Parties & Coalitions

Full name

Lee Maiyani Kinyanjui

Born

1976

Post

Parliament Buildings
Parliament Rd.
P.O Box 41842 – 00100
Nairobi, Kenya

Email

leekinyanjui@yahoo.com

Email

nakurutown@parliament.go.ke

Link

Facebook

Telephone

0722842653

Telephone

0722842653

All parliamentary appearances

Entries 871 to 880 of 1318.

  • 20 Jul 2010 in National Assembly: Mr. Deputy Speaker, Sir, I beg to reply. The Kshs12 million allocated to Kisii-Keroka Road for routine maintenance was not utilized since the road had deteriorated very fast and needed rehabilitation. In this connection, my Ministry has allocated funds for repair and rehabilitation of the mentioned section. I, therefore, confirm to the hon. Member of Parliament that we have already awarded the contract to H. Young and the works will commence in early August, 2010. view
  • 20 Jul 2010 in National Assembly: Mr. Deputy Speaker, Sir, as I have indicated, the contract was awarded to H. Young and we expect to commence works by early August and the latest will be around 7th August. So, essentially, we are talking about two weeks. In the meantime, we will try and mobilize our in-house equipment to ensure that the road is motorable in sections that are currently impassable. view
  • 20 Jul 2010 in National Assembly: Mr. Deputy Speaker, Sir, as I said, my Ministry has awarded a contract to H. Young for the construction of the Kisii-Keroka Road at a total sum of Kshs264 million. The contract begins early September this year 2010 for a contract period of 12 months and we expect the work to be completed by July, 2011. The scope of works includes the drainage works, repair of the base, AC premix and recarpeting and lastly, on-road furniture. view
  • 20 Jul 2010 in National Assembly: Mr. Deputy Speaker, Sir, I beg to reply. (a)Naro-Moru-BlueLine-Munyu-Katicheni-Warazo Jet-Kimahuri-Ndathi Road in Kieni East District and Kanyagia-Talai-Endarasha-Watuka-Bellevue-Githura-Nairutia Road in Kieni West District were not earmarked for construction in the financial year 2009/2010. However, a design for Naro-Moru-BlueLine-Munyu-Karicheni-Warazo Jet- Kimahuri-Ndathi Road in Kieni East District is currently undesigned and the designed work is expected to be completed by December 2010. The design work is given for a total sum of Kshs42,042,800.00. The Kanyagia-Talai-Endarasha-Watuka-Bellevue- Githura-Nairutia Road in Kieni West District will be considered for design subsequently. (b) I am aware that the bridge on Nairutia-Bellevue Road was washed away in April 2010. ... view
  • 20 Jul 2010 in National Assembly: Mr. Deputy Speaker, Sir, the hon. Member has asked three questions. The first one regards the design which will be completed by December 2010. Two, is to do with the other section of the road; how much has been allocated to it. I am afraid I do not have the exact figure but I undertake to give the hon. Member the figures for him to be able to follow up. Three, he has asked a question on the issue of the road that passes through the forest and whether the environmental concerns raised also affect the other road. My Ministry ... view
  • 20 Jul 2010 in National Assembly: Mr. Deputy Speaker, Sir, the first part of the hon. Member’s Question was with regard to Endarasha-Kamuhura-Bellevue. As I have indicated, it is not earmarked for upgrading to bitumen standard in this financial year. However, we will prioritize it in future. With regard to the issue of the road that passes through the Aberdare Forest, my Ministry recognizes the importance of reducing the distance between these two areas. However, as we think about that, we must take into account the environmental aspect. It is for that reason that my Ministry has consulted the relevant Ministries in terms of environmental concerns. ... view
  • 20 Jul 2010 in National Assembly: Allow me to say that the question by hon. Kiuna, much as it is not directly related to this Question, I will offer unsolicited Statement next week on Tuesday, so that we can allay the fears as have been expressed by the hon. Member. view
  • 14 Jul 2010 in National Assembly: Mr. Deputy Speaker, Sir, I beg to reply. (a) The construction of the Daraja Moja Bridge has not stalled. However, in the last few weeks, there was minimal work going on as the contractor awaited for permission from the relevant authorities to explode the hard materials. The contractor has already done so, and the works are ongoing and are indeed ahead of schedule. (b) As I stated above, the contractor has been on site and the construction works are ongoing. (c) I have instructed the contractor to constantly maintain the diversion. However, it should be noted that the use of ... view
  • 14 Jul 2010 in National Assembly: the bridge. For this reason, I appeal to members of the public to bear with us during this time of construction of the bridge. view
  • 14 Jul 2010 in National Assembly: Mr. Deputy Speaker, Sir, I wish to refer you to part of the contract between my Ministry and the contractor. The contract was awarded to Walukati Investment Limited, at a cost of Kshs72 million on 1st February, 2010. The date to commence works was given as 1st March, 2010. The actual expected date of completion will be on 28th March, 2011. Therefore, as per our contract, the contractor is on schedule and the works are going on, as I have already indicated. Parts of the works that had stalled a little bit were to do with excavations and the contractor ... view

Comments

(For newest comments first please choose 'Newest' from the 'Discussion' tab below.)
comments powered by Disqus