is an average of 26,188 per day. 2. From July - ... view
  • 19 Apr 2023 in National Assembly: in time, they had caused a number of accidents due to over-speeding but, since measures have been put in place, we are reviewing the request that has come to my office to allow PSVs to pass through the Expressway. To answer the question related to A8 Road, the road below the Expressway, view
  • 19 Apr 2023 in National Assembly: I will gladly wind up, Hon. Temporary Speaker. The boda boda motor cycles should not be used on highways. We are not supposed to see them on Kitale-Bungoma Road or Kitale-Eldoret Road, but they are there. We must work with the reality that they are there. We are working on a mechanism of regulation. In the statements I made earlier, you notice I did not focus on the boda boda . I will be coming back with boda boda regulations as a result of the same issue. On the road Hon. Jayne Kihara has mentioned, again, Maela road is a ... view