7 Jun 2011 in National Assembly:
Mr. Speaker, Sir, the evaluation of contractors in that case is not only on financials only. That is because if we restricted our evaluation only on the financials, it would mean that anybody, even without any equipment or experience in the field of construction, would just come and bid and tomorrow, we will give him the tender on account of being the lowest bidder. Therefore, I would like to assure the hon. Member that we have an open criteria upon which members, when they are not satisfied, can appeal. When we award the contract, we have a 14 days period ...
view
-
26 May 2011 in National Assembly:
Mr. Temporary Deputy Speaker, Sir, I beg to reply.
view
-
26 May 2011 in National Assembly:
(a) The construction of the Gikumari Bridge on Road UPR3, that is at the Junction of A2 of Ruiru/Gikumari and Juja Farm, off Road E1535, connecting Juja and Munyu was constructed at a cost Kshs20 million. That was disbursed as follows: in the financial year 2008/2009, we allocated Kshs15 million; in the following year, 2009/2010, we allocated a further Kshs5 million. That is a total of Kshs20 million. The followings works were left as outstanding; the approach roads, the guard rails, the protection works, installation of relief culverts, backfilling of abutments of the approaches to the bridge, and gravel wearing ...
view
-
26 May 2011 in National Assembly:
Mr. Temporary Deputy Speaker, Sir, as I have indicated, the works are ongoing and we have not been able to certify the bridge work as complete. Once we are able to certify that, we will make the payments. Therefore, the monies allocated have not actually been spent. As for the photos that the hon. Member is volunteering to give--- I cannot certify whether they are of the same bridge and when they were taken; I will not be able to incorporate them in my answer.
view
-
26 May 2011 in National Assembly:
Mr. Temporary Deputy Speaker, Sir, I have indicated that before any amounts are paid, we will certify that the works are done as per the contract. Therefore, I think the concerns by the hon. Member that that money may have been spent are, indeed, not justified.
view
-
26 May 2011 in National Assembly:
Mr. Temporary Deputy Speaker, Sir, I do not suspect that the photos may be wrong. I have only indicated that if we want to know the current state of the road, we will ask for a certificate from our qualified engineers, who will be able to certify the state of works, and then payment can be done. I have no reason whatsoever, to doubt the photos.
view
-
26 May 2011 in National Assembly:
Mr. Temporary Deputy Speaker, Sir, the answer that I have given the hon. Member is, if I may read it verbatim:
view
-
26 May 2011 in National Assembly:
(b) The construction of the Juja/Gikumari Bridge has not been completed because the funds that had been allocated were not adequate to cover all the works. I have said that and I went on further to state which works were not completed.
view
-
26 May 2011 in National Assembly:
(c) The outstanding works which include the approach roads, guard rails and the protection works will be carried out within this financial year. Mr. Temporary Deputy Speaker, Sir, I have said as much.
view
-
24 May 2011 in National Assembly:
Mr. Speaker, Sir, I beg to reply. (a) The contract for rehabilitation of the Narok-Maasai Mara, that is, Sekenani Gate was awarded on 22nd November, 2010 to M/s Petra Construction Company Limited at a contract sum of Kshs378,034,797. The works commenced on 29th January, 2011 and are scheduled for completion on 28th January, 2012. (b) I want to assure the hon. Member that the contractors have not abandoned the site. Since the contract commenced the contractor has undertaken the following:-
view