15 Aug 2012 in National Assembly:
Madam Temporary Deputy Speaker, I give a commitment that before Christmas, our Ministry will commission the Chemususu Dam.
view
15 Aug 2012 in National Assembly:
Madam Temporary Deputy Speaker, variations, as far as dam costs are concerned, only come when there are added costs. In this case, as far as Chemususu Dam is concerned, there were no added costs. They were only inconveniences. As far as Badassa is concerned, there was added work because of the grouting. As a result, there was an allowance for variation. Regarding Umma Dam, I have stated clearly that there were complications and dispute between the contractor and the client. We had given enough allowance for the variation.
view
15 Aug 2012 in National Assembly:
Madam Temporary Deputy Speaker, that is a different Question. Otherwise, as I have stated here, Badasa Dam will be completed on time. We have clearly stated that by December this year, Badasa and Chemususu dams will be completed. We will also have completed the Kiserian Dam, which is filing with water right now. Therefore, I have no doubt that we are going to fulfill whatever the Ministry has promised.
view
15 Aug 2012 in National Assembly:
Madam Temporary Deputy Speaker, the construction of the dam was different from the pipelines. The only guarantee that I can give is for the dam. Otherwise, if the Member requires an answer for the pipeline, he can ask a Question and we are going to answer.
view
15 Aug 2012 in National Assembly:
Madam Temporary Deputy Speaker, we have given that allowance for the locals to benefit from the resources in their area. I am sure the residents of Mogotio will benefit from the water at Chemususu Dam.
view
15 Aug 2012 in National Assembly:
Madam Temporary Deputy Speaker, with regard to Umma Dam, I said that there is a dispute between the contractor and the client, namely, the National Water Conservation and Pipeline Corporation, at the High Court. The High Court has ordered arbitration to the dispute. Our Ministry has appealed to the Court of Appeal to restart the contract. Therefore, in Umma Dam, there was no issue of integrity as far as I am concerned.
view
15 Aug 2012 in National Assembly:
Madam Temporary Deputy Speaker, I have addressed the question asked. Part (b) of the Question was asking what action the Minister intends to take to ensure that the construction of Chemususu Dam is completed by August, 2012. The Member did not ask about the upper part of the construction. However, the whole contract is progressing according to the contract terms as I initially indicated. I have promised, and the Member knows, that the contract is going on. I have clearly indicated that we are going to complete the dam by December this year. If the Member needs more details, I ...
view
8 Aug 2012 in National Assembly:
Mr. Speaker, Sir, just give me a minute.
view
8 Aug 2012 in National Assembly:
Mr. Speaker, Sir, I seek your indulgence that you give me two minutes to organize myself.
view
8 Aug 2012 in National Assembly:
Mr. Speaker, Sir, I beg to reply.
view