All parliamentary appearances
Entries 221 to 230 of 496.
-
6 Aug 2014 in National Assembly:
(ii) The reasons for the stalling of the construction of Kisumu Airport-Kisian Section of Mau Summit-Busia Road and when work is expected to resume.
view
-
6 Aug 2014 in National Assembly:
(iii) The progress of construction of Mamboleo Junction/Rita Section of Mau Summit-Busia Road.
view
-
6 Aug 2014 in National Assembly:
Hon. Temporary Deputy Speaker, I beg to respond as follows.
view
-
6 Aug 2014 in National Assembly:
1. Nyamasaria-Kondele-Kisat Road, known as Kisumu Southern Bypass, is one of the roads under construction in the on-going rehabilitation of Nyamasaria-Kisumu-Kisian Road; it includes the Kisumu Bypass Road A1 and B1 project. The progress of the work on the bypass is currently at 75 per cent. The combined progress of the two projects is 84 per cent.
view
-
6 Aug 2014 in National Assembly:
2. The construction of Kisumu Airport-Kisian Section has not stalled. However, there has been slow progress of work on that road due to financial constrain. At the moment, the Government is making arrangements to provide funds to rehabilitate the section. The electronic version of the Official Hansard Report is for information purposesonly. A certified version of this Report can be obtained from the Hansard Editor.
view
-
6 Aug 2014 in National Assembly:
3. The section between Mamboleo Junction and Riat is part of Mau Summit-Busia Road Project. The section falls within the ongoing rehabilitation of Kisumu-Kakamega Road which includes dualling of the Mamboleo-Kiboswa section of the road.
view
-
6 Aug 2014 in National Assembly:
Thank you, hon. Temporary Deputy Speaker.
view
-
6 Aug 2014 in National Assembly:
Hon. Temporary Deputy Speaker, it is true that we promised the hon. Member for the area that something would be done on this section within a short period. I want to confirm that we have already started awarding a tender. I wish he could visit the site next week and see whether there is a contractor on the ground.
view
-
6 Aug 2014 in National Assembly:
On hon. Limo’s clarification, this is a road that covers 25 kilometres within Kisumu Town. This is a World Bank project. The World Bank has blacklisted the contractor for the last one year. That is where we have been having a problem. This road is 25 kilometres long. They have done 20 kilometres but the five kilometres that the Member is complaining about is the portion that the Ministry has decided to give to another contractor. So, the slow pace of work is as a result of the contractor; since he is a foreign contractor the World Bank does not ...
view
-
6 Aug 2014 in National Assembly:
Hon. Temporary Deputy Speaker, on hon. Wandayi’s question, it is true that this is a very important road. The Ministry has taken that route of giving it to another The electronic version of the Official Hansard Report is for information purposesonly. A certified version of this Report can be obtained from the Hansard Editor.
view